TeraWulf Announces November 2024 Production and Operations Update

TeraWulf Announces November 2024 Production and Operations Update

TeraWulf宣布2024年11月的生产和运营更新
TeraWulf ·  12/02 21:00

TeraWulf Announces November 2024 Production and Operations Update

TeraWulf宣布2024年11月的生产和运营更新

December 3, 2024 • 4:08 PM EST Download as PDF
2024年12月3日 • 下午4:08 ESt 下载为PDF

Completed critical electrical upgrades to support Lake Mariner HPC hosting and mining buildings

完成了关键电气升级以支持湖马里纳HPC托管和挖矿建筑

Remain on schedule to deliver 72.5 MW of HPC hosting capacity by the end of Q2 2025

按计划在2025年第二季度末交付72.5 MW的HPC托管能力

Successfully installed approximately 7,400 state-of-the-art S21 Pro miners

成功安装了约7400台最先进的S21 Pro矿机

Achieved 8.4 EH/s of operational self-mining capacity, a 68% year-over-year increase

实现了8.4 EH/s的运营自挖能力,同比增长68%

EASTON, Md., Dec. 03, 2024 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) ("TeraWulf" or the "Company"), a leading owner and operator of vertically integrated, next-generation digital infrastructure powered by predominantly zero-carbon energy, today provided its unaudited monthly production and operations update for November 2024.

2024年12月3日,马里兰州伊斯顿,世界环球新闻社报道--TeraWulf Inc.(纳斯达克股票代码:WULF)("TeraWulf"或"公司"),一家主要依靠零碳能源驱动的垂直一体化、下一代数字基础设施的领先业主和运营商,今天提供了其2024年11月份未经审计的生产和运营更新。

November 2024 Production and Operations Highlights

2024年11月生产和运营亮点

  • Bitcoin Production: Self-mined 115 bitcoin, with an average daily production rate of approximately 3.8 bitcoin.
  • Operating Capacity: Maintained 8.4 EH/s of operational self-mining capacity, a 68.0% year-over-year increase.
  • Power Costs: Achieved an average power cost of $41,190 per bitcoin mined, equivalent to approximately $0.051/kWh, excluding proceeds from demand response and ancillary services.
  • Miner Upgrades: Advanced the miner refresh program at Lake Mariner, replacing legacy S19 Pro/J-Pro and M30s+ models with approximately 7,400 S21 Pro miners.
  • Electrical Upgrades: Completed a planned outage to connect high-voltage redundant power feeds, temporarily affecting approximately 5.3 EH/s of miners.
  • 比特币生产:自挖115个比特币,平均每日生产率约为3.8个比特币。
  • 运营容量:保持8.4 EH/s的自挖运作能力,同比增长68.0%。
  • 电力成本:每个比特币矿产的平均电力成本为41,190美元,相当于约0.051美元/kWh,不包括需求响应和辅助服务的收益。
  • 矿工升级:推进Lake Mariner的矿工更新计划,使用约7,400个S21 Pro矿工替代旧款S19 Pro/J-Pro和M30s+型号。
  • 电气升级:完成了计划中的停电,以连接高压冗余电源,暂时影响约5.3 EH/s的矿工。
Key Metrics1 November 2024
October 2024
Bitcoin Self-Mined 115 150
Value per Bitcoin Self-Mined2 $ 83,947 $ 65,427
Power Cost per Bitcoin Self-Mined $ 41,190 $ 36,789
Avg. Operating Hash Rate (EH/s)3 5.9 6.8
Nameplate Miner Efficiency (J/TH)4 19.2 22.0
关键指标1 2024年11月
2024年10月
比特币自挖 115 150
每枚自我挖掘的比特币价值2 $ 83,947 $ 65,427
每枚自我挖掘的比特币的功率成本 $ 41,190 $ 36,789
平均运营算力(EH/s)3 5.9 6.8
额定矿机效率(J/TH)4 19.2 22.0

_______________
1 All figures except Bitcoin Self-Mined are estimates and remain subject to standard month-end adjustments.
2 Computed as the weighted-average opening price of bitcoin on each respective day the Bitcoin Self-Mined is earned.
3 While nameplate mining inventory as of November 30, 2024 for Lake Mariner is estimated at 9.7 EH/s, actual monthly hash rate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair. Performance in November was impacted by planned outage for electrical upgrades and miner fleet upgrade work. Performance in October was impacted by miner fleet upgrade work.
4 Nameplate miner efficiency excludes auxiliary load.

_______________
除比特币自挖外的所有数字均为估算值,并仍然需遵循标准的月末调整。
2、根据获得的比特币自我挖掘日期计算加权平均开盘价。
截至2024年11月30日,Lake Mariner的命名矿井库存估计为9.7 EH/s,但实际的每月哈希率表现取决于多种因素,包括(但不限于)为了提高效率和最大化利润而进行的性能调整、计划停机(用于提高可靠性或性能的范围)、非计划停机、因参与各种现金产生的需求响应程序而造成的削减、由于不良天气和ASIC的维护和修理而导致的性能下降。11月的表现受到电力升级和矿工设备升级工作的计划停机影响。10月的表现则受到了矿工设备升级工作的影响。
4、额定矿工的效率不包括辅助负载。

Management Commentary

管理层评论

Sean Farrell, Chief Operating Officer of TeraWulf remarked, "November marked a pivotal month for Lake Mariner as we completed significant upgrades to our electrical infrastructure. These enhancements will ensure reliable and redundant power delivery to CB-1, CB-2, and future HPC hosting loads, positioning us to meet the increasing demand for Tier 3 HPC infrastructure."

TeraWulf首席运营官Sean Farrell表示:“11月对于湖泊马里纳来说是一个关键的月份,我们完成了电力基础设施的重要升级。这些增强措施将确保对Cb-1、Cb-2以及未来HPC承载负载提供可靠和冗余的电力,帮助我们满足对Tier 3 HPC基础设施日益增长的需求。”

Farrell added, "Despite a brief planned outage, we mined 115 bitcoin with an average daily production rate of nearly four bitcoin. Our miner refresh program has substantially improved efficiency, achieving a weighted average of approximately 19 J/TH. Additionally, our onsite repair teams are on track to restore 1.3 EH/s of mining equipment under warranty by year-end. Construction of MB-5 is proceeding on schedule, with conduit installation complete and foundation pours and structural steel assembly underway."

Farrell补充道:“尽管经历了短暂的计划停机,但我们挖掘了115个比特币,平均每日生产率接近四个比特币。我们的矿工更新计划显著提高了效率,达到了约19 J/TH的加权平均水平。此外,我们的现场维修团队正按计划在年底前恢复1.3 EH/s的保修挖矿设备。Mb-5的施工按计划进行,管道安装已完成,基础浇筑和结构钢铁组装正在进行中。”

Production and Operations Update

生产和运营更新

TeraWulf's commitment to operational excellence and sustainability continues to drive its growth across the Company's bitcoin mining and HPC hosting businesses.

TeraWulf对运营卓越和可持续发展的承诺继续推动其在公司比特币挖矿和HPC托管业务中的增长。

As of November 30, 2024, TeraWulf's operational bitcoin mining capacity was 195 MW at the Lake Mariner facility. Upon completing miner repairs, fleet upgrades and onboarding new miners, TeraWulf's self-mining hash rate is expected to reach approximately 9.7 EH/s. November's average hash rate was 5.9 EH/s, factoring in planned outage for electrical upgrades, demand response events and optimization strategies to maximize profitability.

截至2024年11月30日,TeraWulf在Lake Mariner设施的运营比特币挖矿能力为195 MW。在完成矿机维修、机队升级和新矿工入驻后,TeraWulf的自矿哈希率预计将达到约9.7 EH/s。11月份的平均哈希率为5.9 EH/s,考虑到电气升级的计划停机、需求响应事件和优化策略以最大化盈利能力。

On the WULF Compute front, progress continues on large-scale HPC hosting infrastructure at Lake Mariner. Dry cooler installation is complete for the 20 MW CB-1 facility, which is on track for Q1 2025 completion. We remain on schedule to deliver 72.5 MW of HPC hosting capacity by the end of Q2 2025.

在WULF计算方面,Lake Mariner的大规模HPC托管基础设施的进展持续进行。20 MW的Cb-1设施的干冷却器安装已完成,预计将在2025年第一季度完成。我们仍按计划在2025年第二季度末交付72.5 MW的HPC托管能力。

About TeraWulf

关于TeraWulf

TeraWulf develops, owns, and operates environmentally sustainable, next-generation data center infrastructure in the United States, specifically designed for Bitcoin mining and high-performance computing. Led by a team of seasoned energy entrepreneurs, the Company owns and operates the Lake Mariner facility situated on the expansive site of a now retired coal plant in Western New York. Currently, TeraWulf generates revenue primarily through Bitcoin mining, leveraging predominantly zero-carbon energy sources, including hydroelectric and nuclear power. Committed to environmental, social, and governance (ESG) principles that align with its business objectives, TeraWulf aims to deliver industry-leading economics in mining and data center operations at an industrial scale.

TeraWulf在美国开发、拥有并运营环境可持续的新一代数据中心基础设施,专为比特币挖掘和高性能计算而设计。由经验丰富的能源企业家领导,公司拥有并运营位于纽约西部一座现已退役煤电厂宽敞用地上的Lake Mariner设施。目前,TeraWulf主要通过比特币挖掘实现收入,主要利用水力发电和核电等几乎零碳能源。致力于与业务目标一致的环境、社会和治理(ESG)原则,TeraWulf旨在以工业规模交付挖矿和数据中心运营的业内领先经济效益。

Forward-Looking Statements

前瞻性声明

This press release contains forward-looking statements within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as "plan," "believe," "goal," "target," "aim," "expect," "anticipate," "intend," "outlook," "estimate," "forecast," "project," "continue," "could," "may," "might," "possible," "potential," "predict," "should," "would" and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf's management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) conditions in the cryptocurrency mining industry, including fluctuation in the market pricing of bitcoin and other cryptocurrencies, and the economics of cryptocurrency mining, including as to variables or factors affecting the cost, efficiency and profitability of cryptocurrency mining; (2) competition among the various providers of cryptocurrency mining services; (3) changes in applicable laws, regulations and/or permits affecting TeraWulf's operations or the industries in which it operates, including regulation regarding power generation, cryptocurrency usage and/or cryptocurrency mining, and/or regulation regarding safety, health, environmental and other matters, which could require significant expenditures; (4) the ability to implement certain business objectives and to timely and cost-effectively execute integrated projects; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to growth strategies or operations; (6) loss of public confidence in bitcoin or other cryptocurrencies and the potential for cryptocurrency market manipulation; (7) adverse geopolitical or economic conditions, including a high inflationary environment; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability, delivery schedule and cost of equipment necessary to maintain and grow the business and operations of TeraWulf, including mining equipment and infrastructure equipment meeting the technical or other specifications required to achieve its growth strategy; (10) employment workforce factors, including the loss of key employees; (11) litigation relating to TeraWulf and/or its business; and (12) other risks and uncertainties detailed from time to time in the Company's filings with the Securities and Exchange Commission ("SEC"). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company's filings with the SEC, which are available at www.sec.gov.

本新闻稿包含根据1995年修正版《私人证券诉讼改革法》中的“安全港”条款做出的前瞻性声明。这些前瞻性声明涉及预期的未来事件和预期,而不是历史事实。除历史事实外,所有声明都可以被视为前瞻性声明。此外,尽管没有这些词或表达,但通常可以用诸如“计划”、“相信”、“目标”、“目标”、“目标”、“期望”、“预计”、“有利前景”、“估计”、 “预测”、“项目”、“继续”、“可能”、“可能”、“潜在”、“预测”、“应该”、“将”和其他类似的词汇和表达来识别前瞻性声明,尽管缺乏这些词或表达并不意味着一份声明不是前瞻性的。前瞻性声明基于TeraWulf管理层的当前期望和信念,并天生受到一系列因素、风险、不确定性和假设及其潜在影响的影响。不能保证未来的发展将是预期的发展。由于风险、不确定性和假设的事实、风险、不确定性和假设可能导致实际结果与前瞻性声明中表述的结果有根本不同,这些前瞻性声明可能会根据多种因素(但不限于此)产生的实际月度哈希率表现,包括(但不限于)性能调整以提高效率和最大化利润的计划外停机范围工程,计划之外的停机,参与各种产生现金的需求响应项目和当地政策等影响成本、效率和利润的因素或变量。各种加密货币开采服务提供商之间的竞争,适用法律、法规和/或许可证的变化涉及TeraWulf的业务或其所处行业的法规,包括有关发电、加密货币使用和/或加密货币开采的法规,以及有关安全、健康、环境和其他事项的法规,这可能需要支付巨额支出;实施某些业务目标并实时、具有成本效益地执行综合项目的能力;未能及时且符合增长战略或运营要求的可接受条款融资;公众对比特币或其他加密货币的信心的丧失,以及加密货币市场操纵的可能性;不利的地缘政治或经济状况,包括高通胀环境;网络犯罪、洗钱、恶意软件感染和网络钓鱼等风险,以及由于设备故障或损坏、物理灾害、数据安全漏洞、计算机故障或破坏导致的损失和干扰以及与此类事件相关的成本;支持公司业务和运营所需的设备的可用性、交付计划和成本,包括符合实现其增长战略所需的技术或其他规格要求的开采设备和基础设施设备;员工的雇用工作力因素,包括关键员工的流失;与TeraWulf和/或其业务有关的诉讼;以及其他风险和不确定性,这些风险和不确定性会随时因不同时间或未来企业或经济状况的变化而发生变化。潜在投资者、股东和其他读者被警告不要将太多信任寄托在这些前瞻性声明上,这些前瞻性声明仅在其做出时发挥作用,除非依法或依法规定,否则TeraWulf不承担公开更新前瞻性声明的任何义务。参与者将被指引到关于前瞻性声明的风险和不确定性的全面讨论,以及公司在美国证券交易委员会(“SEC”)的文件中包含的风险因素的讨论,在www.sec.gov。

Investors:
Investors@terawulf.com

投资者:
Investors@terawulf.com

Media:
media@terawulf.com

媒体:
media@terawulf.com


big

Source: TeraWulf Inc.
来源:TeraWulf Inc。

Released December 3, 2024

发布于2024年12月3日