Yinson's Peru Solar Plant Goes Into Action

Yinson's Peru Solar Plant Goes Into Action

Yinson的秘魯太陽能電廠投入運營
Business Today ·  09/24 13:11

Yinson informs that its Matarani Solar Plant in Peru recently entered into its full operational phase, following the commencement of power export and sales in July 2024. The 97 MWp plant, located near Arequipa, positions Yinson Renewables as Peru's second largest solar generator and is its first operational project in Peru.

Yinson表示,繼2024年7月開始電力出口和銷售之後,其位於秘魯的馬塔拉尼太陽能發電廠最近進入全面運營階段。這座97兆瓦的發電廠位於阿雷基帕附近,使Yinson Renewables成爲秘魯第二大太陽能發電機,也是其在秘魯的第一個運營項目。

The plant, which commenced operations ahead of schedule, is designed to deliver 260 GWh of renewable energy annually and is estimated to be able to satisfy the electricity needs of approximately 62,000 Peruvian households and prevent the emission of more than 56,000 tonnes of CO2 per year. The plant includes almost 150,000 panels covering an area of 750,000m2
.
The Matarani Solar Plant has a long-term Power Purchase Agreement (PPA) with Orygen, Peru's leading renewable energy generator, whose majority shareholder is the global sustainable infrastructure investment fund, Actis.
Yinson Renewables acquired the project from Grenergy Renewables in January 2024. Grenergy provided a full turnkey EPC contract for the construction of the project and is also providing operation and maintenance service for the first two years.Yinson Renewables has a strong growth ambition in Latin America, with a pipeline of close to 1 GW
expected to be built in the next three to five years.

該發電廠提前開始運營,設計每年提供260吉瓦時的可再生能源,估計能夠滿足約62,000個秘魯家庭的電力需求,每年可防止超過56,000噸二氧化碳的排放。該工廠包括近 150,000 塊面板,佔地 750,000 平方米

馬塔拉尼太陽能發電廠與秘魯領先的可再生能源發電商Orygen簽訂了長期電力購買協議(PPA),其大股東是全球可持續基礎設施投資基金Actis。
Yinson Renewables 於 2024 年 1 月從格林納基可再生能源公司手中收購了該項目。Grenergy爲該項目的建設提供了完整的交鑰匙EPC合同,並且還提供前兩年的運營和維護服務。Yinson Renewables在拉丁美洲有着強勁的增長目標,其管道容量接近1吉瓦
預計將在未來三到五年內建成。

In Peru, Yinson Renewables also owns the 130 MWp Majes Project, the first phase of which is expected to be ready for construction by end 2024. Matarani is Yinson Renewables' fourth large scale project to reach commercial operations, with the
first three being the Rising Bhadla 1 & 2 plants and the Nokh Solar plant in India.

在秘魯,Yinson Renewables還擁有130兆瓦的Majes項目,該項目的第一階段預計將於2024年底準備就緒,可以開始施工。Matarani是Yinson Renewables第四個實現商業運營的大型項目,
前三個是印度的Rising Bhadla 1和2發電廠以及Nokh Solar發電廠。