  • Following a successful delineation drilling program since the last resource update on August 12, 2022, a new S-K 1300 technical report summary (the "TRS") increases the Burke Hollow Project's Measured and Indicated ("M&I") resources from 2,324,000 lbs U3O8 to 6,155,000 lbs and Inferred resources of 4,883,000 lbs U3O8..
  • The Burke Hollow in-situ recovery ("ISR") Project continues to expand with three Production Areas defined to date, and ongoing exploration and delineation drilling along mineralized trends for additional resource growth.
  • Total Texas Hub and Spoke platform's disclosed M&I resources are now 12,958,000 lbs, with 7,241,000 tons grading approximately 0.085% U3O8, and Inferred resources are now 9,948,100 lbs, with 4,356,000 tons grading approximately 0.120% U3O8.
  • This latest S-K 1300 TRS reconfirms UEC's position as America's leading ISR uranium company with its South Texas and Wyoming Hub & Spoke platforms having 79,156,000 lbs U3O8 of M&I resources and 25,002,000 lbs of Inferred resources.
  • 在2022年8月12日的上一個資源更新以來,經過成功的界定鑽探計劃,新S-K 1300技術報告摘要(“TRS”)將伯克洞項目的測量和指示(“M&I”)資源從2,324,000磅U3O8增加到6,155,000磅,推論資源爲4,883,000磅U3O8。
  • 伯克洞原地回收(“ISR”)項目不斷擴大,並已確定了三個生產區域,同時沿着礦化趨勢進行進一步的資源增長的探勘和界定鑽探。
  • 總的來說,德克薩斯中心與輻射平台的公開披露的M&I資源現在爲12,958,000磅,約0.085%U3O8的7,241,000噸,推論資源現在爲9,948,100磅,約0.120%U3O8的4,356,000噸。
  • 這份最新的S-K 1300 TRS重新確認了UEC作爲美國ISR鈾公司的地位,其南德克薩斯和懷俄明中心和輻射平台擁有79,156,000磅U3O8的M&I資源和25,002,000磅的推論資源。

CORPUS CHRISTI, Texas, June 13, 2024 /CNW/ - Uranium Energy Corp (NYSE:UEC) "UEC" or the "Company") is pleased to announce that it has filed a TRS on EDGAR disclosing updated mineral resources for the Company's Texas Hub and Spoke ISR platform (the "Platform") with an increase in resources at the Burke Hollow Project (the "Project").

德克薩斯州科珀斯克里斯蒂,2024年6月13日/CNW/ - 鈾能源公司(NYSE:UEC)“UEC”或“公司”)很高興宣佈,它已經在EDGAR上提交了關於其Texas Hub and Spoke ISR平台(“平台”)的礦物資源的更新TR的披露,伯克洞項目(“項目”)的資源也得到了增加。

Background:

背景:

  • As a U.S. domestic and domiciled company, UEC is now reporting all mineral resources in accordance with Item 1302 of Regulation S-K ("S-K 1300");
  • S-K 1300 was adopted by the Securities and Exchange Commission ("SEC") to modernize mineral property disclosure requirements for mining registrants and to align U.S. disclosure requirements more closely for mineral properties with current industry and global regulatory standards;
  • The mineral resource estimates set forth in this TRS are an update to previously reported Project resources under the S-K 1300 format; and
  • The Project geology is considered amenable to low-cost, environmentally friendly ISR mining methods.
  • 作爲美國國內成立的公司,UEC現在根據《S-K規則》1302條款(“S-K 1300”)報告所有礦產資源;
  • S-K 1300是美國證監會(“SEC”)採用的,旨在現代化礦業登記申請者的礦業財產披露要求,並更加緊密地將礦業財產的美國披露要求與當前的行業和全球監管標準相一致;
  • 該TRS中的礦產資源估算更新了以前根據S-K 1300格式報告的項目資源;並且
  • 項目地質被認爲是適合低成本,環境友好的ISR採礦方法的。

The TRS was prepared under S-K 1300 and was filed on June 12, 2024 with the SEC through EDGAR on Form 8-K and is also available on SEDAR as a "Material Document" filed on June 12, 2024. The TRS was prepared on behalf of the Company by Western Water Consultants, Inc. d/b/a WWC Engineering, of Sheridan, Wyoming.

TRS是根據S-K 1300準備的,於2024年6月12日提交給SEC,通過EDGAR的8-K表格進行了披露,並作爲在2024年6月12日提交的“重要文件”在SEDAR上可用。TRS是代表公司由位於懷俄明州謝里登的Western Water Consultants Inc. d/b/a WWC Engineering準備的。