VANCOUVER, British Columbia, May 14, 2024 (GLOBE NEWSWIRE) -- Calibre Mining Corp. (TSX: CXB; OTCQX: CXBMF) ("Calibre" or the "Company") is pleased to announce a construction and capital cost update on the Valentine Gold Mine ("Valentine" or "VGM"), located in the central region of Newfoundland & Labrador, Canada. All figures in Canadian Dollars ("C$") unless otherwise stated.
Darren Hall, President and Chief Executive Officer of Calibre, stated: "I am pleased to announce that construction of our fully funded Valentine Gold Mine is 64% complete and we have progressed detailed engineering to 98% from 60%, with the later having formed the basis of the previously disclosed Marathon Gold capital estimates. With the first gold pour scheduled in Q2 2025, the delivery of Valentine is a paradigm shift for Calibre as we transition to a quality mid-tier gold producer unlocking significant value for all stakeholders.
Since acquiring Valentine in January 2024 we have re-baselined the project schedule, significantly progressed detailed engineering, awarded all major contracts, connected site to permanent power, delivered critical path items including mills and motors, employed the operations leadership team, and commenced pre-commissioning and commissioning activities.
Our project optimization and derisking efforts, combined with accelerating a portion of Phase 2 expansion capital, results in an initial capital cost of C$653 million, a C$145 million increase over Marathon Gold's Q3 2023 update. With a C$279 million cost to complete as of April 30, 2024 and approximately C$400 million of cash and restricted cash, we are fully funded. In addition, the Company has substantial cash flows from operations.
I am confident the Valentine gold property has district-scale potential, and we anticipate accelerating our exploration efforts in the near term. The Valentine Gold Mine and surrounding property offers a robust resource base and significant discovery opportunities with an extremely prospective array of exploration targets with similar geology to the prolific Val-d'Or and Timmins camps in the Abitibi gold belt."
Initial Capital Cost Update
First gold production scheduled for Q2 2025;
Updated initial capital cost estimate of C$653 million, an increase of C$145 million versus last reported C$508 million by Marathon Gold Corporation ("Marathon") in Q3 2023;
The updated estimate is consistent with Calibre's pre-acquisition due diligence and consists of three primary components:
Marathon's Schedule and Cost Underestimation of C$70 million;
Calibre's Project Optimization & Derisking of C$40 million; and
Calibre Advancing Operations & Phase 2 Expansion Capital of C$35 million
With a C$279 million cost to complete as of April 30, 2024 and approximately C$400 million of cash and restricted cash, we are fully funded. In addition, the company has substantial cash flows from operations.
Construction and Operational Readiness Highlights
Overall construction progress 64% complete;
Detailed engineering progressed to 98%;
Tailings Management Facility starter dam embankment complete and approved by the Engineer of Record and liner placement has commenced;
Critical path items, including mills and motors, delivered to Newfoundland;
Site connected to permanent hydroelectric power;
Mill building enclosed;
Structural Mechanical Piping ("SMP") and Electrical and Instrumentation ("E&I") contracts awarded;
Pre-commissioning and commissioning contract awarded; and
Operations leadership team employed.
Exploration Highlights
50,000 metre RC drilling completed at Leprechaun pit and underway at the Marathon pit;
Diamond drilling recently completed at the Leprechaun SW discovery (see news release dated April 3, 2024);
Significant district scale exploration potential across 64 km shear zones;
Target delineation drilling across the shear zones commencing this summer;
Exceptional exploration potential over the 250 km2 property with similar geology to the prolific Val-d'Or and Timmins camps in the Abitibi gold belt; and
Strong potential down plunge of existing open pits demonstrates an additional underground mining opportunity outside of the current open pit mine plan.
Marathon Initial Capital Cost Estimate History
Updated Feasibility Study (1) | C$463 million | |
Q2 2023 Construction Report (2) | C$504 million | |
Q3 2023 Construction Report (3) | C$508 million | |
Calibre Initial Capital Cost Estimate
May 14, 2024 Initial Capital Cost | C$653 million | Overall project completion at 64% Detailed engineering at 98% C$374 million spent as of April 30, 2024 C$279 million cost to complete Fully funded with ~C$400 million in cash, and restricted cash First gold Q2 2025
|
C$145 million increase vs Marathon's Q3 2023 estimate due to:
Marathon's Schedule and Cost Underestimation | C$70 million | First gold shift to Q2 2025 Labour costs due to the schedule extension Engineering progressed from 60% to 98% Scope definition increases to major contracts including the SMP and E&I Increased volumes of concrete, steel, etc
Inflationary pressures on consumables Increased camp services and related costs
|
Calibre's Project Optimization and Derisking | C$40 million | Pre commissioning & commissioning contract awarded, and activities commenced Site access upgrade and maintenance Process plant & site infrastructure modifications Employed the operations leadership team
|
Calibre Advancing Operations and Phase 2 Expansion Capital | C$35 million | Advanced Phase 2 CIL & cyanide destruct tanks in preparation of the increase from 2.5 to 4.0Mtpa Advanced process plant effluent treatment plant Advanced permanent mobile equipment maintenance and associated facilities Accommodation upgrades; including air conditioning and telecommunications Advanced critical spares
|
Calibre will also increase working capital over the next 12 months to materially de-risk the execution of the production ramp-up. Areas of focus for working capital include:
Qualified Person
Mr. Paolo Toscano, P. Eng (Ont.), SVP Engineering, Projects and Construction, is a "qualified person" as set out under NI 43-101 and has reviewed and approved the scientific and technical information in this press release.
不列顛哥倫比亞省溫哥華,2024年5月14日(環球新聞專線)——Calibre Mining Corp.(多倫多證券交易所股票代碼:CXB;OTCQX:CXBMF)(“Calibre” 或 “公司”)欣然宣佈位於加拿大紐芬蘭和拉布拉多中部的瓦倫丁金礦(“瓦倫丁” 或 “VGM”)的施工和資本成本最新情況。除非另有說明,否則所有數字均以加元(“C$”)爲單位。
Calibre總裁兼首席執行官達倫·霍爾表示:“我很高興地宣佈,我們資金充足的情人節金礦的建設已完成64%,我們已將詳細工程從60%進展到98%,後者構成了先前披露的Marathon Gold資本估算的基礎。隨着計劃於2025年第二季度進行首次淘金,Valentine的交付對Calibre來說是一種模式轉變,因爲我們正在向高質量的中端黃金生產商過渡,爲所有利益相關者帶來巨大價值。
自2024年1月收購Valentine以來,我們重新確定了項目進度表,在詳細工程方面取得了重大進展,授予了所有主要合同,將場地連接到永久電力,交付了包括磨機和電機在內的關鍵路徑項目,聘用了運營領導團隊,並開始了預調試和調試活動。
我們的項目優化和風險消除工作,加上加快第二階段部分擴張資本,初始資本成本爲6.53億加元,比Marathon Gold的2023年第三季度更新增加了1.45億加元。截至2024年4月30日,我們的竣工成本爲2.79億加元,還有約4億加元的現金和限制性現金,資金充足。此外,公司擁有大量的運營現金流。
我相信瓦倫丁黃金地產具有區域規模的潛力,我們預計在短期內將加快勘探工作。瓦倫丁金礦及周邊地產提供了強大的資源基礎和重要的發現機會,其勘探目標極具前景,其地質與阿比提比金帶多產的瓦勒多爾和蒂明斯營地相似。”
初始資本成本更新
計劃於2025年第二季度首次生產黃金;
更新的初始資本成本估計爲6.53億加元,與馬拉松黃金公司(“馬拉松”)在2023年第三季度上次報告的5.08億加元相比,增加了1.45億加元;
最新的估計與Calibre的收購前盡職調查一致,包括三個主要組成部分:
馬拉松的賽程安排和成本低估了7,000萬加元;
Calibre 的 4,000 萬加元項目優化和風險防控;以及
Calibre 推進運營和第 2 階段擴張資本 3,500 萬加元
截至2024年4月30日,我們的竣工成本爲2.79億加元,還有約4億加元的現金和限制性現金,資金充足。此外,該公司擁有大量的運營現金流。
施工和運營準備要點
探索亮點
在 Leprechaun 礦坑完成了 50,000 米的 RC 鑽探,並正在馬拉松礦坑進行中;
最近在 Leprechaun SW 發現區完成了鑽石鑽探(見 2024 年 4 月 3 日的新聞稿);
在 64 千米的剪切帶上具有巨大的區域規模勘探潛力;
從今年夏天開始在剪切帶進行目標劃界鑽探;
這座佔地250平方公里的土地具有非凡的勘探潛力,其地質與阿比提比金帶多產的瓦勒多爾和蒂明斯營地相似;以及
現有露天礦坑向下傾斜的巨大潛力表明,除了目前的露天採礦計劃之外,還有更多的地下采礦機會。
馬拉松初始資本成本估算曆史
更新的可行性研究 (1) | 463 加元 百萬 | |
2023 年第二季度施工報告 (2) | 504 加元 百萬 | |
2023 年第三季度施工報告 (3) | 508 加元 百萬 | |
Calibre 初始資本成本估算
2024 年 5 月 14 日初始資本成本 | 653 加元 百萬 | |
與 Marathon 2023 年第三季度的估計相比,增加了 1.45 億加元,原因是:
馬拉松的日程安排和成本低估 | 70 加元 百萬 | 黃金首次轉移到2025年第二季度 時間表延期導致的人工成本 工程從 60% 進展到 98% 範圍定義擴大到包括SMP和E&I在內的主要合同 增加混凝土、鋼材等的體積
消耗品面臨的通貨膨脹壓力 營地服務和相關費用增加
|
Calibre 的項目優化和風險防控 | 40 加元 百萬 | 授予了預調試和調試合同,活動開始了 站點訪問升級和維護 加工廠和場地基礎設施改造 僱用了運營領導團隊
|
Calibre 推進運營和第二階段擴張資本 | 35 加元 百萬 | |
Calibre還將在未來12個月內增加營運資金,以實質性地降低執行增產的風險。營運資金的重點領域包括:
合格人員
Paolo Toscano先生,P.Eng(安大略省),工程、項目和施工高級副總裁,是NI 43-101規定的 “合格人士”,他已經審查並批准了本新聞稿中的科學和技術信息。