Calgary, Alberta--(Newsfile Corp. - March 27, 2024) - Copper Fox Metals Inc. (TSXV: CUU) (OTCQX: CPFXF) (FSE: HPU) ('Copper Fox' or the 'Company') through its wholly owned subsidiary Desert Fox Copper Inc., is pleased to provide an update on its 100% owned Van Dyke in-situ copper recovery ('ISCR') project located in the Globe-Miami Mining District, Gila County, Arizona.

艾伯塔省卡爾加里--(Newsfile Corp.-2024 年 3 月 27 日)- Copper Fox Metals Inc.(多倫多證券交易所股票代碼:CUU)(場外交易所代碼:CPFXF)(FSE:HPU)(“Copper Fox” 或 “公司”) 通過其全資子公司 沙漠福克斯銅業公司 很高興提供其位於亞利桑那州吉拉縣環球邁阿密礦區的全資擁有的Van Dyke現場銅回收(“ISCR”)項目的最新情況。

The drillhole rehabilitation program focused on assessing the potential of rehabilitating historical drillholes for use as hydrogeological monitoring and water sampling stations. Of the drillholes selected for completion, due to downhole difficulties encountered, only one of three drillholes were successfully completed.

鑽孔修復計劃的重點是評估修復歷史鑽孔以用作水文地質監測和水採樣站的可能性。在選定完井的鑽孔中,由於遇到井下困難,三個鑽孔中只有一個成功完成。

The current geotechnical work is focused on collecting additional data on the Gila Conglomerate to support an updated mine plan to access the Van Dyke deposit. Highlights of activities completed are:

當前的岩土工程工作側重於收集有關吉拉集團的更多數據,以支持更新的礦山計劃,以開採範戴克礦牀。已完成活動的亮點有:

Highlights

亮點

  • Installation of the vibrating wire piezometers ('VWP's') and data recorder in drillhole M-3 has been completed and daily recording of hydrogeological data from this monitoring station commenced in mid-March. Four stations are now recording hydrogeological data.
  • Analysis of the formational waters from the Gila Conglomerate collected during the drillhole rehabilitation program returned concentrations of metals, anions, and cations well below acceptable limits established by the Environmental Protection Agency ('EPA').
  • Laboratory strength testing of samples of the Gila Conglomerate is nearing completion with preliminary results expected mid-April.
  • Chemical analyses of the pregnant leach solution ('PLS') from the mineralogical and solubility testwork completed in late 2023 and early 2024 is planned.
  • 振動線壓電計(“VWP”)和數據記錄器在鑽孔M-3中的安裝已經完成,該監測站的每日水文地質數據的記錄已於3月中旬開始。現在有四個監測站正在記錄水文地質數據。
  • 對鑽孔修復計劃期間收集的吉拉集團地層水的分析顯示,金屬、陰離子和陽離子的濃度遠低於環境保護署(“EPA”)規定的可接受限值。
  • 對吉拉集團樣本的實驗室強度測試已接近完成,初步結果預計將於4月中旬公佈。
  • 計劃對2023年底和2024年初完成的礦物學和溶解度測試工作中的孕浸溶液(“PLS”)進行化學分析。

Elmer B. Stewart, President and CEO of Copper Fox, stated, "Initiation of the collection of hydrogeological and water quality data is a significant step in advancing the Van Dyke project. The new hydrogeological data will augment the historical hydrogeological database and will be used to prepare an updated hydrogeological model for the Van Dyke project; a critical step in advancing the project to the permitting stage."

Copper Fox總裁兼首席執行官埃爾默·斯圖爾特表示:“開始收集水文地質和水質數據是推進範戴克項目的重要一步。新的水文地質數據將增強歷史水文地質數據庫,並將用於爲範戴克項目準備更新的水文地質模型;這是將該項目推進到許可階段的關鍵一步。”

Drillhole Rehabilitation
A significant component of advancing an ISCR project in Arizona to the permitting stage is the preparation of a robust hydrogeological model for review by the United States Environmental Protection Agency ('USEPA') and Arizona state regulatory authorities. With the completion of drillhole M-3, four hydrogeological monitoring stations are recording data daily.

鑽孔修復
將亞利桑那州ISCR項目推進到許可階段的一個重要組成部分是準備一個強大的水文地質模型,供美國環境保護署(“USEPA”)和亞利桑那州監管機構審查。隨着鑽孔M-3的完工,四個水文地質監測站每天都在記錄數據。

Geotechnical Program
Development of the Van Dyke oxide copper deposit contemplates driving a decline in the Gila Conglomerate to a level approximately fifty meters above the Gila/Leach Cap contact. The geotechnical study is being completed to obtain a better understanding of the geotechnical properties of the Gila Conglomerate that could impact the proposed decline. The drill core logging and sample selection portion of the geotechnical program has been completed and laboratory testing of the samples collected is nearing completion. The data from this study will be used to determine if changes to the mine plan contemplated in the 2020 Preliminary Economic Assessment ('PEA') are required. The geotechnical program also includes a data gap evaluation for the available geotechnical data. A hydrogeological data review from the Van Dyke project is also planned to determine if additional data would be needed to support a prefeasibility level study.

岩土工程項目
Van Dyke氧化銅礦牀的開發考慮將Gila集團的下跌推向比Gila/Leach Cap接觸點高出約五十米的水平。岩土工程研究正在完成之中,目的是更好地了解吉拉集團的岩土工程特性,這可能會影響擬議的衰退。岩土工程計劃的鑽芯測井和樣本選擇部分已經完成,對採集樣本的實驗室測試已接近完成。這項研究的數據將用於確定是否需要修改2020年初步經濟評估(“PEA”)中設想的採礦計劃。岩土工程項目還包括對現有岩土工程數據進行數據差距評估。還計劃對範戴克項目的水文地質數據進行審查,以確定是否需要更多數據來支持預可行性水平的研究。

Water Quality
During the drillhole rehabilitation program, samples of the formational water of the Gila Conglomerate from five drillholes were collected and analyzed for alkalinity, anions, cations, and metal concentrations. The alkalinity, anions, cations, and metal in all water samples returned concentrations well below the thresholds established by the USEPA. Ongoing sampling of the water in the Gila Conglomerate will continue to establish a baseline for the project.

水質
在鑽孔修復計劃中,收集了來自五個鑽孔的吉拉集團地層水樣本,並分析了鹼度、陰離子、陽離子和金屬濃度。所有水樣中的鹼度、陰離子、陽離子和金屬返回的濃度都遠低於美國環保局設定的閾值。正在進行的吉拉集團水質採樣將繼續爲該項目建立基準。

Hydrogeological Data Collection
The hydrogeological data from the four monitoring stations is collected daily and uploaded via satellite to a dedicated database.

水文地質數據收集
每天收集來自四個監測站的水文地質數據,並通過衛星上傳到專用數據庫。

PLS Analyses
The 2020 PEA recommended completion of a five-well pilot test (one injection and four recovery wells) to determine connectivity between the wells, the ability to contain the leaching fluids as well as several other pertinent parameters associated with the in-situ leaching process. The recommended five-well pilot test requires the injection and recirculation of leaching fluid and on completion of the test, "rinsing" of the leached area is required to meet the requirements established by the USEPA and Arizona Department of Environmental Quality ('ADEQ'). Treatment of these solutions is required prior to disposal to meet USEPA and ADEQ standards.

PLS 分析
2020年PEA建議完成一項五口井試驗(一口注入井和四口回收井),以確定油井之間的連通性、容納浸出液體的能力以及與現場浸出過程相關的其他幾個相關參數。建議的五口井試點測試需要注入和再循環浸出液,測試完成後,必須對浸出區域進行 “沖洗”,以滿足美國環保局和亞利桑那州環境質量部(“ADEQ”)制定的要求。在處置這些溶液之前,需要對這些溶液進行處理,以滿足美國環保局和ADEQ標準。

Modelling of the treatment facility to treat the leach solution and rinse water prior to disposal is possible by using the chemistry of the PLS from the solubility testwork and the source water used to make up the leaching solution. This data would provide critical information as to the scope, capacity, and costs of a treatment plant.

通過使用溶解度測試工作中PLS的化學成分和用於構成浸出溶液的源水,可以對處理浸出溶液和在處置前沖洗水的處理設施進行建模。這些數據將提供有關處理廠範圍、容量和成本的關鍵信息。

Qualified Person
Elmer B. Stewart, MSc. P. Geol., President, and CEO of Copper Fox, is the Company's non-independent, nominated Qualified Person pursuant to National Instrument 43-101, Standards for Disclosure for Mineral Projects, and has reviewed and approves the scientific and technical information disclosed in this news release.

合格人員
埃爾默·B·斯圖爾特,理學碩士根據National Instrument 43-101《礦業項目披露標準》,Copper Fox總裁兼首席執行官P. Geol. 是公司的非獨立提名合格人士,並已審查和批准了本新聞稿中披露的科學和技術信息。

About Copper Fox
Copper Fox is a Tier 1 Canadian resource company focused on copper exploration and development in Canada and the United States. The principal assets of Copper Fox and its wholly owned subsidiaries, being Northern Fox Copper Inc. and Desert Fox Copper Inc., are the 100% ownership of the Van Dyke oxide copper project located in Miami, AZ, the 100% interest in the Mineral Mountain and Sombrero Butte porphyry copper exploration projects located in Arizona, the 25% interest in the Schaft Creek Joint Venture with Teck Resources Limited on the Schaft Creek copper-gold-molybdenum-silver project and the 100% owned Eaglehead polymetallic porphyry copper project each located in northwestern British Columbia. For more information on Copper Fox's mineral properties and investments visit the Company's website at .

關於 Copper Fox
Copper Fox是一家加拿大一級資源公司,專注於加拿大和美國的銅礦勘探和開發。Copper Fox及其全資子公司——北狐銅業公司和沙漠狐銅業公司——的主要資產是位於亞利桑那州邁阿密的範戴克氧化銅項目的100%所有權、位於亞利桑那州的礦山和Sombrero Butte斑岩銅勘探項目的100%權益、與泰克資源有限公司合資的沙夫特溪銅金鉬銀項目25%的權益以及 100% 擁有 Eaglehead 多金屬斑岩銅項目,每個項目都位於英國西北部哥倫比亞。有關Copper Fox礦產和投資的更多信息,請訪問該公司的網站,網址爲。

On behalf of the Board of Directors

代表董事會

Elmer B. Stewart
President and Chief Executive Officer

埃爾默 B. 斯圖爾特
總裁兼首席執行官

For additional information please contact:
Fidel Montegu
1-844-464-2820 or 1-604-358-4005
investor@copperfoxmetals.com

欲了解更多信息,請聯繫:
菲德爾·蒙特古
1-844-464-2820 或 1-604-358-4005
investor@copperfoxmetals.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多倫多證券交易所風險投資交易所及其監管服務提供商(該術語在多倫多證券交易所風險投資交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

Cautionary Note Regarding Forward-Looking Information
This news release contains forward-looking statements within the meaning of the Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934, and forward-looking information within the meaning of the Canadian securities laws (collectively, "forward-looking information"). Forward-looking information is identifiable by use of the words "believes," "may," "plans," "will," "anticipates," "intends," "budgets," "could," "estimates," "expects," "forecasts," "projects" and similar expressions, and the negative of such expressions. Forward-looking information in this news release include statements about: updating the hydrogeological model for the Van Dyke project; driving a decline in the Gila Conglomerate; the water quality being below the thresholds of the regulators; hydrogeological data being collected via satellite; and modeling of the treatment facility.

關於前瞻性信息的警示說明
本新聞稿包含1933年《證券法》第27A條和1934年《證券交易法》第21E條所指的前瞻性陳述,以及加拿大證券法所指的前瞻性信息(統稱爲 “前瞻性信息”)。前瞻性信息可以通過使用 “相信”、“可能”、“計劃”、“將”、“預期”、“打算”、“預算”、“可能”、“估計”、“預期”、“預測”、“項目” 等詞語以及此類表達的否定詞來識別。本新聞稿中的前瞻性信息包括有關以下內容的陳述:更新範戴克項目的水文地質模型;推動吉拉集團的下滑;水質低於監管機構的閾值;通過衛星收集水文地質數據;以及處理設施建模。

In connection with the forward-looking information contained in this news release, Copper Fox and its subsidiaries have made numerous assumptions regarding, among other things: completing the planned hydrogeologic program on time and within budget; the availability of service providers; the geological, metallurgical, engineering, financial and economic advice that Copper Fox has received is reliable and is based upon practices and methodologies which are consistent with industry standards; and the stability of economic and market conditions. While Copper Fox considers these assumptions to be reasonable, these assumptions are inherently subject to significant uncertainties and contingencies.

關於本新聞稿中包含的前瞻性信息,Copper Fox及其子公司對以下方面做出了許多假設:在預算內按時完成計劃中的水文地質計劃;服務提供商的可用性;Copper Fox收到的地質、冶金、工程、財務和經濟建議是可靠的,基於符合行業標準的做法和方法;以及經濟和市場條件的穩定性。儘管Copper Fox認爲這些假設是合理的,但這些假設本質上會受到重大的不確定性和突發性的影響。

Additionally, there are known and unknown risk factors which could cause Copper Fox's actual results, performance, or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking information contained herein. Known risk factors include among others: the updated hydrogeological model may not get completed as planned or at all; the geotechnical study may not return the desired results or be completed as planned or at all; the water quality may change; the hydrogeological data might not get collected; modeling of the treatment facility may not provide the results anticipated; uncertainties relating to interpretation of the previous results; the overall economy may deteriorate; uncertainty as to the availability and terms of future financing; fluctuations in commodity prices and demand; currency exchange rates; and uncertainty as to timely availability of permits and other governmental approvals.

此外,還有一些已知和未知的風險因素可能導致Copper Fox的實際業績、業績或成就與本文所包含的前瞻性信息所表達或暗示的任何未來業績、業績或成就存在重大差異。已知的風險因素包括:更新的水文地質模型可能無法按計劃完成或根本無法完成;岩土工程研究可能無法產生預期的結果,也可能無法按計劃完成;水質可能發生變化;水文地質數據可能無法收集;處理設施的建模可能無法提供預期的結果;與先前結果解釋有關的不確定性;整體經濟可能惡化;未來融資的可得性和條款的不確定性;大宗商品的波動價格和需求; 貨幣匯率; 以及及時獲得許可證和其他政府批准方面的不確定性.

A more complete discussion of the risks and uncertainties facing Copper Fox is disclosed in Copper Fox's continuous disclosure filings with Canadian securities regulatory authorities at . All forward-looking information herein is qualified in its entirety by this cautionary statement, and Copper Fox disclaims any obligation to revise or update any such forward-looking information or to publicly announce the result of any revisions to any of the forward-looking information contained herein to reflect future results, events, or developments, except as required by law.

Copper Fox向加拿大證券監管機構提交的持續披露文件中披露了對Copper Fox面臨的風險和不確定性的更全面的討論。除非法律要求,否則此處的所有前瞻性信息均受本警示聲明的全部限制,Copper Fox不承擔修改或更新任何此類前瞻性信息或公開宣佈對本文包含的任何前瞻性信息進行任何修訂以反映未來業績、事件或發展的結果的義務。

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論