Horizonte Minerals PLC Announces Updated Capex and Schedule Estimate

Horizonte Minerals PLC Announces Updated Capex and Schedule Estimate

Horizonte Minerals PLC宣佈更新的資本支出和進度
Accesswire ·  02/20 01:15

HORIZONTE PROVIDES UPDATED CAPEX AND SCHEDULE ESTIMATE

HORIZONTE 提供最新的資本支出和進度估算

HIGHLIGHTS:

亮點:

  • Horizonte announces preliminary Cost-to-Complete estimate and achievable schedule for Araguaia Line 1
  • Estimate prepared by specialized mining construction and engineering firm G Mining Services
  • Graham Crew appointed as interim Chief Operating Officer (iCOO)
  • Actively engaging existing and new potential investors on a full financing solution
  • Horizonte公佈了阿拉瓜亞1號線的初步完工成本估算和可實現的時間表
  • 估算由專業採礦、建築和工程公司 G Mining Services 編制
  • Graham Crew 被任命爲臨時首席運營官 (iCOO)
  • 積極吸引現有和新的潛在投資者參與全面的融資解決方案

LONDON, UK / ACCESSWIRE / February 19, 2024 / Horizonte Minerals Plc (AIM:HZM)(TSX:HZM) ("Horizonte" or the "Company") announces the preliminary results of a review of the Cost-to-Complete ("CTC") estimate and schedule for its 100%-owned Araguaia Nickel Project ("Araguaia" or "the Project"). The preliminary results of the review indicate that the estimated capital required to complete the construction of Araguaia, commission the project and deliver first metal is approximately US$454 million. As a result, the Estimate at Completion ("EAC") currently stands at US$1,004 million, approximately 87% higher than the previously disclosed capex budget of US$537 million (prior to October 2023). The Company anticipates achieving mechanical completion in Q1 2026.

英國倫敦/ACCESSWIRE/2024年2月19日/Horizonte Minerals Plc(AIM: HZM)(多倫多證券交易所股票代碼:HZM)(“奧裏藏特” 或 “公司”)公佈了對其100%持股的阿拉瓜亞鎳業項目(“阿拉瓜亞” 或 “項目”)竣工成本(“CTC”)估算和時間表的初步審查結果。審查的初步結果表明,完成阿拉瓜亞的建設、調試項目和交付第一批金屬所需的估計資本約爲4.54億美元。因此,竣工時估計(“EAC”)目前爲10.04億美元,比先前披露的5.37億美元資本支出預算(2023年10月之前)高出約87%。該公司預計在2026年第一季度實現機械完工。

G Mining Services ("GMS"), a specialized mining construction and engineering firm, were engaged by the Company to undertake the review process, delivering the re-estimated CTC and achievable schedule estimates. GMS is currently constructing the Tocantinzinho gold project located in Pará state and have notable accomplishments in the successful construction of other mining projects including Lundin Gold's Fruta del Norte Project in Ecuador, Newmont Mining's Merian Mine in Suriname and IAMGOLD's Greenstone project in Ontario.

該公司聘請了專業的採礦建築和工程公司G Mining Services(“GMS”)進行審查過程,提供了重新估算的CTC和可實現的進度估算。GMS目前正在建設位於帕拉州的託坎丁齊尼奧黃金項目,並在成功建設其他採礦項目方面取得了顯著成就,包括厄瓜多爾的倫丁黃金公司的Fruta del Norte項目、蘇里南的紐蒙特礦業的梅里安礦和安大略省的IAMGOLD的綠石項目。

The Company will continue to work closely with its major shareholders and senior lenders on a full funding solution, targeted for Q2 2024. As part of these conversations and given the increase in the CTC estimate, discussions to restructure the Company's debt facilities are being held in conjunction with actively engaging existing and new potential investors. The Company notes that additional interim funding will be required to implement such full funding solution.

該公司將繼續與其主要股東和高級貸款機構密切合作,制定全額融資解決方案,目標是在2024年第二季度推出。作爲這些對話的一部分,鑑於CTC估計值的增加,正在討論重組公司的債務安排,同時積極吸引現有和新的潛在投資者。該公司指出,實施此類全額融資解決方案將需要額外的臨時資金。

Interim CEO Karim Nasr commented,

臨時首席執行官卡里姆·納斯爾評論說,

"Since our last update, a significant volume of work has been completed to develop a new Project Execution Plan, develop a realistic mine plan and business plan, all while continuing to proactively engage with the Company's cornerstone shareholders, senior lenders, vendors and contractors as well as the community and local authorities.

“自我們上次更新以來,在制定新的項目執行計劃、制定切合實際的礦山計劃和商業計劃方面已經完成了大量工作,同時繼續積極與公司的基石股東、高級貸款人、供應商和承包商以及社區和地方當局進行接觸。

"While the new Cost-to-Complete is higher than previously announced by the company, it is now built on solid methodologies, which is a testament to the hard work undertaken to date by the whole Horizonte team. The Company is pleased to partner with G Mining Services, who have a track record of success in the region and are currently building the Tocantinzinho project with G Mining Ventures in Para state. The Company is now in a position to properly assess its ability to finance and complete the Araguaia Nickel Project (Line 1) and bring it into production.

“儘管新的完成成本高於公司先前宣佈的價格,但它現在建立在可靠的方法基礎上,這證明了整個Horizonte團隊迄今爲止所做的辛勤工作。該公司很高興與G Mining Services合作,後者在該地區有着良好的成功記錄,目前正在帕拉州與G Mining Ventures合作建設託坎丁齊尼奧項目。該公司現在能夠正確評估其融資和完成阿拉瓜亞鎳礦項目(1號線)並將其投入生產的能力。

"It is important to note that while completing the Cost-to-Complete estimate is a significant milestone, resuming and completing construction activities at Araguaia are still subject to the successful completion of a full financing solution, which the company will seek to develop in the coming weeks, but with no guarantee of success. Further, the CTC estimate is the capital required to complete the construction of Araguaia, commission the project and deliver first metal. The final financing amount will be higher and will depend on a variety of factors including discussions with Senior Lenders, suppliers, cornerstone investors and other third parties."

“值得注意的是 儘管完成完工成本估算是一個重要的里程碑,但阿拉瓜亞建築活動的恢復和完成仍取決於全面融資解決方案的成功完成,該公司將在未來幾周內尋求制定該解決方案,但不能保證成功。此外,CTC的估計是完成阿拉瓜亞的建造、項目調試和交付第一批金屬所需的資金。最終融資額將更高,這將取決於多種因素,包括與高級貸款人、供應商、基石投資者和其他第三方的討論。”

BASIS OF COST TO COMPLETE ("CTC") ESTIMATE

完成成本的依據(“CTC”)估算

Based on the work to date, a total of around 4.7 million work-hours are required to finish construction of Araguaia Line 1. The current optimized plan assumes a smaller workforce which drives a revised construction schedule of approximately 18 months.

根據迄今爲止的工作,完成阿拉瓜亞1號線的施工總共需要約470萬個工時。當前的優化計劃假設員工人數減少,從而推動修訂後的施工進度約爲18個月。

The EAC currently stands at US$1,004 million, of which a total of US$479 million has been spent up to the end of 2023, US$52 million is outstanding to trade creditors, US$15 million for critical activities during the slowdown period and US$4 million pre-first metal mining costs, resulting in a CTC of US$454 million. The capex estimate includes all the direct and indirect costs, local taxes and duties and US$54 million contingency deemed to be required to complete the construction of Line 1, commission the project and deliver first metal. This estimate is based on the Association for the Advancement of Cost Engineering (AACE) Class 3 standard, with an accuracy range between -10% and +30%, of the final project cost. The Company intends to work with GMS over the refinancing period to refine this to a control estimate, AACE Class 1 with an accuracy range of -3% to +15%.

東非共同體目前爲10.04億美元,其中截至2023年底的總支出爲4.79億美元,未償還給貿易債權人的5200萬美元,經濟放緩時期的關鍵活動1,500萬美元,以及首次金屬開採前的400萬美元,使CTC達到4.54億美元。資本支出估算包括所有直接和間接成本、地方稅和關稅以及被認爲需要完成1號線的建設、調試項目和交付第一批金屬所需的5400萬美元應急費用。該估算基於成本工程促進協會(AACE)的3級標準,精度範圍爲最終項目成本的-10%至+ 30%。該公司打算在再融資期間與GMS合作,將其完善爲控制估計,即AACE 1級,準確度範圍爲-3%至+ 15%。

The costs for these items have been derived from vendor quotes for the equipment and materials. The capex estimate is after tax, including growth and contingency and excluding escalation. The CTC excludes the owner's costs incurred during the slow-down phase between 10 November 2023 and June 2024, which are being funded with current cash and the aforementioned additional interim funding requirement. The CTC also excludes working capital, capitalized ramp-up costs and financing costs which will be included in the full funding solution.

這些物品的成本來自供應商對設備和材料的報價。資本支出估算是稅後,包括增長和應急支出,不包括升值。CTC不包括業主在2023年11月10日至2024年6月的減速階段產生的費用,這些費用由當期現金和上述額外臨時資金要求提供資金。CTC還不包括營運資金、資本化增值成本和融資成本,這些費用將包含在全額融資解決方案中。

SCHEDULE ESTIMATE

日程估算

The project schedule has been re-estimated by GMS following a complete review of the quantities remaining, the procurement packages and logistics, and re-estimation of the work-hours required to complete construction and commissioning. GMS have been working with key equipment suppliers including Hatch Ltd and FLSmidth to fully assess the remaining work. The current project schedule estimate anticipates approximately 18 months of construction from re-mobilisation to the projected first metal date. Remobilisation is currently planned for Q3-2024 with a first metal date of Q1-2026, subject to successful refinancing and restart decision.

GMS對剩餘數量、一攬子採購和物流進行了全面審查,並重新估算了完成施工和調試所需的工作時間後,重新估算了項目進度。GMS一直在與包括Hatch Ltd和flsMidth在內的主要設備供應商合作,以全面評估剩餘的工作。根據目前的項目進度估計,從重新調動到預計的首批金屬建成日期,施工時間約爲18個月。目前計劃對 Q3-2024 進行重組,首個金屬日期爲 Q1-2026,但須視再融資成功和重啓決定而定。

One of the key inputs for the new schedule was the productivity assumptions that drive the estimated progress for the principal project workstreams. GMS provided updated productivity figures based on their experience at the Tocantinzinho gold project located in Pará state, Brazil and therefore has recent, first-hand experience of achievable productivity rates for the main trades.

新進度表的關鍵輸入之一是生產率假設,這些假設推動了主要項目工作流的預計進度。GMS根據其在位於巴西帕拉州的Tocantinzinho黃金項目的經驗,提供了最新的生產率數據,因此獲得了有關主要行業可實現生產率的最新第一手經驗。

Further, as part of the review exercise, the Company reviewed the production ramp-up schedule and associated working capital and capitalized operating costs requirements. The original schedule assumed a 12-month ramp up to nameplate capacity; while achievable, this was considered to be a best-case scenario and has since been replaced by a more conservative 18-month ramp-up.

此外,作爲審查工作的一部分,公司審查了增產計劃以及相關的營運資金和資本化運營成本要求。最初的時間表假設將銘牌容量增加12個月;儘管可以實現,但這被認爲是最佳情況,後來被更爲保守的18個月增長所取代。

PROJECT EXECUTION PLAN

項目執行計劃

GMS have also re-developed the Project Execution Plan (PEP) as a self-perform model as employed at Tocantinzinho and other projects GMS have been involved in. Under this model the Company will directly employ the owner's team and construction employees with expertise and support from GMS. GMS employees brought into the project will be seconded directly to Araguaia Nickel Project with objectives, salaries and any incentives set and paid by the Company.

GMS還重新制定了項目執行計劃(PEP),將其作爲一種自我績效模型,Tocantinzinho和GMS參與的其他項目都採用了這種模式。在這種模式下,公司將直接僱用業主團隊和施工員工,由GMS提供專業知識和支持。參與該項目的GMS員工將直接借調到Araguaia Nickel項目,其目標、薪水和任何激勵措施均由公司制定和支付。

The benefits of this model include a simplified management structure, a reduction in the number of contractors and consultants, and full alignment of the owner's team and construction team. Specialist contractors and OEMs will continue to be critically important partners in the project execution.

該模式的好處包括簡化管理結構,減少承包商和顧問的數量,以及業主團隊和施工團隊的全面調整。專業承包商和原始設備製造商將繼續是項目執行中至關重要的合作伙伴。

SENIOR MANAGEMENT CHANGES

高級管理層變動

Maryse Bélanger, interim Chief Operating Officer ("COO") of the Company will step down as COO effective 21 February 2024, following a period of handover to Graham Crew, who is appointed as new interim COO. The Company wishes to thank Mrs. Belanger for her invaluable assistance in this challenging period.

在移交給被任命爲新任臨時首席運營官的格雷厄姆·克魯一段時間後,公司臨時首席運營官(“COO”)瑪麗絲·貝蘭格將辭去首席運營官的職務,自2024年2月21日起生效。公司要感謝Belanger女士在這個充滿挑戰的時期所提供的寶貴幫助。

Mr Crew was Chief Technical Officer of La Mancha Resource Capital LLP ("La Mancha"), which advises La Mancha Resource Fund SCSp, one of the Company's major shareholders. Mr Crew has been on a period of secondment to the Company in recent months having stepped down from his day-to-day executive role within La Mancha. He was previously a Non-executive Director at Golden Star Resources Limited before becoming Chief Operating Officer. He has extensive operational experience in Australia, Africa and Asia and was previously Operations Manager for La Mancha Resources Australia, including the development and construction and ramp up of the Mungari processing facility, prior to the divestment of those assets to Evolution Mining. He began his career with Western Mining Corporation at Olympic Dam and Leinster Nickel Operations. He holds a B.Eng (Mining Engineering) from the West Australian School of Mines, is a Member of the Australian institute of Corporate Directors and a Fellow of the Australasian Institute of Mining & Metallurgy.

克魯先生曾是拉曼恰資源資本有限責任公司(“拉曼查”)的首席技術官,該公司爲該公司的主要股東之一拉曼恰資源基金sCSp提供諮詢。Crew先生已辭去拉曼恰的日常行政職務,最近幾個月一直借調到公司。在成爲首席運營官之前,他曾在金星資源有限公司擔任非執行董事。他在澳大利亞、非洲和亞洲擁有豐富的運營經驗,在將這些資產剝離給Evolution Mining之前,他曾擔任澳大利亞拉曼查資源公司的運營經理,包括開發、建設和擴建Mungari加工設施。他的職業生涯始於西部礦業公司的奧林匹克大壩和倫斯特鎳業公司。他擁有西澳大利亞礦業學院的工程學士學位(採礦工程),是澳大利亞公司董事協會的成員和澳大利亞礦業與冶金學會的會員。

Completion of construction activities at Araguaia will be subject to successful completion of a full financing solution in 2024. There can be no certainty at this stage that the full financing solution will be achieved and further updates will be provided in due course.

阿拉瓜亞建築活動的完成將取決於2024年全面融資解決方案的成功完成。現階段無法確定能否實現全面的融資解決方案,並在適當時候提供進一步的更新。

This announcement contains inside information for the purposes of Article 7 of EU Regulation 596/2014, as retained in the UK pursuant to the European Union (Withdrawal) Act 2018.

本公告包含根據2018年《歐盟(退出)法》在英國保留的歐盟第596/2014號法規第7條之目的的內部信息。

For further information, visit or contact:

欲了解更多信息,請訪問或聯繫:

Horizonte Minerals plc
Patrick Chambers (Head of IR)

info@horizonteminerals.com
+44 (0) 203 356 2901

Peel Hunt LLP (Nominated Adviser & Joint Broker)
Ross Allister
David McKeown
Bhavesh Patel

+44 (0) 20 7418 8900

BMO (Joint Broker)
Thomas Rider
Pascal Lussier Duquette
Andrew Cameron

+44 (0) 20 7236 1010

Barclays (Joint Broker)
Philip Lindop
Richard Bassingthwaighte

+44 (0) 20 7623 2323

奧裏藏特礦業有限公司
帕特里克·錢伯斯(投資者關係主管)

info@horizonteminerals.com
+44 (0) 203 356 2901

Peel Hunt LLP(提名顧問兼聯合經紀人)
羅斯·艾利斯特
大衛麥基恩
Bhavesh Patel

+44 (0) 20 7418 8900

BMO(聯合經紀人)
托馬斯·裏德
帕斯卡爾·盧西爾·杜奎特
安德魯卡梅隆

+44 (0) 20 7236 1010

巴克萊(聯合經紀人)
菲利普·林多普
理查德·巴辛斯韋特

+44 (0) 20 7623 2323

ABOUT HORIZONTE MINERALS

關於奧裏藏特礦物

Horizonte Minerals Plc (AIM/TSX: HZM) is developing two 100%-owned, Tier 1 projects in Pará state, Brazil - the Araguaia Nickel Project and the Vermelho Nickel-Cobalt Project. Both projects are high-grade, low-cost, with low carbon emission intensities and are scalable. Araguaia is under construction and when fully ramped up with both Line 1 and Line 2, is forecast to produce 29,000 tonnes of nickel per year. Vermelho is at feasibility study stage. Horizonte's combined production profile of over 60,000 tonnes of nickel per year positions the Company as a globally significant nickel producer. Horizonte's top three shareholders are La Mancha Investments S.à r.l., Glencore Plc and Orion Mine Finance.

Horizonte Minerals Plc(AIM/TSX:HZM)正在巴西帕拉州開發兩個100%持股的一級項目——阿拉瓜亞鎳礦項目和Vermelho鎳鈷項目。這兩個項目都具有高品位、低成本、低碳排放強度,並且具有可擴展性。阿拉瓜亞正在建設中,當1號線和2號線全面擴建後,預計每年將生產29,000噸鎳。Vermelho 正處於可行性研究階段。Horizonte的年鎳總產量超過6萬噸,這使該公司成爲全球重要的鎳生產商。奧裏藏特的前三名股東是拉曼查投資有限公司、嘉能可集團和獵戶座礦業融資。

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

關於前瞻性信息的警示性聲明

Except for statements of historical fact relating to the Company, certain information contained in this press release constitutes "forward-looking information" under Canadian securities legislation. Forward-looking information includes, but is not limited to, the ability of the Company to complete any planned acquisition of equipment, statements with respect to the potential of the Company's current or future property mineral projects; the ability of the Company to complete a positive feasibility study regarding the second RKEF line at Araguaia on time, or at all, the ability of the Company to complete a positive feasibility study regarding the Vermelho Project on time, or at all, the success of exploration and mining activities; cost and timing of future exploration, production and development; the costs and timing for delivery of the equipment to be purchased, the estimation of mineral resources and reserves and the ability of the Company to achieve its goals in respect of growing its mineral resources; the realization of mineral resource and reserve estimates and achieving production in accordance with the Company's potential production profile or at all. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, and are inherently subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to risks related to: the inability of the Company to complete any planned acquisition of equipment on time or at all, the ability of the Company to complete a positive feasibility study regarding the implementation of a second RKEF line at Araguaia on the timeline contemplated or at all, the ability of the Company to complete a positive feasibility study regarding the Vermelho Project on the timeline contemplated or at all, exploration and mining risks, competition from competitors with greater capital; the Company's lack of experience with respect to development-stage mining operations; fluctuations in metal prices; uninsured risks; environmental and other regulatory requirements; exploration, mining and other licences; the Company's future payment obligations; potential disputes with respect to the Company's title to, and the area of, its mining concessions; the Company's dependence on its ability to obtain sufficient financing in the future; the Company's dependence on its relationships with third parties; the Company's joint ventures; the potential of currency fluctuations and political or economic instability in countries in which the Company operates; currency exchange fluctuations; the Company's ability to manage its growth effectively; the trading market for the ordinary shares of the Company; uncertainty with respect to the Company's plans to continue to develop its operations and new projects; the Company's dependence on key personnel; possible conflicts of interest of directors and officers of the Company, and various risks associated with the legal and regulatory framework within which the Company operates, together with the risks identified and disclosed in the Company's disclosure record available on the Company's profile on SEDAR at , including without limitation, the annual information form of the Company for the year ended December 31, 2022, and the Araguaia and Vermelho Technical Reports available on the Company's website Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

除與公司有關的歷史事實陳述外,根據加拿大證券立法,本新聞稿中包含的某些信息構成 “前瞻性信息”。前瞻性信息包括但不限於公司完成任何計劃中的設備收購的能力、關於公司當前或未來房地產礦業項目潛力的陳述;公司按時完成有關阿拉瓜亞第二條RKEF線的積極可行性研究的能力,或者完全包括公司按時完成有關Vermelho項目的積極可行性研究的能力,或者完全是成功的能力勘探和採礦活動;未來成本和時機勘探、生產和開發;待購買設備的成本和交付時間、礦產資源和儲量的估算以及公司實現礦產資源開發目標的能力;實現礦產資源和儲量估算並根據公司潛在的生產狀況實現產量或完全實現產量。通常,前瞻性信息可以通過使用前瞻性術語來識別,例如 “計劃”、“預期” 或 “不期望”、“預期”、“預期”、“估計”、“預測”、“打算”、“預期” 或 “不預期” 或 “相信”,或者使用某些行動、事件或結果 “可能”、“可能”、“相信” 等詞語和短語或陳述的變體將”、“可能” 或 “將採取”、“發生” 或 “實現”。前瞻性信息基於管理層根據其經驗以及對趨勢、當前狀況和預期發展的看法,以及管理層認爲與此類陳述發表之日情況相關和合理的其他因素而做出的合理假設、估計、分析和觀點,這些因素本質上受已知和未知的風險、不確定性和其他因素的影響,這些因素可能導致公司的實際業績、活動水平、業績或成就取得實質性進展與此類前瞻性信息所表達或暗示的不同,包括但不限於與以下風險相關的風險:公司無法按時或根本完成任何計劃中的設備收購;公司能否在設想的時間表或根本完成關於在阿拉瓜亞實施第二條RKEF生產線的積極可行性研究;公司能否在設想的時間表內完成有關Vermelho項目的積極可行性研究;或總而言之,勘探和採礦風險,來自擁有更多資本的競爭對手的競爭;公司在開發階段的採礦業務方面缺乏經驗;金屬價格波動;未投保的風險;環境和其他監管要求;勘探、採礦和其他許可證;公司未來的付款義務;與公司採礦特許權的所有權和麪積有關的潛在爭議;公司對未來獲得足夠融資的能力的依賴;公司依賴與第三者的關係各方;公司的合資企業;公司運營所在國可能出現的貨幣波動和政治或經濟不穩定;匯率波動;公司有效管理增長的能力;公司普通股交易市場;公司繼續發展業務和新項目的計劃的不確定性;公司對關鍵人員的依賴;公司董事和高級管理人員可能存在的利益衝突以及與法律和法律相關的各種風險公司運營所處的監管框架,以及公司在SEDAR上的公司簡介中發現和披露的公司披露記錄中發現和披露的風險,包括但不限於公司截至2022年12月31日止年度的年度信息表以及公司網站上提供的Araguaia和Vermelho技術報告。儘管公司管理層試圖確定可能導致實際業績與前瞻性信息中包含的業績存在重大差異的重要因素,可能還有其他因素導致結果與預期、估計或預期不符。無法保證此類陳述會被證明是準確的,因爲實際結果和未來事件可能與此類陳述中的預期存在重大差異。

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit .

該信息由倫敦證券交易所的新聞服務RNS提供。RNS已獲得金融行爲監管局的批准,成爲英國的主要信息提供商。與使用和分發此信息相關的條款和條件可能適用。欲了解更多信息,請聯繫 rns@lseg.com 或訪問。

SOURCE: Horizonte Minerals PLC

資料來源:奧裏藏特礦業有限公司


譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論