share_log

Silver Tiger Announces PEA With NPV of US$287M for the Open Pit Portion of El Tigre Silver-Gold Project

Silver Tiger Announces PEA With NPV of US$287M for the Open Pit Portion of El Tigre Silver-Gold Project

Silver Tiger宣布El Tigre银金项目露天矿部分的净现值为2.87亿美元
Accesswire ·  2023/11/01 19:00

HALIFAX, NS / ACCESSWIRE / November 1, 2023 / Silver Tiger Metals Inc. (TSXV:SLVR)(OTCQX:SLVTF) ("Silver Tiger" or the "Corporation") is pleased to announce a Preliminary Economic Assessment ("PEA") for its 100% owned, silver-gold El Tigre Project (the "Project" or "El Tigre") located in Sonora, Mexico. The PEA is centered on the conventional open pit mining economics of the Stockwork Mineralization Zone defined in the updated MRE released September 12, 2023 (Figure 1).

新南威尔士州哈利法克斯/ACCESSWIRE /2023 年 11 月 1 日/ Silver Tiger Metals Inc.(多伦多证券交易所股票代码:SLVR)(OTCQX: SLVTF)(“银虎” 或 “公司”)欣然宣布其位于墨西哥索诺拉的100%拥有的银金El Tigre项目(“项目” 或 “El Tigre”)的初步经济评估(“PEA”)。PEA以Stockwork矿化区的传统露天采矿经济学为中心,该经济学在2023年9月12日发布的更新的MRE中定义(图1)。

Highlights of the PEA, with a base case silver price of $23.75/oz and gold price of $1,850/oz are as follows (all figures in US dollars unless otherwise stated):

PEA的亮点如下,基本白银价格为23.75美元/盎司,金价为1,850美元/盎司(除非另有说明,否则所有数字均以美元计):

  • After-Tax net present value ("NPV") (using a discount rate of 5%) of US$287 Million with an After-Tax IRR of 55.8% and Payback Period of 1.7 years (Base Case);
  • 13-year mine life recovering a total of 60 Million payable silver equivalent ounces ("AgEq") or 776,000 gold equivalent ounces ("AuEq"), consisting of 16 Million silver ounces and 571,000 gold ounces;
  • Total project undiscounted after tax cash flow of US$445 Million;
  • Initial capital costs of $59 Million, including $7.7 Million in contingency costs, over an expected 12-month build, expansion capital of $33 Million and sustaining capital costs of $31 Million over the life of mine ("LOM");
  • Average LOM operating cash costs of $803/oz AuEq, and all in sustaining costs ("AISC") of $843/oz AuEq or Average LOM operating cash costs of $10/oz AgEq, and all in sustaining costs ("AISC") of $11/oz AgEq; and
  • Average annual production of approximately 4.6 Million AgEq oz or 59,000 AuEq oz.
  • 税后净现值(“NPV”)(使用5%的贴现率)为2.87亿美元,税后内部收益率为55.8%,投资回收期为1.7年(基本情况);
  • 矿山寿命为13年,共回收6000万应付银当量盎司(“AgeQ”)或77.6万金当量盎司(“AueQ”),包括1,600万银盎司和57.1万盎司金盎司;
  • 未贴现的项目税后现金流总额为4.45亿美元;
  • 初始资本成本为5,900万美元,包括770万美元的应急费用,为期12个月,扩建资本为3,300万美元,矿山生命周期内的维持资本成本为3,100万美元(“LOM”);
  • 平均LOM运营现金成本为803美元/盎司AueQ,所有维持成本(“AISC”)为843美元/盎司AueQ或平均LOM运营现金成本为10美元/盎司AgeQ,所有维持成本(“AISC”)为11美元/盎司AgeQ;以及
  • 平均年产量约为460万盎司或59,000当量盎司。

Glenn Jessome, President & CEO stated "We are very pleased with the work completed by our consultants and our technical team on the PEA for the open pit at El Tigre. The open pit delivers robust economics with an NPV of US$287 million and substantial after tax cash flows of US$445 million." Mr. Jessome continued "This is a pivotal point for our Company as we now have a clear path forward to quickly completing a PFS and making a construction decision for the open pit. The open pit has good grade, low strip, wide benches and exceptional metallurgy. With such positive parameters and with our new VP of Operations Francisco Albelais, a career expert in the construction of large heap leach mines in Mexico, we are confident we will be able to advance the open pit portion of the project very quickly." Mr. Jessome concluded "The open pit is only one component of El Tigre as we have also recently delivered over 90-million silver equivalent ounces in the underground in the Mineral Resource Estimate and disclosed an Exploration Target establishing 7 to 9 million tonnes at 225 to 265 g/t AgEq for 50 to 75 million silver equivalent ounces. The Company will also continue to work on this substantial underground Mineral Resource and advance that towards a PEA."

总裁兼首席执行官格伦·杰索姆表示:“我们对我们的顾问和技术团队在El Tigre露天矿PEA方面所完成的工作感到非常满意。露天矿带来了强劲的经济效益,净现值为2.87亿美元,税后现金流为4.45亿美元。”杰索姆先生继续说:“这是我们公司的关键时刻,因为我们现在有一条明确的前进道路,可以快速完成PFS并做出露天矿的施工决策。露天矿品位良好,带材低,长凳宽阔,冶金效果出色。有了如此积极的参数,再加上我们新的运营副总裁弗朗西斯科·阿尔贝莱斯(Francisco Albelais),他是墨西哥大型堆滤矿建设的职业专家,我们相信我们将能够迅速推进该项目的露天部分。”杰索姆先生总结说:“露天矿只是El Tigre的一个组成部分,因为我们最近还在矿产资源估算中在地下交付了超过9000万盎司的白银当量,并披露了一个勘探目标,即700万至900万吨的AgeQ含量为225至265克/吨,相当于5000万至7500万盎司的白银当量。该公司还将继续开发这种大量的地下矿产资源,并将其推向PEA。”

Figure 1: El Tigre Mineral Resource Block Model 3D Visualization, showing pit constrained Resources.
图 1:El Tigre 矿产资源区块模型三维可视化,显示了矿坑受限的资源。

Preliminary Economic Assessment Summary

初步经济评估摘要

The PEA was prepared by independent consultants Micon International Limited ("Micon"), with metallurgical test work completed by SGS Canada Inc.'s Lakefield office ("SGS") and process plant design and costing by D.E.N.M. Engineering Ltd., and environmental and permitting led by CIMA Mexico. Following are tables and figures showing key assumptions, results, and sensitivities.

PEA由独立顾问Micon International Limited(“Micon”)编写,冶金测试工作由加拿大GS公司完成。”s 莱克菲尔德办公室(“SGS”)和加工厂的设计和成本由D.E.N.M. 工程有限公司负责,环境和许可由墨西哥CIMA领导。以下是显示关键假设、结果和敏感性的表格和数字。

Table 1: El Tigre PEA Key Economic Assumptions and Results

表 1:El Tigre PEA 关键经济假设和结果

Assumption / Result Unit

Value

Assumption / Result Unit

Value

Total OP Plant Feed Mined kt

57,038

Net Revenue US$M

1,422

Operating Strip Ratio Ratio

2.0

Initial Capital Costs US$M

59

Silver Grade 1 g/t

14.27

Expansion Capital Costs US$M

33

Gold Grade 1 g/t

0.39

Sustaining Capital Costs US$M

31

AuEq Grade 1 g/t

0.57

Mining Costs - Plant $/t Feed

5.81

Silver Recovery 2 %

61

Mining Costs - Material $/t Material

1.91

Gold Recovery 2 %

80

Processing Costs $/t Feed

4.46

Silver Price US$/oz

23.75

G&A Costs $/t Feed

0.61

Gold Price US$/oz

1,850

Operating Cash Cost US$/oz AuEq

803

Payable Silver Metal Moz

15.9

All in Sustaining Cost US$/oz AuEq

843

Payable Gold Metal koz

571

After-Tax NPV (5% discount) US$M

287

Payable AuEq koz

776

Pre-Tax NPV (5% discount) US$M

420

Mine Life Yrs

13

After-Tax IRR %

55.8

Average mining rate t/day

36,000

Pre-Tax IRR %

79.4

After-Tax Payback Period Yrs

1.7

假设/结果 单元

价值

假设/结果 单元

价值

开采的 OP 植物饲料总量 kt

57,038

净收入 百万美元

1,422

操作条带比率 比率

2.0

初始资本成本 百万美元

59

银级 1 g/t

14.27

扩张资本成本 百万美元

33

黄金等级 1 g/t

0.39

维持资本成本 百万美元

31

AueQ 等级 1 g/t

0.57

采矿成本-工厂 $/t Feed

5.81

白银回收 2 %

61

采矿成本-材料 $/t 材质

1.91

黄金回收 2 %

80

处理成本 $/t Feed

4.46

白银价格 美元/盎司

23.75

并购成本 $/t Feed

0.61

黄金价格 美元/盎司

1,850

运营现金成本 美元/盎司 AueQ

803

应付银色金属 Moz

15.9

全部包含维持成本 美元/盎司 AueQ

843

应付金属 koz

571

税后净现值(5%折扣) 百万美元

287

应付账款 AueQ koz

776

税前净现值(5% 折扣) 百万美元

420

我的生活 是的

13

税后内部收益率 %

55.8

平均采矿率 t/天

36,000

税前内部收益率 %

79.4

税后投资回收期 是的

1.7

  1. Grades shown are LOM average process plant feed grades include only OP sources. Mining losses of 2.5% and external dilution of 2.5% with low grade waste for OP material was incorporated in the mining schedule.
  2. Column testing indicated both higher and gold and silver recovery (83% and 64%) at a 3/8-in crush size. In the process design and financial model, these have been discounted by 3% for leaching in the field versus optimum conditions in the laboratory.
  1. 显示的等级是 LOM 加工厂的平均饲料等级,仅包括 OP 来源。采矿计划中纳入了2.5%的采矿损失和2.5%的外部稀释以及低品位OP材料的低品位废物。
  2. 色谱柱测试表明,压碎尺寸为3/8英寸时,金银回收率均较高(83%和64%)。在工艺设计和财务模型中,与实验室的最佳条件相比,实地浸出可享受3%的折扣。

Figure 2: El Tigre Cash Flow Profile by Year

图 2:按年度划分的 El Tigre 现金流概况

Figure 2 above highlights the post-tax cash flows of US$445 Million associated with the El Tigre Project. The economics of the project have been evaluated based on the base case scenario $23.75/oz silver price and gold price of $1,850/oz. As illustrated in the following sensitivity tables, the project remains robust even at lower commodity prices or with higher costs.

上图2突出显示了与El Tigre项目相关的4.45亿美元的税后现金流。该项目的经济性是根据基本情景评估的,银价为每盎司23.75美元,黄金价格为1850美元/盎司。如以下灵敏度表所示,即使在大宗商品价格较低或成本较高的情况下,该项目仍保持强劲。

Table 2 - El Tigre PEA Gold and Silver Price Sensitivities

表 2-El Tigre PEA 黄金和白银价格敏感度

Sensitivity Base Case
Silver Price (US$/oz)

17

19

21

23.75

26

30

33

Gold Price (US$/oz)

1,324

1,480

1,636

1,850

2,025

2,337

2,571

After-Tax NPV (5%) (US$M)

108

161

214

287

347

453

532

After-Tax IRR (%)

28.3

37.2

45.3

55.8

64.1

78.5

88.9

After-Tax Payback (years)

4.1

2.6

2.0

1.7

1.5

1.3

1.1

灵敏度 基础案例
白银价格(美元/盎司)

17

19

21

23.75

26

30

33

黄金价格(美元/盎司)

1,324

1,480

1,636

1,850

2,025

2,337

2,571

税后净现值 (5%)(百万美元)

108

161

214

287

347

453

532

税后内部收益率 (%)

28.3

37.2

45.3

55.8

64.1

78.5

88.9

税后投资回报(年)

4.1

2.6

2.0

1.7

1.5

1.3

1.1

Table 3 - El Tigre PEA Operating Cost and Capital Cost Sensitivities

表 3-El Tigre PEA 运营成本和资本成本敏感度

Sensitivity

-20%

-10%

Base Case

10%

20%

Operating Costs - NPV (US$M)

345

316

287

258

229

Operating Costs - IRR (%)

64.4

60.1

55.8

51.5

47.2

Capital Costs - NPV (US$M)

301

293

287

280

273

Capital Costs - IRR (%)

68.0

61.3

55.8

51.2

47.3

灵敏度

-20%

-10%

基础案例

10%

20%

运营成本-净现值(百万美元)

345

316

287

258

229

运营成本-内部收益率 (%)

64.4

60.1

55.8

51.5

47.2

资本成本-净现值(百万美元)

301

293

287

280

273

资本成本-内部收益率 (%)

68.0

61.3

55.8

51.2

47.3

Capital and Operating Costs

资本和运营成本

The El Tigre Project has been envisioned as an open pit mining operation starting at a processing rate of 7,500 tonnes per day for years 1-3 and then ramping up to 15,000 tonnes per day by year 5 after 1 year construction for ramp up.

El Tigre项目被设想为露天采矿作业,起始处理量为7,500吨,持续1-3年,然后在扩建1年后,到第5年将增加到每天15,000吨。

The process plant is comprised of conventional three (3) stage crushing to an optimum -3/8-in crush size. The crushed material will be conveyed and loaded on the lined pad areas. A series of pumping and piping will allow irrigation of the stacked heap material and subsequent production of pregnant solution to flow to the respective impoundment pond. The pregnant solution will be pumped to the recovery facility consisting of the Merrill - Crowe process (zinc precipitation) and refinery to produce the gold and silver dore for marketing. The process barren solution will be recycled (with NaCN addition) and pumped back to the heap for further leaching.

该加工设备由传统的三 (3) 级破碎机组成,可达到最佳的粉碎尺寸 -3/8 英寸。粉碎的物料将被输送并装载到衬垫区域。一系列的抽水和管道将允许灌溉堆积的堆积物,随后产生的孕液流向相应的蓄水池。怀孕的溶液将被泵送到由美林-克劳工艺(锌沉淀)和炼油厂组成的回收设施,生产金银矿石以供销售。工艺贫瘠的溶液将被回收利用(添加NaCn),然后泵回堆中进行进一步浸出。

Water supply to the process plant is provided by nearby surface wells and a new high voltage grid power will be installed by the local utility to supply process and infrastructure power requirements. Expansion capital includes the cost to increase the process plant capacity from 7,500 tonnes per day to 15,000 tonnes per day as noted.

加工厂的供水由附近的地表井提供,当地公用事业公司将安装新的高压电网电力,以满足工艺和基础设施的电力需求。如前所述,扩张资本包括将加工厂产能从每天7,500吨提高到每天15,000吨的成本。

Table 4 - LOM Capital Cost Estimate

表 4-LOM 资本成本估算

Type

Initial
(US$k)

Expansion
(US$k) 1

Sustaining
(US$k)

Total
(US$k)

Plant direct costs

31,921

25,800

57,721

Mining direct costs

5,340

3,250

30,924

39,514

Pre-stripping

2,347

2,347

Infrastructure

9,470

9,470

Project indirect costs

2,200

2,200

Total

51,278

29,050

30,924

111,252

Contingency (15%)

7,692

4,358

12,049

Total - Initial Capital

58,969

33,408

30,924

123,301

类型

初始的
(千美元)

扩张
(千美元) 1

维持
(千美元)

总计
(千美元)

工厂直接成本

31,921

25,800

57,721

采矿直接成本

5,340

3,250

30,924

39,514

预剥离

2,347

2,347

基础架构

9,470

9,470

项目间接成本

2,200

2,200

总计

51,278

29,050

30,924

111,252

意外开支 (15%)

7,692

4,358

12,049

总计-初始资本

58,969

33,408

30,924

123,301

  1. Expansion capital is not included in AISC calculations
  1. AISC计算中不包括扩张资金

Mining

采矿

Open pit mining will be contracted and carried out by drill and blast followed by conventional loading and truck haulage to the waste rock storage facilities and the process plant.

露天采矿将签订合同,通过钻探和爆破进行,然后进行常规装载和卡车运送到废石储存设施和加工厂。

Metallurgy

冶金

A preliminary metallurgical test program was carried out by SGS Lakefield of Ontario, Canada on open pit samples. Details of the testing were outlined in the previous Sliver Tiger News Release dated August 24, 2023. The program included crushing, coarse bottle rolls, and composite column testing at both 3/8-in and 1/2 -in crush size. The leach samples comprised of drill core sample representing the Stockwork Mineralization Zone of the Mineral Resource. This preliminary test program estimated average gold and silver respective metallurgical recoveries of 83.1 % Au and 64.3 % Ag at the 3-/8-in crush. Percolation testing also indicated no requirement for agglomeration of the crushed material is required prior to loading.

加拿大安大略省的SGS Lakefield对露天矿样品进行了初步的冶金测试计划。测试的细节已在2023年8月24日之前的Silver Tiger新闻稿中概述。该项目包括破碎、粗瓶轧制和压碎尺寸均为 3/8 英寸和 1/2 英寸的复合柱测试。浸出样品由代表矿产资源斯托克矿化区的钻芯样品组成。该初步测试计划估计,在压碎3-/8英寸时,金银各自的平均冶金回收率为83.1%,银的平均回收率为64.3%。渗透测试还表明,在装载之前不需要对破碎的材料进行结块。

Underground Mineral Resource

地下矿产资源

As previously released, the Company will also continue to work on this substantial underground Mineral Resource and advance that towards PEA. Out-of-Pit Mineral Resources at El Tigre of 21 Moz AgEq grading 279 g/t AgEq contained in 2.3 Mt and 70 Moz AgEq grading 235 g/t AgEq contained in 9.2 Mt (Table 5). For higher grade sensitivity cases refer to updated MRE release dated September 12, 2023.

正如先前发布的那样,该公司还将继续开发这种庞大的地下矿产资源,并将其推向PEA。El Tigre的露天矿产资源AgeQ等级为279 g/t AgeQ的含量为230万吨,920万吨含有70Moz AgeQ等级为235 g/t AgeQ(表5)。有关更高等级的灵敏度案例,请参阅 2023 年 9 月 12 日更新的 MRE 版本。

Table 5 - Mineral Resource Estimate released September 2023

表 5-2023 年 9 月发布的矿产资源估算

  1. Mineral Resources which are not Mineral Reserves, do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
  2. The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration.
  3. The Mineral Resources in this news release were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines (2014) prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council and CIM Best Practices (2019).
  4. Historically mined areas were depleted from the Mineral Resource model.
  5. Approximately 74.7% of the Indicated and 22.3% of the Inferred contained AgEq ounces are pit constrained, with the remainder out-of-pit. See tables 2 and 3 for details of the split between pit constrained and out-of-pit deposits.
  6. The pit constrained AuEq cut-off grade of 0.14 g/t was derived from US$1,800/oz Au price, US$24/oz Ag price, 80% process recovery for Ag and Au, US$5.30/tonne process cost and US$1.00/tonne G&A cost. The constraining pit optimization parameters were $1.86/t mineralized mining cost, $1.86/t waste mining cost and 50-degree pit slopes.
  7. The out-of-pit AuEq cut-off grade of 1.5 g/t AuEq was derived from US$1,800/oz Au price, US$24/oz Ag price, $4.00$/lb Cu, $0.95 $/lb Pb, $1.40 $/lb Zn, 85% process recovery for all metals, $50/t mining cost, US$20/tonne process and US$4 G&A cost. The out-of-pit Mineral Resource grade blocks were quantified above the 1.5 g/t AuEq cut-off, below the constraining pit shell within the constraining mineralized wireframes and exhibited sufficient continuity to be considered for cut and fill and long hole mining
  8. The tailings AuEq cut-off grade of 0.30 g/t was derived from US$1,800/oz Au price, US$24/oz Ag price, 85% process recovery for Ag and Au, US$14/t process cost and US$1.00/t G&A cost.
  9. No Mineral Resources are classified as Measured.
  10. AgEq and AuEq calculated at an Ag/Au ratio of 75:1.
  11. Totals may not agree due to rounding
  1. 非矿产储备的矿产资源没有显示出经济可行性。矿产资源的估算可能会受到环境、许可、法律、所有权、税收、社会政治、营销或其他相关问题的重大影响。
  2. 该估计值中的推断矿产资源的置信度低于适用于指示矿产资源的置信度,因此不得转换为矿产储量。有理由预计,通过持续的勘探,大多数推断矿产资源可以升级为指示矿产资源。
  3. 本新闻稿中的矿产资源是根据加拿大矿业、冶金和石油学会(CIM)、CIM矿产资源和储量标准、定义和指南(2014年)由CIM储量定义常设委员会编写并由CIM理事会通过以及CIM最佳实践(2019年)进行估算的。
  4. 从历史上看,矿产资源模型已耗尽了雷区。
  5. 大约 74.7% 的指示盎司和推断出的 22.3% 的 AgeQ 盎司受坑限制,其余未开坑。有关矿坑受限矿床和露天矿床之间划分的详细信息,请参见表 2 和表 3。
  6. 矿坑限制的AueQ临界品位为0.14克/吨,源于每盎司1,800美元的金价、24美元/盎司的银价、80%的银和金的工艺回收率、5.30美元/吨的加工成本以及每吨1.00美元的并购成本。限制矿坑优化参数为1.86美元/吨矿化开采成本、1.86美元/吨废物开采成本和50度的矿坑斜率。
  7. 1.5 g/t AueQ 的露天金当量边界品位来自每盎司金价 1,800 美元、银价 24 美元、每磅铜 4.00 美元、0.95 美元/磅 Pb、1.40 美元/磅 Zn、所有金属的工艺回收率 85%、50美元/吨的开采成本、20美元/吨的工艺和4美元的并购成本。露天矿产资源品位区块的量化程度高于 1.5 g/t AueQ 临界值、限制矿化线框内的限制矿井壳以下,并表现出足够的连续性,可以考虑在开采和填充以及长孔开采中使用
  8. 尾矿 AueQ 截止品位为 0.30 g/t,源自每盎司 1,800 美元的金价、24 美元/盎司的银价、85% 的银和金工艺回收率、14 美元的工艺成本和 1.00 美元/吨的并购成本。
  9. 没有矿产资源被归类为已测量。
  10. AgeQ 和 aueQ 以 75:1 的银/金比率计算。
  11. 由于四舍五入,总数可能不一致

Exploration Potential

探索潜力

Exploration potential at the El Tigre Project is substantial with prospective areas for exploration both down dip and along strike with the disclosed target establishing 7 to 9 Million tonnes at 225 to 265 g/t AgEq for 50 to 75 Moz AgEq.

El Tigre项目的勘探潜力巨大,有潜在的勘探区域既有向下倾斜也有沿线的勘探区域,披露的目标为700万吨至900万吨,年龄为225至265克/吨,年龄为50至75 Moz AgeQ。

Figure 3-Exploration Potential released September 2023

图 3-2023 年 9 月发布的探索潜力

Surface Rights Agreement

表面权利协议

The Company owns royalty-free, 100% of the 6,238 hectares land-package encompassing the footprint of proposed mining operation with no Ejido presence. In addition, the company controls 28,414 hectares of Concessions to conduct exploration along a 25 km strike length of the Sierra Madres.

该公司拥有6,238公顷土地的100%免版税,包括拟议的采矿作业的占地面积,没有Ejido的存在。此外,该公司控制着28,414公顷的特许权,沿着马德雷斯山脉25公里的走向长度进行勘探。

Qualified Persons

合格人员

This PEA was based on information and data supplied by Silver Tiger, and was undertaken by William J. Lewis, B.Sc., P.Geo., Kerrine Azougarh, B.Sc., P.Eng. and Christopher Jacobs, CEng, MIMMM, MBA of Micon International Limited. Of Toronto, Ontario, and David J. Salari, P. Eng. of D.E.N.M. Engineering Ltd are the Qualified Persons as defined under National Instrument 43-101. All Qualified Persons have reviewed and approved the scientific and technical information in this press release.

该PEA基于Silver Tiger提供的信息和数据,由Micon International Limited的理学学士、P.Geo. 理学学士威廉·刘易斯、理学学士、P.Eng. Kerrine Azougarh、CenG、MIMMM MIBA、Christopher Jacobs承担。安大略省多伦多的D.E.N.M. Engineering Ltd.的工程师David J. Salari是国家仪器43-101所定义的合格人员。所有合格人员均已审查并批准本新闻稿中的科学和技术信息。

A Technical Report is being prepared on the Preliminary Economic Assessment in accordance with National Instrument 43-101 ("NI-43-101"), and will be available on the Company's website and SEDAR within 45 days of the date of this news release. The effective date of this Preliminary Economic Assessment is November 1, 2023.

正在根据国家仪器43-101(“NI-43-101”)编写关于初步经济评估的技术报告,该报告将在本新闻发布之日起45天内在公司网站和SEDAR上公布。本初步经济评估的生效日期为2023年11月1日。

VRIFY Slide Deck and 3D Presentation - Silver Tiger's El Tigre Project

VRIFY 幻灯片和 3D 演示文稿——Silver Tiger 的 El Tigre 项目

VRIFY is a platform being used by companies to communicate with investors using 360° virtual tours of remote mining assets, 3D models and interactive presentations. VRIFY can be accessed by website and with the VRIFY iOS and Android apps.

VRIFY是公司使用的平台,通过远程采矿资产的360°虚拟导览、3D模型和交互式演示与投资者进行沟通。VRIFY 可以通过网站访问,也可以通过 VRIFY iOS 和 Android 应用程序访问。

Access the Silver Tiger Metals Inc. Company Profile on VRIFY at:

在 VRIFY 上访问 Silver Tiger Metals Inc. 公司简介,网址为:

The VRIFY Slide Deck and 3D Presentation for Silver Tiger Metals Inc. can be viewed at: and on the Corporation's website at: .

Silver Tiger Metals Inc. 的 VRIFY Slide Deck 和 3D 演示文稿可以在以下网址查看:也可以在公司的网站上查看:。

About Silver Tiger and the El Tigre Historic Mine District

关于 Silver Tiger 和 El Tigre 历史矿区

Silver Tiger Metals Inc. is a Canadian company whose management has more than 25 years' experience discovering, financing and building large epithermal silver projects in Mexico. Silver Tiger's 100% owned 28,414 hectare Historic El Tigre Mining District is located in Sonora, Mexico. Principled environmental, social and governance practices are core priorities at Silver Tiger.

Silver Tiger Metals Inc. 是一家加拿大公司,其管理层在墨西哥发现、融资和建造大型超热液银项目拥有超过25年的经验。Silver Tiger拥有的28,414公顷历史悠久的埃尔蒂格雷矿区位于墨西哥索诺拉州。有原则的环境、社会和治理实践是Silver Tiger的核心优先事项。

The El Tigre historic mine district is located in Sonora, Mexico and lies at the northern end of the Sierra Madre silver and gold belt which hosts many epithermal silver and gold deposits, including Dolores, Santa Elena and Las Chispas at the northern end. In 1896, gold was first discovered on the property in the Gold Hill area and mining started with the Brown Shaft in 1903. The focus soon changed to mining high-grade silver veins in the area with production coming from 3 parallel veins the El Tigre Vein, the Seitz Kelley Vein and the Sooy Vein. Underground mining on the middle El Tigre Vein extended 1,450 metres along strike and was mined on 14 levels to a depth of approximately 450 metres. The Seitz Kelley Vein was mined along strike for 1 kilometre to a depth of approximately 200 meters. The Sooy Vein was only mined along strike for 250 metres to a depth of approximately 150 metres. Mining abruptly stopped on all 3 of these veins when the price of silver collapsed to less than 20¢ per ounce with the onset of the Great Depression. By the time the mine closed in 1930, it is reported to have produced a total of 353,000 ounces of gold and 67.4 Million ounces of silver from 1.87 Million tons (Craig, 2012). The average grade mined during this period was over 2 kilograms silver equivalent per ton.

埃尔蒂格雷历史矿区位于墨西哥索诺拉,位于马德雷山脉银金矿带的北端,那里有许多超热银和金矿床,包括位于北端的多洛雷斯、圣埃琳娜和拉斯希斯帕斯。1896 年,在金山地区的土地上首次发现了黄金,1903 年,棕色竖井开始了采矿。重点很快转向了在该地区开采高等级银矿脉,产量来自三条平行矿脉,即艾尔泰格雷矿脉、塞兹凯利矿脉和苏伊矿脉。El Tigre Vein中部的地下采矿沿着走向延伸了1,450米,在14层上进行了开采,深度约为450米。Seitz Kelley Vein 沿着走向线埋设地雷 1 千米,深度约为 200 米。Sooy Vein 仅在走向沿途开采了 250 米,深度约为 150 米。随着大萧条的开始,白银价格暴跌至每盎司不到20美分,这三条矿脉的采矿突然停止了。据报道,到1930年该矿关闭时,该矿已从187万吨中共生产了35.3万盎司的黄金和6,740万盎司的白银(Craig,2012年)。在此期间,开采的平均等级超过每吨2千克白银当量。

For further information, please contact:

欲了解更多信息,请联系:

Glenn Jessome
President and CEO
902 492 0298
jessome@silvertigermetals.com

Glenn Jessome
总裁兼首席执行官
902 492 0298
jessome@silvertigermetals.com

CAUTIONARY STATEMENT:

警示声明:

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

多伦多证券交易所风险交易所及其监管服务提供商(该术语在多伦多证券交易所风险交易所的政策中定义)均不对本新闻稿的充分性或准确性承担责任。

This News Release includes certain "forward-looking statements". All statements other than statements of historical fact included in this release, including, without limitation, statements regarding potential mineralization, Mineral Resources and Reserves, the ability to convert Inferred Mineral Resources to Indicated Mineral Resources, the ability to complete future drilling programs and infill sampling, the ability to extend Mineral Resource blocks, the similarity of mineralization at El Tigre to Delores, Santa Elena and Chispas, exploration results, and future plans and objectives of Silver Tiger, are forward-looking statements that involve various risks and uncertainties. Forward-looking statements are frequently characterized by words such as "may", "is expected to", "anticipates", "estimates", "intends", "plans", "projection", "could", "vision", "goals", "objective" and "outlook" and other similar words. Although Silver Tiger believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, there can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from Silver Tiger's expectations include risks and uncertainties related to exploration, development, operations, commodity prices and global financial volatility, risk and uncertainties of operating in a foreign jurisdiction as well as additional risks described from time to time in the filings made by Silver Tiger with securities regulators.

本新闻稿包括某些 “前瞻性陈述”。除本新闻稿中包含的历史事实陈述以外的所有陈述,包括但不限于有关潜在矿化、矿产资源和储量、将推断矿产资源转换为指示矿产资源的能力、完成未来钻探计划和填充采样的能力、扩展矿产资源区块的能力、El Tigre矿化与德洛雷斯、圣埃琳娜和奇斯帕斯的相似性、勘探结果以及Silver Tiger的未来计划和目标的陈述前瞻性涉及各种风险和不确定性的陈述。前瞻性陈述通常以 “可能”、“预期”、“预期”、“估计”、“打算”、“计划”、“预测”、“可能”、“愿景”、“目标”、“目标”、“目标” 和 “展望” 等词语以及其他类似词汇为特征。尽管Silver Tiger认为此类前瞻性陈述中表达的预期是基于合理的假设,但无法保证此类陈述会被证明是准确的,实际结果和未来事件可能与此类陈述中的预期存在重大差异。可能导致实际业绩与Silver Tiger的预期存在重大差异的重要因素包括与勘探、开发、运营、大宗商品价格和全球金融波动相关的风险和不确定性、在外国司法管辖区运营的风险和不确定性,以及Silver Tiger在向证券监管机构提交的文件中不时描述的其他风险。

SOURCE: Silver Tiger Metals Inc.

来源: 银虎金属公司


View source version on accesswire.com:
在 accesswire.com 上查看源代码版本:

译文内容由第三方软件翻译。


以上内容仅用作资讯或教育之目的,不构成与富途相关的任何投资建议。富途竭力但不能保证上述全部内容的真实性、准确性和原创性。
    抢沙发