HIGHLIGHTS

高光

  • Construction progress continues to be made at Araguaia
    • Strong safety performance, no lost time injuries with close to 5.1 million hours worked
    • Rotary Kiln sections have been installed on the support piers
    • The furnace shell is complete with roof installation underway
    • All critical equipment packages have been contracted and are either on site or en route to site
    • As of 30 September, 138,000 tonnes of ore averaging 1.92% Ni has been stockpiled
    • Commissioning of the 126 km (230kV) power transmission line underway
  • US$429 million has been spent at Araguaia as of 30 September 2023
  • As stated on 2 October 2023, Reta Engenharia has been retained to complete a detailed capital cost and schedule analysis which is expected to be completed by mid Q4-2023
  • The Company is continuing to progress construction activities while advancing financing discussions with its cornerstone shareholders and lenders
  • Araguaia Nickel Project Line 2 Feasibility Study ("FS"), which aims to double nickel production from 14,500 tonnes per annum to 29,000 tonnes per annum, to be published in mid Q4-2023
  • 在Araguaia的建設繼續取得進展
    • 強大的安全性能,沒有損失時間傷害,工作時間接近510萬小時
    • 迴轉窯段已安裝在支承墩上
    • 爐殼已完成,正在進行爐頂安裝
    • 所有關鍵設備包已簽訂合同,已在現場或運往現場的途中
    • 截至9月30日,已儲存13.8萬噸平均含鎳1.92%的礦石
    • 126公里(230千伏)輸電線路正在調試
  • 截至2023年9月30日,已在Araguaia花費了4.29億美元
  • 如2023年10月2日所述,已聘請Reta Engenharia完成詳細的資本成本和時間表分析,預計將於2023年第四季度中期完成
  • 公司繼續推進建設活動,同時推進與基石股東和貸款人的融資談判
  • Araguaia鎳專案2號線可行性研究,目標是將鎳產量從每年14,500噸增加一倍至29,000噸,將於2023年第四季度中期公佈

LONDON, UK / ACCESSWIRE / October 23, 2023 / Horizonte Minerals Plc (AIM:HZM)(TSX:HZM) ("Horizonte" or the "Company"), the nickel company developing two Tier 1 assets in Brazil, reports that construction activities continue to progress well at its Araguaia Nickel Project ("Araguaia" or "the Project"). As of 30 September 2023, US$429 million has been spent on Araguaia with progress made across key work fronts and no interruptions to date on construction activities.

英國倫敦/ACCESSWIRE/2023年10月23日/Horizonte Minerals Plc(AIM:HZM)(多倫多證券交易所代碼:HZM)(“Horizonte”或“公司”)在巴西開發兩個一級資產的鎳公司報告稱,其Araguaia鎳專案(“Araguaia”或“The Project”)的建設活動繼續進展順利。截至2023年9月30日,已在Araguaia上花費了4.29億美元,各主要工作戰線都取得了進展,建設活動迄今沒有中斷。

As stated in the press release dated 2 October 2023, a number of factors arising from the completion of the detailed engineering work has led to an increase in material and quantities, scope changes, increased costs around the main electromechanical erection contract and increased duration on delivery schedule. These changes require additional financing resulting in an expected increase in the overall Project capital requirement by at least 35% (from the current capex budget of US$537m) and delay of first production to Q3-2024. Reta Engenharia is expected to complete its capital cost and schedule analysis report, following which an independent technical advisor, nominated by Senior Lenders will review the updated costs with targeted completion by mid Q4-2023.

如2023年10月2日的新聞稿所述,詳細工程工作完成後產生的多個因素導致材料和數量增加、範圍改變、主要機電安裝合同成本增加以及交付進度延長。這些變化需要額外的融資,從而導致專案總體資本需求預期增加至少35%(目前的資本支出預算為5.37億美元),並將首批生產推遲到2024年第三季度。Reta Engenharia預計將完成其資本成本和時間表分析報告,隨後由高級貸款人提名的獨立技術顧問將審查更新的成本,目標是在第四季度至2023年中期完成。

Jeremy Martin, CEO of Horizonte, commented: "Despite the current challenges, I am pleased to report that construction activities at the Araguaia Project continue to progress well, with a strong safety performance to date.

Horizonte首席執行官傑裡米·馬丁評論道: 儘管目前面臨挑戰,但我很高興地報告,Araguaia專案的建設活動繼續進展順利,迄今安全表現強勁。

"Notwithstanding the expected increase in capital, the Araguaia project remains a Tier 1 nickel project with lower quartile C1 cash costs, and a long mine life of 28 years producing a high grade, low impurity FeNi product. Discussions with the Company's major shareholders and lenders to fund the project to completion are progressing."

儘管預計將增加資本,Araguaia專案仍是一個一級鎳專案,具有較低的四分之一現金成本,以及長達28年的礦山壽命,生產高品位、低雜質的FeNi產品。與公司主要股東和貸款人的談判正在進行中,以資助該專案完成。

CAPITAL COST REVIEW PROCESS

資本成本審核流程

Reta Engenharia's detailed capital cost and schedule analysis is on-going, with the updated estimate being assessed to meet the requirements of AACEI Class 1, improved from the estimate utilised in September 2022.

Reta Engenharia的詳細資本成本和時間表分析正在進行中,正在評估最新的估計數,以滿足AACEI 1級的要求,比2022年9月使用的估計數有所改善。

Principal capital changes are linked to the following:

本金資本變動與以下因素相關:

  • Civil works: the development of engineering maturity and identification of new scopes to the project resulted in increases in civil quantities (concrete, rebar and formwork) and the corresponding rise in the installation costs. These changes relate to the water storage reservoir, the water abstraction pipeline, selected major equipment packages and equipment interfaces.
  • Electromechanical (EM) assembly: increased equipment and materials quantities have resulted from the completion of the critical detailed engineering, and the shift of more EM activities into the wet season given the expected delay to 3Q-2024. This represents a significant percentage of the cost increase given the lower productivity in the wet season and increased quantities.
  • Refractory: the cost to install 4.3 kt of refractory was significantly underestimated.
  • Vendor delays: one of the vendors have not been able to deliver key packages in line with the project timeline leading to termination of the contract and the sourcing of alternatives at higher prices.
  • Schedule extension: given the above and the expected schedule delay of around six months, there is an associated increase in costs and working capital linked to the increased schedule duration.
  • 土木工程:隨著工程成熟度的發展和項目新範圍的確定,土建工程量(混凝土、鋼筋和模板)增加,安裝費用也相應增加。這些變化涉及蓄水池、取水管道、選定的主要成套設備和設備接口。
  • 機電(EM)元件:設備和材料數量增加的原因是完成了關鍵的詳細工程,以及由於預計延遲到2024年第三季度,更多的EM活動將轉移到雨季。考慮到雨季生產率較低和數量增加,這在成本增加中佔了很大比例。
  • 耐火材料:安裝4.3kt耐火材料的成本被嚴重低估。
  • 供應商延遲:其中一家供應商未能按照專案時間表交付關鍵包裹,導致合同終止,並以更高的價格採購替代品。
  • 日程延期:鑑於上述情況以及預計約六個月的時間表延遲,與延長時間表持續時間相關的成本和營運資金增加。

More detailed information will be given once the final engineering study is complete by mid Q4-2023.

更詳細的資訊將在最終工程研究於2023年第四季度中期完成後提供。

Click on, or paste the following link into your web browser, to view the full announcement.

點擊或將以下鏈接黏貼到您的Web瀏覽器中,以查看完整的公告。

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit .

這些資訊由倫敦證券交易所的新聞服務RNS提供。RNS被金融市場行為監管局批准為英國的主要資訊提供商。與該資訊的使用和分發有關的條款和條件可能適用。欲瞭解更多資訊,請聯繫rns@lSeg.com或訪問。

SOURCE: Horizonte Minerals PLC

資料來源:Horizonte Minerals PLC


View source version on accesswire.com:
在Accesswire.com上查看源代碼版本:

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論