share_log

ZincX Resources Closes Private Placement With Ross Beaty

ZincX Resources Closes Private Placement With Ross Beaty

ZincX Resources 與 Ross Beaty 完成私募配售
Accesswire ·  2023/07/06 15:05

VANCOUVER, BC / ACCESSWIRE / July 6, 2023 / ZincX Resources Corp. ("ZincX" or the "Company"), (TSXV:ZNX)(OTCQB:ZNCXF)(FRA:M9R) is pleased to announce that the Company has closed its non-brokered private placement of 10,000,000 common shares of the Company at a price of $0.10 per share to raise gross proceeds of $1,000,000.

溫哥華,BC/ACCESSWIRE/2023年7月6日/ZincX Resources Corp.(“ZincX”或“公司”),(多倫多證券交易所股票代碼:ZNX)(OTCQB:ZNCXF)(FRA:M9R)很高興地宣佈,本公司已完成以每股0.10美元的價格定向增發本公司10,000,000股普通股,以籌集1,000,000美元的總收益。

Peeyush Varshney, Chief Executive Officer of ZincX, commented, "We are pleased to welcome well known mining entrepreneur Ross Beaty as a new significant shareholder of the Company."

ZincX首席執行官Peeyush Varshney表示:“我們很高興歡迎著名礦業企業家Ross Beaty成為公司新的重要股東。”

The Company intends to use the proceeds from the private placement to continue to advance the Company's Akie and Kechika Regional projects in British Columbia and for working capital purposes.

該公司打算利用私募所得資金繼續推進公司在不列顛哥倫比亞省的Akie和Kechika地區專案,並將其用作營運資金。

All securities issued will be subject to a four-month hold period expiring on November 7, 2023.

所有發行的證券將有四個月的持有期,至2023年11月7日到期。

The private placement remains subject to the final approval of the TSX Venture Exchange.

定向增發仍有待多倫多證券交易所創業板的最終批准。

The Akie Zn-Pb-Ag Project

AKIE鋅鉛銀專案

The 100% owned Akie property is situated within the Kechika Trough, the southernmost area of the regionally extensive Paleozoic Selwyn Basin and one of the most prolific sedimentary basins in the world for the occurrence of SEDEX zinc-lead-silver and stratiform barite deposits.

全資擁有的Akie地產位於Kechika海槽內,Kechika海槽是區域廣泛的古生代Selwyn盆地的最南端,也是世界上最多產Sedex鋅鉛銀和層狀重晶石礦床的沉積盆地之一。

Drilling on the Akie property by ZincX Resources since 2005 has identified a significant body of baritic-zinc-lead SEDEX mineralization known as the Cardiac Creek deposit. The deposit is hosted by siliceous, carbonaceous, fine-grained clastic rocks of the Middle to Late Devonian Gunsteel Formation.

自2005年以來,ZincX Resources在Akie礦區進行的鑽探發現了一個重要的鎂鋅鉛Sedex礦化礦體,稱為心臟溪礦床。礦床賦存於中、晚泥盆世滾鋼組硅質、碳質、細粒碎屑岩中。

The Company updated the estimate of mineral resources at Cardiac Creek in 2018, as follows:

該公司更新了2018年哈迪克克裡克的礦產資源估計,如下:

5% Zinc Cut-Off Grade

Contained Metal:

Category

Tonnes
(million)

Zn (%)

Pb (%)

Ag (g/t)

Zn (B lbs)

Pb (B lbs)

Ag (M oz)

Indicated

22.7

8.32

1.61

14.1

4.162

0.804

10.3

Inferred

7.5

7.04

1.24

12.0

1.169

0.205

2.9

5%鋅下限品位

所含金屬:

類別

公噸
(百萬)

鋅(%)

PB(%)

銀(克/噸)

鋅(B磅)

PB(B磅)

銀(百萬盎司)

已指示

22.7

8.32

1.61

14.1

4.162

0.804

10.3

推論

7.5

7.04

1.24

12.0

1.169

0.205

2.9

The Company announced robust positive results from the 2018 Preliminary Economic Assessment (PEA). The PEA envisages a conventional underground mine and concentrator operation with an average production rate of 4,000 tonnes per day. The mine will have an 18-year life with potential to extend the life-of-mine (LOM) through resource expansion at depth. Key parameters for the PEA are as follows:

該公司宣佈了2018年初步經濟評估(PEA)的強勁積極結果。PEA設想了一個常規的地下礦山和選礦廠作業,平均日產量為4,000噸。該礦將擁有18年的壽命,有可能通過在深部擴大資源來延長礦山壽命(LOM)。PEA的關鍵參數如下:

Parameter

Base Case1

Tonnes Mined

25.8 Mt

Mined Head Grades

7.6% Zn; 1.5% Pb; 13.08 g/t Ag

Tonnes Milled

19.7 Mt

Milled Head Grades (after DMS2 upgrade)

10.0% Zn; 1.9% Pb; 17.17 g/t Ag

Total Payable Metal (LOM)

$3,960M3

Initial CAPEX

$302.3M including $45.7M contingency

LOM Total CAPEX

$617.9M including $58.5M contingency

All-in Total OPEX

$102.4 per tonne milled

Pre-Tax NPV7%

$649M

Pre-Tax IRR

35%

Pre-Tax Payback

2.6 years

After-Tax NPV7%

$401M

After-Tax IRR

27%

After-Tax Payback

3.2 years

參數

基本情況1

開採的噸數

25.8公噸

礦頭品位

7.6%鋅;1.5%鉛;13.08g/t銀

已碾磨噸數

19.7公噸

磨頭牌號(DMS之後2.升級)

10.0%鋅;1.9%鉛;17.17g/t銀

應付金屬合計(LOM)

39.6億美元3.

初始資本支出

3.023億美元,包括4570萬美元的應急費用

LOM總資本支出

6.179億美元,包括5850萬美元的應急費用

All-In Total運營支出

碾磨每噸$102.4

稅前淨現值7%

6.49億美元

稅前內部收益率

35%

稅前回款

2.6年

稅後淨現值7%

4.01億美元

稅後內部收益率

百分之二十七

稅後回收

3.2年

1. The base case used metal prices are calculated from the 3 year trailing average coupled with two year forward projection of the average price; and are: US$1.21/lb for zinc, US$1.00/lb for lead and US$16.95 for silver. A CDN$/US$ exchange rate of 0.77 was used. The NPV discount rate is 7%. 2. DMS = dense media separation. 3. All dollar amounts expressed in Canadian dollars.

1.所用金屬價格的基本情況是根據三年的歷史平均價格加上兩年平均價格的遠期預測計算出來的;鋅為1.21美元/磅,鉛為1.00美元/磅,白銀為16.95美元。使用的是0.77加元/美元的匯率。淨現值貼現率為7%。2.DMS=重介質分離。3.所有以加元表示的美元金額。

The PEA is considered preliminary in nature and includes mineral resources, including inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mineral resources that are not mineral reserves have not yet demonstrated economic viability. Due to the uncertainty that may be attached to mineral resources, it cannot be assumed that all or any part of a mineral resource will be upgraded to mineral reserves. Therefore, there is no certainty that the results concluded in the PEA will be realized.

PEA被認為是初步性質的,包括礦產資源,包括被認為在地質學上過於投機的推斷礦產資源,因此無法將其歸類為礦產儲量。不屬於礦產儲備的礦產資源尚未顯示出經濟可行性。由於礦產資源可能存在不確定性,不能假設全部或部分礦產資源將升級為礦產儲量。因此,PEA中得出的結果是否會實現並不確定。

Kechika Regional Project

克奇卡地區專案

In addition to the Akie Project, the Company owns 100% of eight of eleven large, contiguous property blocks that comprise the Kechika Regional Project including the advanced Mt. Alcock prospect. The Kechika Regional Project also includes the Pie, Yuen and Cirque East properties which the Company maintains a significant 49% interest with partners Teck Resources Limited (TSX: TECK.B) and Korea Zinc Co. Ltd holding 51%. These properties collectively extend northwest from the Akie property for approximately 140 kilometres covering the highly prospective Gunsteel Formation shale; the main host rock for known SEDEX zinc-lead-silver deposits in the Kechika Trough of northeastern British Columbia. These projects are located approximately 260 kilometres north northwest of the town of Mackenzie, British Columbia, Canada.

除了Akie專案外,該公司還擁有組成Kechika地區專案的11個連續大型物業區塊中8個的100%權益,其中包括Advanced Mt.阿爾科克的前景。凱奇卡地區專案還包括派、園和馬戲團東物業,公司與合作夥伴泰克資源有限公司(多倫多證券交易所股票代碼:TECK.B)和韓國鋅有限公司持有51%的股份,持有這些物業49%的重大權益。這些物業從Akie地產向西北方向延伸約140公里,覆蓋極具前景的GunSteel組葉巖,該葉巖是不列顛哥倫比亞省東北部Kechika海槽已知的Sedex鋅鉛銀礦床的主要容礦岩石。這些專案位於加拿大不列顛哥倫比亞省麥肯齊鎮西北偏北約260公里處。

Zinc (Zn)

鋅(Zin)

Zinc is one of many critical metals facilitating the transition to a low-carbon and greener future and is used in renewable energy storage systems and through the protection of steel to improve its durability and service life in solar and wind turbine applications. The primary uses of zinc are the galvanization of steel protecting against corrosion due to weather conditions, the production of brass and bronze, and in die-casting to produce a wide range of metal products. In agriculture, zinc can also increase crop yields and crop quality and is an essential nutrient in human development and disease prevention.

鋅是促進向低碳和更綠色未來過渡的許多關鍵金屬之一,用於可再生能源存儲系統,並在太陽能和風力渦輪機應用中通過保護鋼來提高其耐用性和使用壽命。鋅的主要用途是對鋼進行鍍鋅,防止因天氣條件而造成的腐蝕,生產黃銅和青銅,並用於壓鑄生產各種金屬產品。在農業中,鋅還可以增加作物產量和作物質量,是人類發育和疾病預防的重要營養物質。

Ken MacDonald P.Geo., Vice President of Exploration for the Company, is the designated Qualified Person as defined by National Instrument 43-101 and is responsible for the technical information contained in this release. Mike Makarenko P.Eng, JDS Energy and Mining, is the designated Qualified Person as defined by National Instrument 43-101 and is responsible for the PEA technical information contained in this release.

本公司勘探部副總裁肯·麥克唐納·P·吉奧是國家儀器43-101規定的指定合格人員,對本新聞稿中包含的技術資訊負責。JDS能源與礦業公司的Mike·馬卡連科·P·恩格是National Instrument 43-101中指定的合格人員,負責本新聞稿中包含的PEA技術資訊。

The TSX Venture Exchange has neither approved nor disapproved the contents of this press release.

多倫多證券交易所創業板既沒有批准也沒有反對本新聞稿的內容。

ON BEHALF OF THE BOARD OF DIRECTORS

我代表董事會

ZINCX RESOURCES CORP.

ZINCX資源公司。

"PEEYUSH VARSHNEY"

《皮耶什·瓦什尼》

PEEYUSH VARSHNEY, LL.B
CEO & CHAIRMAN

Peeyush Varshney,LL.B
首席執行官兼董事長

Contact:

聯繫方式:

Investor Relations
Phone (604) 684-2181
info@zincxresources.com

投資者關係
電話:(604)684-2181
郵箱:Info@zincxresource ces.com

SOURCE: ZincX Resources Corp.

資料來源:ZincX Resources Corp.


View source version on accesswire.com:
在Accesswire.com上查看源代碼版本:

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論