EnCore Energy Provides Alta Mesa ISR Uranium Central Processing Plant Update and New Discovery

EnCore Energy Provides Alta Mesa ISR Uranium Central Processing Plant Update and New Discovery

eNcore Energy 提供 Alta Mesa ISR 铀中央处理厂更新和新发现
PR Newswire ·  2023/05/18 19:00

NYSE American: EU
TSXV: EU

纽约证券交易所美国证券交易所:欧盟
TSXV:欧盟

CORPUS CHRISTI, Texas, May 18, 2023 /PRNewswire/ - enCore Energy Corp. (NYSE American: EU) (TSXV: EU) (the "Company" or "enCore") today announced the South Texas Alta Mesa In Situ Recovery("ISR") Uranium Central Processing Plant upgrades and refurbishments are ahead of schedule and under budget. This follows the previously announced (EU News Release - March 15, 2023) formal production decision for the resumption of uranium production in early 2024. The Company also announces continuing positive results from the wellfield delineation drill program and a newly discovered mineralized zone at the Alta Mesa wellfield.

得克萨斯州科珀斯克里斯蒂2023年5月18日 /PRNewswire/- eNore Energy (纽约证券交易所美国股票代码:EU)(多伦多证券交易所:EU)(the”公司“或”eNCore”)今天宣布,南德克萨斯州阿尔塔梅萨原地回收(“ISR”)铀中央处理厂的升级和翻新已提前且不在预算之内。这是继先前宣布的(欧盟新闻稿- 2023年3月15日)关于在2024年初恢复铀生产的正式生产决定。该公司还宣布,井场划界钻探计划以及在阿尔塔梅萨井田新发现的矿化区继续取得积极成果。

Presently there are 6 drill rigs working at Alta Mesa with a 7th rig to be added shortly. The wellfield drilling operations, within Production Authorization Area 7 (PAA), which commenced in March 2023, are advancing rapidly with 81 holes drilled to date with drilling delineating the roll front mineralization within PAA-7. The Middle C unit, a productive sand, essential for ISR, in PAA-3 was not previously known to be mineralized under PAA-7. The drilling program has encountered unexpected significant grade in the Middle C unit underlying PAA-7, with grade thicknesses multiplied by the thickness of the mineralization at or above the cutoff value] ranging from 0.481 to 1.888 in 4 of the holes. Further drilling along trend will continue to delineate this new mineralized sand and is likely to increase the overall mineralization within PAA-7.

目前有 6 台钻机在 Alta Mesa 工作,其中 7 台第四 不久将添加装备。7号生产授权区(PAA)内的井田钻探作业始于 2023 年 3 月,正在迅速推进,迄今已钻探了 81 个孔,钻探描绘了 PAA-7 内的轧前矿化情况。以前未知 PAA-3 中的 Middle C 单元是一种高产沙子,对 ISR 至关重要,在 PAA-7 下会矿化。钻探计划在 PAA-7 下方的 Middle C 单元中遇到了意想不到的高品位,其中 4 个孔的等级厚度乘以等于或高于临界值] 的矿化厚度从 0.481 到 1.888 不等。沿着趋势进一步钻探将继续勾勒出这种新的矿化沙的轮廓,并有可能增加 PAA-7 内的整体矿化程度。

Of these holes, 14 are being cased as injection wells and 14 as recovery wells while further refined delineation drilling within the PAA continues to establish the exact pattern of injection and recovery wells from which to maximize production efficiency.

在这些孔中,有14个被用作注入井,14个作为回收井,而在PAA内部进一步完善的划界钻探继续确定注入和回收井的确切模式,从而最大限度地提高生产效率。

Significant highlights include:

重要亮点包括:

Drill Hole

Mineralized Horizon1

Grade

% U3O8

Thickness

(feet)

Grade
Thickness
(GT)

67-10

Lower C-upper 1

0.197

11

2.140

61-17

Lower C-upper 1

0.363

3.0

1.271

61-18

Lower C-upper 1

Lower C-upper 2

Lower C-lower 1

0.139

0.297

0.293

3.5

4.0

3.5

0.487

1.187

1.027

74-95

Lower C-upper 2

Lower C-lower 1

0.293

0.353

4.5

8.0

1.319

2.827

73-95

Middle C

0.146

3.5

0.509

55-15

Middle C

Lower C-lower 1

0.272

0.131

5.5

3.0

1.496

0.392

钻孔

矿化地平线1

等级

% U3O8

厚度

(英尺)

等级
厚度
(GT)

67-10

Lower c-upper 1

0.197

11

2.140

61-17

Lower c-upper 1

0.363

3.0

1.271

61-18

Lower c-upper 1

Lower c-upper 2

Lower c-lower 1

0.139

0.297

0.293

3.5

4.0

3.5

0.487

1.187

1.027

74-95

Lower c-upper 2

Lower c-lower 1

0.293

0.353

4.5

8.0

1.319

2.827

73-95

中间 C

0.146

3.5

0.509

55-15

中间 C

Lower c-lower 1

0.272

0.131

5.5

3.0

1.496

0.392

1-

All intercepts are located in the PAA-7 at Alta Mesa, which hosts mineralization within the Goliad Formation. The Company has identified five saturated (required for ISR), mineralized sandstone horizons within the Goliad Formation lying approximately 400 to 520 feet below the surface. The water level is located approximately 120 feet below surface.

1-

所有截面都位于 Alta Mesa 的 PAA-7 中,那里是戈利亚德组内矿化的地方。该公司已在戈利亚德组内发现了五个饱和(ISR 必需的)矿化砂岩地层,位于地表以下约400至520英尺处。水位位于地表以下大约 120 英尺处。

The Alta Mesa Central Processing Plant (CPP) is advancing towards a restart of production and presently completing minor scheduled renovations with equipment upgrades and refurbishments underway. A thorough equipment evaluation determined 90% of the piping and valves are operational with limited maintenance requirements. Of 40 pumps and motors evaluated, including major pumps, 30 are being rebuilt and refurbished on site mitigating some supply chain risks. Longer lead time items now ordered are not critical for initial plant production start-up.

阿尔塔梅萨中央加工厂(CPP)正朝着重启生产的方向迈进,目前正在完成计划中的小规模翻新,设备升级和翻新正在进行中。一项全面的设备评估确定,90% 的管道和阀门在维护要求有限的情况下正常运行。在评估的40台泵和发动机中,包括大型泵,有30台正在现场重建和翻新,以缓解一些供应链风险。现在订购的更长交货时间对工厂的初始生产启动并不重要。

To view the Alta Mesa project maps and enCore Energy's South Texas projects please visit:

查看 Alta Mesa 项目地图和 eNCore Energy 的地图 南德克萨斯州 项目请访问:

Alta Mesa In-Situ Recovery ("ISR") Uranium Central Processing Plant ("Alta Mesa CPP") & Project
阿尔塔梅萨原地回收(“ISR”)铀中央处理厂(“Alta Mesa CPP”)和项目

The Alta Mesa CPP and project is a fully licensed and constructed ISR uranium project and CPP currently on standby, located on 200,000+ acres of private land in the state of Texas. Alta Mesa will be enCore's second producing location following resumption of uranium production at the South Texas Rosita Uranium Processing Plant ("Rosita") scheduled for 2023.

Alta Mesa CPP和项目是一个获得充分许可和建造的ISR铀项目,CPP目前处于待命状态,位于该州超过20万英亩的私人土地上 德州。继计划于2023年恢复南德克萨斯罗西塔铀加工厂(“Rosita”)的铀生产之后,阿尔塔梅萨将成为eNcore的第二个生产基地。

Total operating capacity is 1.5 million lbs U3O8 (uranium) per year. Alta Mesa historically produced nearly 5 million lbs of U3O8 between 2005 and 2013, when full production was curtailed as a result of low uranium prices at the time.

总运营容量为 150 万磅 U3O8 (铀)每年。Alta Mesa 历史上生产了近 500 万磅的U3O8 在2005年至2013年之间,当时由于铀价格低迷,全部产量被削减。

Alta Mesa Processing Plant and Project highlights include:

阿尔塔梅萨加工厂和项目亮点包括:

  • The Alta Mesa CPP is enCore's third fully licensed production facility, along with Rosita and Kingsville Dome CPP's, all located in the business-friendly state of Texas. There are only 11 licensed and constructed uranium production facilities in all of the United States (US);
  • The Alta Mesa Processing Plant can reach commercial production levels with limited required capital, from funds on hand, within an estimated 10 months of announced production decision;
  • Advancing the Alta Mesa CPP, in conjunction with planned production in 2023 at the Rosita CPP, will cement enCore Energy's position as the early leader in In-Situ Recovery (ISR) uranium production in the US;
  • Alta Mesa's operations are located on private land, with 100% of minerals privately owned, and in a supportive jurisdiction with primary regulatory authority residing with the State of Texas;
  • The Alta Mesa Processing Plant utilizes well-known ISR technology to extract uranium in a non-invasive process using natural groundwater and oxygen, coupled with a proven ion exchange process, to recover the uranium.
  • Alta Mesa CPP 是 eNCore 的第三家获得全面许可的生产设施,与 Rosita 和 Kingsville Dome CPP 一样,都位于商业友好型州 德州。所有国家只有11个获得许可和建造的铀生产设施 美国 (我们);
  • 在宣布生产决定后的10个月内,阿尔塔梅萨加工厂可以用有限的所需资金从现有资金中达到商业生产水平;
  • 推进Alta Mesa CPP,加上计划在2023年在Rosita CPP上进行生产,将巩固eNorgy作为美国原地回收(ISR)铀生产早期领导者的地位;
  • Alta Mesa的业务位于私人土地上,100%的矿产均为私人所有,并且位于支持性司法管辖区,主要监管机构设在私人土地上 得克萨斯州;
  • 阿尔塔梅萨加工厂利用众所周知的ISR技术,使用天然地下水和氧气以非侵入性工艺提取铀,再加上经过验证的离子交换工艺,以回收铀。

Alta Mesa & Mesteña Grande Mineral
Resource Summary (0.30 GT cut-off)1,2

Tons

('000)

Avg. Grade

(% U3O8)

Pounds

('000)

Total Measured Mineral Resource1

54

0.152

164

Alta Mesa Indicated Mineral Resource

1,397

0.106

2,959

Mesteña Grande Indicated Mineral Resource

119

0.120

287

Total Measured & Indicated Resources

1,570

0.109

3,410

Alta Mesa Inferred Mineral Resource

1,263

0.126

3,192

Mesteña Grande Inferred Mineral Resource

5,733

0.119

13,601

Total Inferred Resources

6,996

0.120

16,793

Alta Mesa & MestenaGrand Minera
资源摘要(0.30 GT 截止值)1,2

('000)

平均。等级

(% U)3O8)

英镑

('000)

测得的矿产资源总量1

54

0.152

164

阿尔塔梅萨指明的矿产资源

1,397

0.106

2,959

MestenaGrande 指定矿产资源

119

0.120

287

测得和指示的资源总量

1,570

0.109

3,410

阿尔塔梅萨推断的矿产资源

1,263

0.126

3192

Mestena Grande 推断的矿产资源

5,733

0.119

13,601

推断资源总数

6,996

0.120

16,793

1.2 Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields. Wellfield recovery factors have not been applied to indicated and inferred mineral resources. As reported in the NI-43-101 Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, USA completed by Doug Beahm, PE, PG, of BRS Engineering. (Effective January 19, 2023).

1.2 代表估计可在现有井田内开采的现地矿产资源部分。未将井田恢复系数应用于已指明和推断的矿产资源。正如报道的那样 美国德克萨斯州布鲁克斯县和吉姆·霍格县阿尔塔梅萨铀项目的 NI-43-101 技术报告摘要由BRS Engineering的PE、PG Doug Beahm完成。(2023 年 1 月 19 日生效)

The Company advises that it is not basing its production decisions at Alta Mesa or Rosita on a feasibility study of mineral reserves demonstrating economic and technical viability. The production decision is based on known past In-Situ Recovery (ISR) and processing operations at these two production facilities and surrounding lands. However, the Company understands that there is increased uncertainty, and consequently a higher risk of failure, when production is undertaken in advance of a feasibility study. In addition, the mineral resource at Alta Mesa includes inferred resources which are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. The Company has determined to proceed with a production decision based on past operations at Alta Mesa and Rosita, including past ISR operations in the known mineral resource areas.

该公司表示,其在Alta Mesa或Rosita的生产决策并不是基于一项表明经济和技术可行性的矿产储量可行性研究。生产决策基于过去在这两个生产设施及周边土地上已知的原位回收(ISR)和加工业务。但是,公司明白,在可行性研究之前进行生产时,不确定性会增加,因此失败的风险也会增加。此外,阿尔塔梅萨的矿产资源包括推断出的资源,这些资源在地质学上被认为过于投机性,无法对其进行经济考虑,因此无法将其归类为矿产储量。公司已决定根据过去在阿尔塔梅萨和罗西塔的业务,包括ISR过去在已知矿产资源领域的业务,继续做出生产决策。

Year End Financial Statements
年终财务报表

The Company also announces that its Annual Information Form, Consolidated Annual Financial Statements and Management's Discussion and Analysis for the year ended December 31, 2022 have been filed with Canadian securities regulatory authorities. enCore has also filed its Annual Report on Form 40-F for the year ended December 31, 2022, with the U.S. Securities and Exchange Commission. Copies of these documents may be obtained via , www.sec.gov (for the Form 40-F) or .

公司还宣布,截至该年度的年度信息表、合并年度财务报表和管理层的讨论与分析 2022年12月31日 已向加拿大证券监管机构提交。eNcore还提交了截至年度的40-F表年度报告 2022年12月31日,与美国证券交易委员会合作。这些文件的副本可通过 www.sec.gov(适用于 40-F 表格)或.

Shareholders may also receive a hard copy of these documents without charge upon request to enCore Energy Corp, 1200 – 750 W. Pender Street, Vancouver, BC V6C 2T8, or to [email protected].

应向eNcore Energy Corp提出要求,股东还可以免费获得这些文件的硬拷贝,1200 — 750 W. 彭德街温哥华,BC V6C 2T8,或者到 [电子邮件保护]

Stock Option Grant
股票期权授予

The Company also announces that it has granted incentive stock options (the "Options") to certain of its directors, officers and related party consultants to purchase an aggregate of up to 2,075,000 common shares in the capital of the Company at a price of $2.79 CDNper share for a five-year period, in accordance with its Stock Option Plan. Vesting will occur over a period of twenty-four months, with an initial 25% of the Options vesting six months following the date of grant, followed by an additional 25% of the Options every six months thereafter until fully vested.

公司还宣布,已向其某些董事、高级管理人员和关联方顾问授予激励性股票期权(“期权”),允许他们以总额为2,075,000股公司资本的普通股收购 2.79 美元 根据其股票期权计划,cdNper的股票有效期为五年。归属将在二十四个月内进行,最初的25%期权将在授予之日后六个月归属,之后每六个月再归属25%的期权,直到完全归属。

John M. Seeley, Ph.D., P.G., C.P.G., enCore's Manager of Geology and Exploration, and a Qualified Person under NI 43-101, has reviewed and approved the technical disclosure in this news release on behalf of enCore.

约翰·M·西利,博士,P.G.,CPG.,EnCore的地质与勘探经理,也是NI 43-101下的合格人员,已代表EnCore审查并批准了本新闻稿中的技术披露。

About enCore Energy Corp.
关于 EnCore Energy

enCore Energy Corp. is committed to providing clean, reliable, and affordable domestic nuclear energy by becoming the next United States uranium producer in 2023. enCore solely utilizes In-Situ Recovery (ISR) for uranium extraction, a well-known and proven technology co-developed by the leaders at enCore Energy. In-Situ Recovery extracts uranium in a non-invasive process using natural groundwater and oxygen, coupled with a proven ion exchange process, to recover the uranium. Uranium production is planned at enCore's licensed and past-producing South Texas Rosita Processing Plant in 2023, and at its licensed and past-producing South Texas Alta Mesa Processing Plant in 2024. Future projects in enCore's production pipeline include the Dewey-Burdock project in South Dakota and the Gas Hills project in Wyoming, along with significant uranium resource endowments in New Mexico providing long-term opportunities. The enCore team is led by industry experts with extensive knowledge and experience in all aspects of ISR uranium operations and the nuclear fuel cycle. enCore diligently works to realize value from other owned assets, including our proprietary uranium database that includes technical information from many past producing companies, from our various non-core assets, and by leveraging our ISR expertise in researching opportunities that support the use of this technology as applied to other metals. enCore is also committed to working with local communities and indigenous governments to create positive impact from corporate developments.

EnCore Energy Corp. 致力于通过成为下一个核能来提供清洁、可靠和负担得起的国内核能 美国 2023 年的铀生产商。eNcore 仅使用原位回收 (ISR) 进行铀提取,这是一项由eNcore Energy领导者共同开发的知名且久经考验的技术。In-Situ Recovery 使用天然地下水和氧气,再加上经过验证的离子交换工艺,通过非侵入性过程提取铀。eNcore计划于2023年在获得许可和过去生产的南德克萨斯罗西塔加工厂生产铀,并于2024年在其许可和过去生产的南德克萨斯阿尔塔梅萨加工厂生产铀。eNcore的未来生产项目包括位于的杜威-伯多克项目 南达科他州 以及位于的煤气山项目 怀俄明州,以及该国的大量铀资源储备 新墨西哥州 提供长期机会。eNCore 团队由在 ISR 铀运营和核燃料循环的各个方面具有丰富知识和经验的行业专家领导。eNCore 努力从其他自有资产中实现价值,包括我们的专有铀数据库,其中包括来自许多过去生产公司的技术信息,来自我们的各种非核心资产,并利用我们的 ISR 专业知识来研究支持将该技术应用于其他金属的机会。eNCore 还致力于与当地合作社区和土著政府将从企业发展中产生积极影响。

Cautionary Note Regarding Forward-Looking Statements: Certain information contained in this news release, including: any information relating to the Company being a leading uranium company; and any other statements regarding future expectations, beliefs, goals or prospects; may constitute "forward-looking information" and "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation (collectively, "forward-looking statements"). All statements in this news release that are not statements of historical fact (including statements containing the words "expects", "is expected", "does not expect", "plans", "anticipates", "does not anticipate", "believes", "intends", "estimates", "projects", "potential", "scheduled", "forecast", "budget" and similar expressions or variations (including negative variations) of such words and phrases, or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken) should be considered forward-looking statements. All such forward-looking statements are subject to important risk factors and uncertainties, many of which are beyond the company's ability to control or predict. Forward-looking statements necessarily involve known and unknown risks, including, without limitation, risks associated with general economic conditions; adverse industry events; future legislative and regulatory developments; that results of past mining operations at the Alta Mesa and Rosita sites are indicative of the results of proposed mining activities at those sites; that a production decision will result in actual production commencing and that such production will be economically viable over time; the ability of enCore to implement its business strategies; and other risks. A number of important factors could cause actual results or events to differ materially from those indicated or implied by such forward-looking statements, including without limitation exploration and development risks, changes in commodity prices, access to skilled mining personnel, the results of exploration and development activities; production risks; uninsured risks; regulatory risks; defects in title; the availability of materials and equipment, timeliness of government approvals and unanticipated environmental impacts on operations; risks posed by the economic and political environments in which the Company operates and intends to operate; increased competition; assumptions regarding market trends and the expected demand and desires for the Company's products and proposed products; reliance on industry equipment manufacturers, suppliers and others; the failure to adequately protect intellectual property; the failure to adequately manage future growth; adverse market conditions, the failure to satisfy ongoing regulatory requirements and factors relating to forward looking statements listed above which include risks as disclosed in the companies' annual information form filings. Should one or more of these risks materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. The Company assumes no obligation to update the information in this communication, except as required by law. Additional information identifying risks and uncertainties is contained in filings by the Company with the various securities commissions which are available online at www.sec.gov and . Forward-looking statements are provided for the purpose of providing information about the current expectations, beliefs and plans of management. Such statements may not be appropriate for other purposes and readers should not place undue reliance on these forward-looking statements, that speak only as of the date hereof, as there can be no assurance that the plans, intentions or expectations upon which they are placed will occur. Such information, although considered reasonable by management at the time of preparation, may prove to be incorrect and actual results may differ materially from those anticipated. Forward-looking statements contained in this news release are expressly qualified by this cautionary statement.

关于前瞻性陈述的警示说明: 本新闻稿中包含的某些信息,包括:与公司是领先的铀公司有关的任何信息;以及有关未来预期、信念、目标或前景的任何其他陈述;可能构成适用的加拿大人所指的 “前瞻性信息” 和 “前瞻性陈述” 美国 证券立法(统称为 “前瞻性陈述”)。本新闻稿中所有非历史事实陈述的陈述(包括包含 “预期”、“预期”、“预期”、“未预期”、“未预期”、“相信”、“打算”、“估计”、“项目”、“潜力”、“预期”、“预计”、“预算” 等词语的陈述)以及此类词语和短语的类似表达或变体(包括负面变体),或关于 “可能”、“可能”、“将”、“可能” 或 “将” 采取某些行动、事件或结果的陈述)应被视为前瞻性陈述。所有这些前瞻性陈述都受重要的风险因素和不确定性的影响,其中许多因素和不确定性超出了公司的控制或预测能力。前瞻性陈述必然涉及已知和未知的风险,包括但不限于与总体经济状况相关的风险;不利的行业事件;未来的立法和监管发展;阿尔塔梅萨和罗西塔基地过去采矿业务的结果表明这些地点拟议采矿活动的结果;生产决策将导致实际生产开始,随着时间的推移,此类生产将具有经济可行性;eNcore实施其业务战略的能力;和其他风险。许多重要因素可能导致实际业绩或事件与此类前瞻性陈述所表明或暗示的结果存在重大差异,包括但不限于勘探和开发风险、大宗商品价格变化、获得熟练采矿人员的机会、勘探和开发活动的结果;生产风险;未投保风险;监管风险;所有权缺陷;材料和设备的可用性、政府批准的及时性以及对运营的意外环境影响;带来的风险公司运营和打算运营的经济和政治环境;竞争加剧;对市场趋势以及对公司产品和拟议产品的预期需求和愿望的假设;对行业设备制造商、供应商和其他人的依赖;未能充分保护知识产权;未能充分管理未来增长;不利的市场条件、未能满足持续的监管要求以及与上述前瞻性陈述相关的因素,包括公司年度信息表文件中披露的风险。如果这些风险中的一项或多项得以实现,或者前瞻性陈述所依据的假设被证明不正确,则实际结果可能与本文描述的预期、计划、预期、相信、估计或预期的结果存在重大差异。除非法律要求,否则公司没有义务更新本通讯中的信息。识别风险和不确定性的其他信息包含在公司向各证券委员会提交的文件中,这些文件可在网上查阅 www.sec.gov 和。提供前瞻性陈述的目的是提供有关管理层当前期望、信念和计划的信息。此类陈述可能不适合用于其他目的,读者不应过分依赖这些前瞻性陈述,这些陈述仅代表截至本文发布之日,因为无法保证所提出的计划、意图或期望会实现。此类信息虽然在准备时被管理层认为是合理的,但可能被证明是不正确的,实际结果可能与预期的结果存在重大差异。本警告声明明确限定了本新闻稿中包含的前瞻性陈述。

SOURCE enCore Energy Corp.