share_log

High Tide Resources Announces Filing of the Labrador West Iron Project NI 43-101 Technical Report

High Tide Resources Announces Filing of the Labrador West Iron Project NI 43-101 Technical Report

High Tide Resources 宣佈提交拉布拉多西部鋼鐵項目 NI 43-101 技術報告
Accesswire ·  2023/04/06 21:05

TORONTO, ON / ACCESSWIRE / April 6, 2023 / High Tide Resources Corp. ("High Tide" or the "Company") (CSE:HTRC) is pleased to announce the filing of a National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101") compliant technical report for the Labrador West Iron Project (the "Labrador West Technical Report").

安大略省多倫多/ACCESSWIRE/2023 年 4 月 6 日/ High Tide 資源公司 (”漲潮“或者”公司“) (CSE: HTRC) 很高興地宣佈已提交國家文書 43-101- 礦產項目披露標準 (”在 43-101“) 拉布拉多西部鋼鐵項目的合規技術報告(”拉布拉多西部技術報告“)。

The Labrador West Technical Report is dated April 6, 2023 with an effective date of January 31, 2023 and was completed by Mercator Geological Services ("Mercator") and BBA Inc. ("BBA") at the request of High Tide. The report titled, "NI 43-101 Technical Report, Mineral Resource Estimate, Labrador West Iron Project, Newfoundland and Labrador, Canada" has been filed on the Company's profile on SEDAR at and will be posted on the Company's website at . There are no material differences in the Labrador West Technical Report from the information disclosed in the news release issued February 23, 2023 titled "High Tide Resources Announces Maiden Mineral Resource Estimate at its Labrador West Iron Project".

拉布拉多西部技術報告的日期爲2023年4月6日,生效日期爲2023年1月31日,由墨卡托地質服務公司完成(”墨卡託“) 和 BBA Inc. (”BBA“)應漲潮的要求。這份名爲 “NI 43-101技術報告,礦產資源估算,加拿大紐芬蘭和拉布拉多的拉布拉多西部鋼鐵項目” 的報告已在SEDAR的公司簡介中提交,並將發佈在公司的網站上,網址爲。拉布拉多西部技術報告與2023年2月23日發佈的題爲 “High Tide Resources宣佈其拉布拉多西部鐵礦項目首次礦產資源估算” 的新聞稿中披露的信息沒有實質性區別。

The Inferred Mineral Resource estimate was prepared by Mercator in accordance with the CIM Standards for Mineral Resources and Mineral Reserves (MRMR) (May 10, 2014) and CIM MRMR Best Practice Guidelines (November, 2019) and has been reported in accordance with NI 43-101 (see High Tide press release dated February 23, 2023).

推斷的礦產資源估算值由墨卡託根據CIM礦產資源和礦產儲量標準(MRMR)(2014年5月10日)和CIM MRMR最佳實踐指南(2019年11月)編制,並根據NI 43-101進行報告(見2023年2月23日的漲潮新聞稿)。

Table 1: Labrador West Mineral Resource Estimate - Effective Date: January 31, 2023

表 1:拉布拉多西部礦產資源估算——生效日期:2023 年 1 月 31 日

Type

Cut-off (FeT %)

Category

Tonnes (millions)

(FeT %)

Pit Shell Constrained

15

Inferred

654.9

28.84

類型

截止值 (fET%)

類別

噸(百萬)

(英尺%)

炮彈受限

15

推斷

654.9

28.84

Notes:

注意事項:

  1. Total iron (FeT) Mineral Resources include only oxide-facies iron formation (magnetite or hematite dominated).
  2. Mineral Resources are defined within an optimized conceptual pit shell with an overall pit slope angle of 500 and a 1.3:1 strip ratio (waste: mineralized material)
  3. Pit shell optimization parameters include: pricing of CDN $129 /tonne for 65% Fe concentrate, exchange rate of CDN $1.30 to US$ 1.00, mining cost at CDN $3.00/t, processing cost at CDN $4.55/t processed, tailings cost at CDN $0.35 processed, rail & port cost at CDN $18.00/t shipped, G & A Cost at CDN $5.00/t processed, Ocean Freight at CDN $28.00/t shipped and mill recovery at 80%.
  4. A cut-off grade of 15% FeT was selected for definition of the Mineral Resource.
  5. Mineral Resources were estimated using Inverse Distance Squared methods applied to 3 m downhole assay composites. Iron grades were capped at 50 % FeT. Model block size is 20 m (x) by 20 m (y) by 12 m (z).
  6. Bulk density for the block model was calculated from a linear regression relationship between FeT (%) and specific gravity measurements from the Labrador West project. The average bulk density estimated for the deposit is 3.10 g/cm3
  7. Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.
  8. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.
  9. Mineral Resource tonnages are rounded to the nearest 100,000.
  1. 鐵 (FeT) 礦產資源總量僅包括氧化相鐵的形成(以磁鐵礦或赤鐵礦爲主)。
  2. 礦產資源是在經過優化的概念坑殼內定義的,礦坑總坡度角爲 500,條帶比爲 1. 3:1(廢物:礦化物質)
  3. 坑殼優化參數包括:65% 鐵精礦每噸129加元的定價,1.30加元兌1.00加元的匯率,3.00加元/噸的採礦成本,加工成本爲4.55加元/噸,加工尾礦成本爲0.35加元加元,鐵路和港口成本爲每噸18.00加元運輸,G和A成本爲5.00加元/噸已處理,海運成本爲5.00加元每噸出貨28.00加元,工廠復甦率爲80%。
  4. 選擇了 15% fET 的臨界等級作爲礦產資源的定義。
  5. 礦產資源是使用應用於 3 m 井下分析複合材料的反距離平方方法估算的。鐵的等級上限爲 50% fET。模型方塊大小爲 20 m (x) x 20 m (y) x 12 m (z)。
  6. 方塊模型的體積密度是根據FeT (%) 和拉布拉多西部項目的比重測量值之間的線性回歸關係計算得出的。據估計,該礦牀的平均體積密度爲3.10 g/cm3
  7. 礦產資源可能受到環境、許可、法律、所有權、稅收、社會政治、營銷或其他相關問題的實質性影響。
  8. 礦產資源不是礦產儲量,也沒有顯示出經濟可行性。
  9. 礦產資源噸位四捨五入到最接近的 100,000。

Labrador West Iron Project

拉布拉多西部鋼鐵項目

The Labrador West Iron Project (the "Project") is comprised of one mineral licence (99 mineral claims), 2,475 hectares in size (the "Property"). The area was explored and drilled by Rio Tinto Exploration from 2010 to 2012, and then by High Tide in 2020 & 2022. To date, approximately 7,500 m of core in 27 completed holes has been drilled on the Property. Located less than 20 kilometres northeast of Labrador City, the Project is proximal to all the critical infrastructure required to explore and develop a major new iron deposit in the heart of the southern Labrador Trough. Experience by major producers operating in the Labrador Trough indicates that hematite and magnetite in this geological setting are readily recoverable using modern, industry standard beneficiation methods, that produce high purity, desirable iron concentrates.

拉布拉多西部鋼鐵項目(“項目”)由一份礦產許可證(99份礦產索賠)組成,面積爲2475公頃(“財產”)。力拓勘探公司在2010年至2012年期間對該地區進行了勘探和鑽探,然後在2020年和2022年由漲潮進行勘探和鑽探。迄今爲止,該物業已在27個已完成的孔中鑽了大約7,500米的岩心。該項目位於拉布拉多城東北不到20公里處,靠近在拉布拉多海槽南部中心勘探和開發大型新鐵礦牀所需的所有關鍵基礎設施。在拉布拉多槽運營的主要生產商的經驗表明,這種地質環境中的赤鐵礦和磁鐵礦很容易使用現代的行業標準選礦方法進行開採,這些方法可以生產出高純度、理想的鐵精礦。

Iron and the Western Labrador Trough Infrastructure Advantage

鋼鐵與西部拉布拉多海槽基礎設施優勢

The Labrador Trough of western Labrador and adjoining Quebec constitutes Canada's primary iron producing district and is host to world-class deposits that have been mined for more than half a century. These have produced over 2 billion tonnes of iron ore to date and are considered to have very significant growth potential. The high quality of the deposits in the region allows for a wide range in product diversity, which includes premium fines, concentrate and pellet grades.

拉布拉多西部和毗鄰的魁北克的拉布拉多海槽是加拿大的主要鐵產區,也是開採了半個多世紀的世界級礦牀的所在地。迄今爲止,它們已經生產了超過20億噸的鐵礦石,被認爲具有非常可觀的增長潛力。該地區礦牀質量高,產品多樣性廣泛,包括優質細粉、濃縮物和顆粒等級。

The Project is strategically located near the mining communities of Wabush and Labrador City in the province of Newfoundland & Labrador and Fermont in Quebec. The area is home to Champion Iron Ore's Bloom Lake Mine, ArcelorMittal's Mont-Wright Mine, Tacora Resources' Scully Mine, and Rio Tinto/IOC's Carol Lake Mine.

該項目地理位置優越,位於紐芬蘭和拉布拉多省的瓦布什和拉布拉多市以及魁北克的費爾蒙特礦業社區附近。該地區是 Champion Iron Ore 的布魯姆湖礦、安賽樂米塔爾的 Mont-Wright 礦、Tacora Resources 的 Scully Mine 和 Rio Tinto/IOC 的卡羅爾湖礦的所在地。

The Wabush and Labrador City region is very well served with skilled labour and a highway as well as access to abundant low-cost hydroelectricity and a common carrier railway. The railway has 80 million tonnes per year of capacity for transport of iron products to the deep-water port of Sept Isles, Quebec, which provides year-round access to global markets.

瓦布什和拉布拉多城地區服務良好,有熟練勞動力和高速公路,還有豐富的低成本水電和公共運輸鐵路。這條鐵路每年的運力爲8000萬噸,可將鐵產品運送到魁北克塞特島的深水港,該港全年提供進入全球市場的通道。

About High Tide

關於 High Tide

High Tide is focused on and committed to the development of mineral projects critical to infrastructure development using industry best practices combined with a strong social license from local communities. High Tide owns a 100% interest in the Project which hosts a NI 43-101 Inferred iron resource of 659 Mt @ 28.84% Fe and is located adjacent to IOC's Carol Lake Mine in Labrador City, NL. This resource is exposed at surface and was pit constrained for an open-pit mining scenario. The Technical Report was filed on SEDAR on April 6, 2023 and was authored by Ryan Kressall M.Sc., P.Geo, Matthew Herrington, M.Sc., P.Geo, Catharine Pelletier, P.Eng. and Jeffrey Cassoff P.Eng.

High Tide專注於並致力於利用行業最佳實踐和當地社區的強有力的社會許可,開發對基礎設施發展至關重要的礦產項目。High Tide擁有該項目的100%權益,該項目擁有659萬噸 @ 28.84%鐵的NI 43-101推斷鐵資源,毗鄰國際奧委會位於荷蘭拉布拉多城的卡羅爾湖礦。這種資源暴露在地表,在露天採礦場景中受到礦坑限制。該技術報告於 2023 年 4 月 6 日在 SEDAR 上提交,由 Ryan Kressall M.Sc.、P.Geo、P.Eng. Matthew Herrington、P.Geo、Catharine Pelletier、P.Eng. 和 Jeffrey Cassoff P.Eng 撰寫。

The Company also owns a 100% interest in the Lac Pegma copper-nickel-cobalt deposit located 50 kilometres southeast of Fermont, Quebec and is earning a 100% interest in the road accessible Clearcut Lithium Project located ~75 kilometres southwest of Val d'Or, Quebec and the road accessible Big Bang Lithium Project located ~275 kilometres northeast of Thunder Bay, Ontario. Majority shareholder Avidian Gold (TSX.V: AVG) controls approximately 30% of High Tide's outstanding shares.

該公司還擁有位於魁北克省費蒙特東南50公里處的Lac Pegma銅鎳鈷礦牀的100%權益,並正在獲得位於魁北克瓦爾德奧爾西南約75公里的道路無障礙Clearcut鋰項目和位於安大略省桑德貝東北約275公里處的道路無障礙Big Bang鋰項目的100%權益。大股東Avidian Gold(多倫多證券交易所股票代碼:AVG)控制着High Tide約30%的已發行股份。

Qualified Person

合格人員

The technical information contained in this news release has been approved by Steve Roebuck,

本新聞稿中包含的技術信息已獲得史蒂夫·羅巴克的批准,

P.Geo., Director, President and Interim CEO of High Tide, who is a Qualified Person as defined in "National Instrument 43-101, Standards of Disclosure for Mineral Projects."

P.Geo.,High Tide董事、總裁兼臨時首席執行官,他是 “國家儀器43-101,礦產項目披露標準” 中定義的合格人員。

For further information, please contact:

欲瞭解更多信息,請聯繫:

Steve Roebuck
Director, President & Interim CEO
Mobile: (905) 741-5458
Email: sroebuck@hightideresources.com

史蒂夫·羅巴克
董事、總裁兼臨時首席執行官
手機:(905) 741-5458
電子郵件:sroebuck@hightideresources.com

Neither Canadian Securities Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Canadian Securities Exchange) accepts responsibility for the adequacy or accuracy of this news release.

加拿大證券交易所及其監管服務提供商(該術語在加拿大證券交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

Forward looking information

前瞻性信息

This news release includes certain "forward-looking statements" which are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". Since forward-looking statements are based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties. Although these statements are based on information currently available to the Company, the Company provides no assurance that actual results will meet management's expectations. Risks, uncertainties and other factors involved with forward-looking information could cause actual events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward looking information in this news release includes, but is not limited to, closing of the Agreement, exercising the Option, the acquisition of low cost and potentially high reward lithium projects, the ability to keep exploration costs low, expected access to regional lithium processing hubs, the Company's objectives, goals or future plans, statements, exploration results, potential mineralization, the estimation of mineral resources, exploration and mine development plans, timing of the commencement of operations and estimates of market conditions. Factors that could cause actual results to differ materially from such forward-looking information include, but are not limited to: the ability to anticipate and counteract the effects of COVID-19 pandemic on the business of the Company, including without limitation the effects of COVID-19 on the capital markets, commodity prices supply chain disruptions, restrictions on labour and workplace attendance and local and international travel, failure to receive requisite approvals in respect of the foregoing, failure to identify mineral resources, failure to convert estimated mineral resources to reserves, the inability to complete a feasibility study which recommends a production decision, the preliminary nature of metallurgical test results, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, inability to fulfill the duty to accommodate First Nations and other indigenous peoples, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects, capital and operating costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry, and those risks set out in the Company's public documents filed on SEDAR. Although the Company believes that the assumptions and factors used in preparing the forward-looking information in this news release are reasonable, undue reliance should not be placed on such information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law.

本新聞稿包括某些不包含歷史事實的 “前瞻性陳述”。前瞻性陳述包括描述公司未來計劃、目標或目標的估計和陳述,包括大意是公司或管理層預計會出現既定條件或結果的措辭。前瞻性陳述可以用 “相信”、“預期”、“期望”、“估計”、“可能”、“可能”、“將”、“將”、“將” 或 “計劃” 等術語來識別。由於前瞻性陳述基於假設並涉及未來的事件和條件,因此就其本質而言,它們涉及固有的風險和不確定性。儘管這些陳述基於公司目前獲得的信息,但公司不能保證實際業績會達到管理層的預期。前瞻性信息所涉及的風險、不確定性和其他因素可能導致實際事件、結果、業績、前景和機會與此類前瞻性信息所表達或暗示的事件、結果、業績、前景和機會存在重大差異。本新聞稿中的前瞻性信息包括但不限於協議的達成、行使期權、收購低成本和潛在高回報的鋰項目、保持低勘探成本的能力、進入區域鋰加工中心的預期准入、公司的目標、目標或未來計劃、聲明、勘探結果、潛在礦化、礦產資源估計、勘探和礦山開發計劃、開始運營的時間以及市場狀況的估計。可能導致實際業績與此類前瞻性信息存在重大差異的因素包括但不限於:預測和抵消 COVID-19 疫情對公司業務影響的能力,包括但不限於 COVID-19 對資本市場的影響、大宗商品價格、供應鏈中斷、對勞動力和工作場所出勤以及本地和國際旅行的限制、未能獲得上述方面的必要批准、未能識別礦產資源、未能轉換估計可儲備的礦產資源,無法完成可行性研究以提出生產決定的建議,冶金試驗結果的初步性質,延遲獲得或未能獲得所需的政府、環境或其他項目批准,政治風險,無法履行容納原住民和其他土著人民的義務,與未來所需資金的可得性和成本有關的不確定性,股票市場的變化,通貨膨脹,匯率的變化,大宗商品價格、項目開發延遲、資本和運營成本與估計以及礦產勘探和開發行業涉及的其他風險以及公司在SEDAR上提交的公開文件中列出的風險有很大差異。儘管公司認爲在本新聞稿中準備前瞻性信息時使用的假設和因素是合理的,但不應過分依賴此類信息,此類信息僅在本新聞稿發佈之日適用,也無法保證此類事件會在披露的時間範圍內發生或根本不會發生。除非法律要求,否則公司不打算或有義務更新或修改任何前瞻性信息,無論是由於新信息、未來事件還是其他原因造成的。

SOURCE: High Tide Resources Corp.

來源: 漲潮資源公司