Platinum Group Metals Ltd. Reports Update on Waterberg Project and Infill Drill Program

Platinum Group Metals Ltd. Reports Update on Waterberg Project and Infill Drill Program

白金集團金屬有限公司報告 Waterberg 項目和填充鑽探計劃的最新情況
newsfile ·  2023/03/30 16:06

Vancouver, British Columbia and Johannesburg, South Africa--(Newsfile Corp. - March 30, 2023) - Platinum Group Metals Ltd. (TSX: PTM) (NYSE American: PLG) ("Platinum Group", "PTM" or the "Company") reports that an infill drill campaign (the "Infill Drill Program") underway since November 2022, at the Waterberg Project, located on the Northern Limb of the Bushveld Complex in South Africa (the "Waterberg Project"), has been completed. All 16 planned T Zone boreholes and 16 planned F Zone boreholes have been drilled.

溫哥華, 不列顛哥倫比亞省和約翰內斯堡, 南非--(新聞檔公司-2023 年 3 月 30 日)- 白金集團金屬有限公司 多倫多證券交易所代碼:PTM)(紐約證券交易所美國交易所代碼:PLG)(」白金集團「,」聚四氟乙烯「或」公司「) 報告說,填充鑽探活動 (」填充鑽探計劃「) 正在進行自 2022 年 11 月, 在沃特伯格項目, 位於南非布什維爾德綜合體的北部肢體 (該」沃特贝格项目「),已完成。所有 16 個計劃 T 區鑽孔和 16 個計劃的 F 區鑽孔已鑽孔。

Drill cores from the completed boreholes have been logged, and the mineralized intercepts recovered have been sampled and sent for assay by Intertek Genalysis Minerals in Australia. Final assay results for all T Zone boreholes and one F Zone borehole (WB303) were reported in the Company's news release dated January 26, 2023. All F Zone final assays from the Infill Drill program have now been received and are tabulated below:

已經記錄完成的鑽孔中的鑽芯,並且已經由澳大利亞的 Intertek Genalysis Minerals 進行了採樣並發送測定。公司日期為 2023 年 1 月 26 日的新聞稿中報導了所有 T 區鑽孔和一個 F 區鑽孔(WB303)的最終測定結果。現在已收到來自「填充鑽探」計劃的所有 F 區最終測試,並列出如下:

Area Borehole ID From
(m)
To
(m)
Zone(1) Length(2)
(m)
Pt
(g/t)
Pd
(g/t)
Rh
(g/t)
Au
(g/t)
4PGE
(g/t)
F Zone WB302 231.33 322.00 CSF 90.67 0.33 0.78 0.02 0.05 1.18
Includes WB302 248.00 260.50 CSF 12.50 0.63 1.54 0.04 0.10 2.31
Includes WB302 309.83 322.00 CSF 12.17 0.54 1.37 0.04 0.06 2.01
F Zone WB304 248.50 318.50 CSF 70.00 0.77 1.68 0.05 0.13 2.63
Includes WB304 248.50 281.00 CSF 32.50 1.02 2.31 0.07 0.21 3.61
Includes WB304 296.50 318.50 CSF 22.00 0.71 1.53 0.04 0.09 2.37
F Zone WB305 232.50 260.00 CSF 27.50 1.26 2.77 0.08 0.19 4.30
F Zone WB306

CSF Beyond Subcrop(3)
F Zone WB307

CSF Beyond Subcrop(3)
F Zone WB308 226.88 275.00 CSF 48.12 1.12 2.67 0.07 0.19 4.05
Includes WB308 226.88 250.50 CSF 23.62 1.61 3.95 0.11 0.26 5.93
F Zone WB309 236.00 254.00 CSF 18.00 1.57 3.22 0.08 0.21 5.08
F Zone WB310 293.00 410.00 CSF 117.00 0.34 0.76 0.02 0.05 1.17
Includes WB310 312.00 322.00 CSF 10.00 0.52 1.22 0.03 0.09 1.86
Includes WB310 389.00 410.00 CSF 21.00 0.58 1.37 0.03 0.09 2.07
F Zone WB311 310.00 395.00 CSF 85.00 0.34 0.77 0.02 0.05 1.18
Includes WB311 310.00 319.60 CSF 9.60 0.65 1.57 0.04 0.09 2.35
Includes WB311 386.00 395.00 CSF 9.0 0.74 1.35 0.03 0.08 2.20
F Zone WB312

CSF Beyond Subcrop(3)
F Zone WB313 281.55 304.00 CSF 22.45 1.48 3.24 0.09 0.19 5.00
F Zone WB314

CSF Beyond Subcrop(3)
F Zone WB315

CSF Beyond Subcrop(3)
F Zone WB316 285.00 313.00 CSF 28.00 0.55 1.35 0.04 0.09 2.03
Includes WB316 285.00 290.00 CSF 5.00 0.84 1.92 0.05 0.11 2.92
Includes WB316 305.00 313.00 CSF 8.00 1.01 2.6 0.07 0.18 3.86
F Zone WB317 356.00 357.92 CSF 1.92 1.72 3.28 0.12 0.12 5.24
地區 鑽孔標識
(米)

(米)
區域(一) 長度(二)
(米)
PT
(克/噸)
PD
(克/噸)
Rh
(克/噸)
非盟
(克/噸)
四分鐘
(克/噸)
F 區域 WB302 231.33 322.00 CSF 90.67 0.33 0.78 0.02 0.05 1.18
包括 WB302 248.00 260.50 CSF 12.50 0.63 1.54 0.04 0.10 2.31
包括 WB302 309.83 322.00 CSF 12.17 0.54 1.37 0.04 0.06 2.01
F 區域 WB304 248.50 318.50 CSF 70.00 0.77 1.68 0.05 0.13 2.63
包括 WB304 248.50 281.00 CSF 32.50 1.02 2.31 0.07 0.21 3.61
包括 WB304 296.50 318.50 CSF 22.00 0.71 1.53 0.04 0.09 2.37
F 區域 WB305 232.50 260.00 CSF 27.50 1.26 2.77 0.08 0.19 4.30
F 區域 WB306

CSF 超越次裁剪(三)
F 區域 WB307

CSF 超越次裁剪(三)
F 區域 WB308 226.88 275.00 CSF 48.12 1.12 2.67 0.07 0.19 4.05
包括 WB308 226.88 250.50 CSF 23.62 1.61 3.95 0.11 0.26 5.93
F 區域 WB309 236.00 254.00 CSF 18.00 1.57 3.22 0.08 0.21 5.08
F 區域 WB310 293.00 410.00 CSF 117.00 0.34 0.76 0.02 0.05 1.17
包括 WB310 312.00 322.00 CSF 10.00 0.52 1.22 0.03 0.09 1.86
包括 WB310 389.00 410.00 CSF 21.00 0.58 1.37 0.03 0.09 2.07
F 區域 WB311 310.00 395.00 CSF 85.00 0.34 0.77 0.02 0.05 1.18
包括 WB311 310.00 319.60 CSF 9.60 0.65 1.57 0.04 0.09 2.35
包括 WB311 386.00 395.00 CSF 9.0 0.74 1.35 0.03 0.08 2.20
F 區域 WB312

CSF 超越次裁剪(三)
F 區域 WB313 281.55 304.00 CSF 22.45 1.48 3.24 0.09 0.19 5.00
F 區域 WB314

CSF 超越次裁剪(三)
F 區域 WB315

CSF 超越次裁剪(三)
F 區域 WB316 285.00 313.00 CSF 28.00 0.55 1.35 0.04 0.09 2.03
包括 WB316 285.00 290.00 CSF 5.00 0.84 1.92 0.05 0.11 2.92
包括 WB316 305.00 313.00 CSF 8.00 1.01 2.6 0.07 0.18 3.86
F 區域 WB317 356.00 357.92 CSF 1.92 1.72 3.28 0.12 0.12 5.24

Notes:

注意:

(1) CSF = Central Super F Zone.

(1)CSF = 中環超級 F 區。

(2) The true width of the shallow dipping (30° to 35°) mineralized zones are approximately 82% to 87% of the reported interval from the vertical drill hole.

(2)淺浸(30° 至 35°)礦化區的實際寬度約為垂直鑽孔報告間隔的 82% 至 87%。

(3) Borehole collared east of where westward dipping F Zone subcrops.

(3) 鑽孔領東部,其中向西浸 F 區底部。

Copper grades per tonne for all F Zone intercepts listed above averaged 0.060%. Nickel grades per tonne for all F Zone intercepts listed above averaged 0.184%.

上述所有 F 區截距的銅級每噸平均值為 0.060%。上述所有 F 區截距的每噸鎳等級平均為 0.184%。

In addition to the Infill Drill Program, several geotechnical holes have also been completed and several more remain to be drilled. One exploration borehole is currently underway at a location approximately 15 kilometres north of the main project area and is presently at a depth of approximately 1,300 metres. This exploration borehole is intended to improve our understanding of the geology and economic potential of the Waterberg deposit on prospecting rights located adjacent to the north of the Waterberg Project's granted mining right. Intrusive formations of the Bushveld Igneous Complex have been intercepted in this exploration borehole, as expected.

除了填充鑽探計劃外,還完成了幾個岩土工程孔,還有幾個還有待鑽孔。一個勘探鑽孔目前正在進行,位於主要工程區以北約 15 公里處的位置,目前深度約為 1,300 米。這個勘探鑽孔旨在提高我們對 Waterberg 礦床的地質和經濟潛力的理解,該礦床位於 Waterberg 項目授予的採礦權北部毗鄰的勘探權。正如預期的那樣,在這個勘探井中截獲了 Bushveld 火成複合物的侵入形成。

The Infill Drill Program targeted near surface, inferred, and indicated mineral resource blocks that have good potential for conversion to higher confidence levels, potentially identifying additional tonnage for inclusion in early mine plans. Drilling of the 16 F Zone boreholes was also intended to improve the delineation of the F Zone subcrop geometry. Results from the F Zone drilling as tabulated above are consistent with expectations.

Infill Drill 計劃針對地表附近,推斷和指示的礦產資源塊,這些礦產資源塊具有良好的潛力轉化為更高的可信度,從而可能識別其他噸位以納入早期礦山計劃中。16 F Zone 鑽孔的鑽孔也旨在改善 F Zone 次裁剪幾何圖形的描繪。以上表列出的 F Zone 鑽探結果與預期一致。

Some tonnage in the resource blocks drilled in the Infill Drill Program was included in previous mine planning for the 2019 Waterberg Project Definitive Feasibility Study (the "Waterberg DFS"). The Waterberg DFS technical report entitled "Independent Technical Report, Waterberg Project Definitive Feasibility Study and Mineral Resource Update, Bushveld Complex, South Africa" was filed on SEDAR at and on EDGAR at www.sec.gov on October 7, 2019.

在填充鑽探計劃中鑽探的資源塊中的一些噸位已包括在 2019 年 Waterberg 項目最終可行性研究的先前礦山規劃中(「」沃特伯格 DFS「)。沃特伯格 DFS 技術報告題為「獨立技術報告,沃特伯格項目確定可行性研究和南非布什維爾德綜合體礦產資源更新」已於 2019 年 10 月 7 日在 EDGAR 上向 SEDAR 提交,網址為 www.sec.gov。



Waterberg Deposit



沃特伯格存款

Platinum Group President and CEO, Frank Hallam, said, "We are once again pleased with the results from our Infill Drill Program and geotechnical drilling. Results are as expected and project geologists will use the results to update the Waterberg resource estimate, which project engineers will then use to optimize the Waterberg mine plan and development schedule for use in our Waterberg DFS Update, which is in process."

白金集團總裁兼首席執行官 Frank Hallam 表示:「我們再次對我們的填充鑽探計劃和岩土鑽探的結果感到滿意。結果如預期,項目地質學家將使用這些結果來更新 Waterberg 資源估算,然後項目工程師將使用這些估算來優化 Waterberg 礦山計劃和開發計劃,以便在我們正在進行的 Waterberg DFS 更新中使用。」

As reported previously, on October 18, 2022, project operating company Waterberg JV Resources Pty Ltd. ("Waterberg JV Co.") approved in principle a pre-construction work program of approximately US $21.0 million over a 23-month period ending August 31, 2024 (the "Work Program"). From the Work Program, an initial budget of approximately US $2.5 million was approved for expenditure by March 31, 2023, and this work, including the Infill Drill Program, is nearly complete. On March 24, 2023, the Waterberg JV Co. Board of Directors approved the funding of a second tranche of the Work Program (the "Stage Two Budget") in the amount of US $3.6 million. The Stage Two Budget will cover the period from April 1, 2023 to August 31, 2023 and is to include Waterberg DFS Update engineering, pre-construction engineering, electrical power supply engineering and the permitting and licensing of construction aggregate borrow pits identified near the planned Waterberg mine site.

如先前報導, 在 2022 年 10 月 18 日,項目運營公司沃特伯格合資資源私人有限公司 (」沃特伯格合資公司「) 在截至 2024 年 8 月 31 日的 23 個月期間,原則上批准了約 21.0 億美元的施工前工作計劃(」工作計劃「)。根據工作計劃,在 2023 年 3 月 31 日之前批准了約 250 萬美元的初始預算用於支出,這項工作(包括填充鑽探計劃)已接近完成。在 2023 年 3 月 24 日,沃特伯格合資公司。董事會批准了工作計劃的第二批資金(」第二階段預算案「) 在 360 萬美元的金額.第二階段預算將涵蓋 2023 年 4 月 1 日至 2023 年 8 月 31 日期間,包括 Waterberg DFS 更新工程、施工前工程、電力供應工程以及在計劃中的 Waterberg 礦場附近確定的建築總體借礦坑的許可和許可。

Waste rock material retained after assaying of the T Zone and F Zone infill drilling will be further processed to determine dry-stack tailings characteristics and provide additional concentrate metallurgical data. If dry stack tailings methods are implemented, it is estimated that Waterberg mine water consumption could be reduced by 40% to 50%.

在檢測 T 區和 F 區填充鑽孔後保留的廢石材料將進一步處理,以確定乾堆尾尾的特性並提供額外的濃縮冶金數據。如果實施了幹堆尾礦方法,估計沃特伯格礦山用水量可以減少 40% 至 50%。

The Company is focussed on advancing the Waterberg Project to a development and construction decision. The Waterberg Project is planned to be a mechanised, shallow, decline access platinum, palladium, rhodium, and gold mine and is projected to be one of the largest and lowest cost underground platinum group metals mines globally.

該公司專注於將 Waterberg 項目推進到開發和施工決策。Waterberg 項目計劃成為一座機械化、淺層、下滑接入鉑金、鈀、銠和金礦,預計將成為全球最大且成本最低的地下鉑金集團金屬礦場之一。

PTM is the operator of the Waterberg Project as directed by a technical committee comprised of representatives from joint venture partners Impala Platinum Holdings Ltd. ("Implats"), Mnombo Wethu Consultants (Pty) Ltd. ("Mnombo"), Japan Organization for Metals and Energy Security (formerly Japan Oil, Gas and Metals National Corporation) ("JOGMEC") and Hanwa Co., Ltd. ("Hanwa"). Shareholders are encouraged to see the Company's filings on SEDAR () or on EDGAR (www.sec.gov) and to visit the Company's website at .

PTM 是 Waterberg 項目的運營商,由合資夥伴黑斑羚白金控股有限公司的代表組成的技術委員會的指導。(」不平坦「), 姆諾博衛圖顧問 (私人) 有限公司 (」姆諾博「),日本金屬和能源安全組織(原日本石油,天然氣和金屬國家公司)(」JOGMEC「) 和阪和股份有限公司 (」)阪和「)。我們鼓勵股東在 SEDAR()或 EDGAR(www.sec.gov)上查看公司的文件,並訪問公司的網站,網址為。

Quality Assurance and Quality Control

質量保證和質量控制

The Company and Waterberg JV Co. have instituted a complete quality assurance / quality control ("QA/QC") program, including the insertion of blanks, certified reference materials (standards), and field duplicates within the sample stream. Referee analyses are also completed. The program is being followed and is to industry standard. QA/QC procedures are overseen by a qualified person, and the data has been verified by and is considered reliable in the opinion of the qualified person for this news release (as described below).

公司和沃特伯格合資公司已經制定了完整的質量保證/質量控制(」質保質/質量「) 程式,包括在樣本流中插入空白、認證參考資料 (標準) 和欄位副本。裁判員分析也完成。該計劃正在遵循,並符合行業標準。質素保證/質量控制程序由合格人員監督,並且該資料已由合資格人員核實,並認為該新聞稿的合格人員認為是可靠的(如下所述)。

NQ (47.6mm diameter) drill core is cut in-half and quartered with a diamond saw, with one-quarter placed in sealed bags and shipped to the laboratory and the other three quarters retained on site. Third party laboratory checks on 5% of the samples are carried out as well. Chain of custody is maintained from the drill to the submittal into the laboratory preparation facility.

NQ(直徑 47.6 毫米)鑽芯切割成兩半並用鑽石鋸四分之一,四分之一放置在密封袋中,並運送到實驗室,另外四分之三保留在現場。也會對 5% 的樣本進行第三方實驗室檢查。從演習到提交到實驗室準備設施保持監管鏈。

Analytical testing was performed by the Intertek Genalysis Minerals Global Centre of Excellence, located in Perth, Western Australia. The entire sample is dried and crushed to ~2mm, of which a 300 gram split is pulverized to at least 85% of material to 75μm or better. Grade for Au, Pt and Pd is determined by using a 25g lead collection fire assay with Inductively Coupled Plasma-Optical Emission Spectrometry (ICP-OES) finish. On samples where the Au, Pt and Pd grade was found to be above 1 g/T, 6E analysis (for all PGEs) was done using 25g nickel sulphide collection and Inductively Coupled Plasma-Mass Spectrometry (ICP-MS) finish. Base metals and other major elements were determined by four acid digestion with Inductively Coupled Plasma Optical Emission Spectrometry (ICP-OES) finish.

分析測試由位於西澳大利亞州珀斯的 Intertek Genalysis 礦物全球卓越中心進行。將整個樣品乾燥並壓碎至 2 毫米,其中將 300 克分裂粉碎至少 85% 的材料至 75 微米或更好。Au,Pt 和 Pd 的等級是通過使用 25 克鉛收集火測定和電感耦合等離子體光發射光譜法(ICP-OES)完成確定的。在 Au,Pt 和 Pd 等級被發現高於 1 g/T 的樣品上,使用 25 克硫化鎳收集和電感耦合等離子質譜(ICP-MS)完成了 6E 分析(用於所有 PGE)。鹼金屬和其他主要元素是通過四種酸性消化與電感耦合等離子體發射光譜法(ICP-OES)完成確定的。

Borehole Location Table

鑽孔位置表

Borehole
ID
Easting
(WGS84 LO29)
Northing
(WGS84 LO29)
Elevation
(masl)
Dip Azimuth EOH
(m)
WB302 -2585876.6 -9553.8 1045.35 -90 0 367.55
WB303 -2585898.7 -9607.0 1045.41 -90 0 391.18
WB304 -2585784.3 -9610.3 1047.76 -90 0 385.40
WB305 -2585950.1 -9551.2 1043.16 -90 0 349.70
WB306 -2585909.4 -9514.3 1044.05 -90 0 301.16
WB307 -2586045.2 -9725.5 1043.10 -90 0 370.50
WB308 -2585924.3 -9585.2 1044.81 -90 0 387.13
WB309 -2585972.9 -9607.3 1044.09 -90 0 362.21
WB310 -2585960.9 -9724.0 1045.07 -90 0 432.13
WB311 -2586107.0 -9903.9 1044.21 -90 0 439.90
WB312 -2586287.7 -10012.0 1041.54 -90 0 333.60
WB313 -2586389.9 -10096.0 1040.41 -90 0 345.90
WB314 -2586442.7 -10029.0 1038.20 -90 0 319.89
WB315 -2586518.3 -10101.0 1037.10 -90 0 296.60
WB316 -2586482.1 -10154.0 1038.81 -90 0 332.00
WB317 -2586722.6 -10437.0 1035.62 -90 0 387.80
鑽孔
ID
東距
(八四十九曲)
北距
(八四十九曲)
海拔
(混搭)
方位角
(米)
WB302 -2585876.6 -9553.8 1045.35 -90 0 367.55
WB303 -2585898.7 -9607.0 1045.41 -90 0 391.18
WB304 -2585784.3 -9610.3 1047.76 -90 0 385.40
WB305 -2585950.1 -9551.2 1043.16 -90 0 349.70
WB306 -2585909.4 -9514.3 1044.05 -90 0 301.16
WB307 -2586045.2 -9725.5 1043.10 -90 0 370.50
WB308 -2585924.3 -9585.2 1044.81 -90 0 387.13
WB309 -2585972.9 -9607.3 1044.09 -90 0 362.21
WB310 -2585960.9 -9724.0 1045.07 -90 0 432.13
WB311 -2586107.0 -9903.9 1044.21 -90 0 439.90
WB312 -2586287.7 -10012.0 1041.54 -90 0 333.60
WB313 -2586389.9 -10096.0 1040.41 -90 0 345.90
WB314 -2586442.7 -10029.0 1038.20 -90 0 319.89
WB315 -2586518.3 -10101.0 1037.10 -90 0 296.60
WB316 -2586482.1 -10154.0 1038.81 -90 0 332.00
WB317 -2586722.6 -10437.0 1035.62 -90 0 387.80

Qualified Person

合資格人士

Rob van Egmond, P.Geo., a consultant geologist to the Company and a former employee, is an independent qualified person as defined in National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). Mr. van Egmond has reviewed, validated, and approved the scientific and technical information contained in this news release and has previously visited the Waterberg Project site.

Rob van Egmond,P.Geo.,該公司的地質顧問學家和前僱員,是國家儀表 43-101 礦產項目披露標準中定義的獨立合格人員(」在 43-101「)。van Egmond 先生已經審查,驗證和批准了本新聞稿中包含的科學和技術信息,並且之前曾訪問過 Waterberg 項目網站。

About Platinum Group Metals Ltd.

關於白金集團金屬有限公司

Platinum Group Metals Ltd. is the operator of the Waterberg Project, a bulk underground palladium and platinum deposit located in South Africa. The Waterberg Project was discovered by Platinum Group and is being jointly developed with Implats, Mnombo, JOGMEC and Hanwa.

鉑金集團金屬有限公司是 Waterberg 項目的運營商,該項目是位於南非的散裝地下鈀和鉑金礦床。Waterberg 項目由白金集團發現,並正在與伊普拉特斯,姆諾博,JOGMEC 和漢和共同開發。

On behalf of the Board of
Platinum Group Metals Ltd.

代表董事會
白金集團金屬有限公司

Frank R. Hallam
President, CEO and Director

弗兰克 ·R· 哈勒姆
總裁、首席執行官兼董事

For further information contact:
Kris Begic, VP, Corporate Development
Platinum Group Metals Ltd., Vancouver
Tel: (604) 899-5450 / Toll Free: (866) 899-5450

有關更多信息,請聯繫:
克里斯·貝吉克,企業發展副總裁
溫哥華白金集團金屬有限公司
電話:(六四) 899-5450 / 免付費電話:(八六六)

Disclosure

披露

The Toronto Stock Exchange ("TSX") and the NYSE American have not reviewed and do not accept responsibility for the accuracy or adequacy of this news release, which has been prepared by management.

多倫多證券交易所 (」TSX「) 和紐約證券交易所美國人沒有審查,也不承擔管理層編寫的本新聞稿的準確性或充分性的責任。

This news release contains forward-looking information within the meaning of Canadian securities laws and forward-looking statements within the meaning of U.S. securities laws (collectively "forward-looking statements"). Forward-looking statements are typically identified by words such as: "believe", "expect", "anticipate", "intend", "estimate", "may", "plans", "postulate" and similar expressions, or are those, which, by their nature, refer to future events. All statements that are not statements of historical fact are forward-looking statements. Forward-looking statements in this news release include, but are not limited to, statements regarding additional boreholes to be drilled, improved understanding of geology and economic potential of the Waterberg deposit, the potential for conversion of mineral resource blocks to higher confidence levels, potential identification of additional tonnage for inclusion in early mine plans, the updated Waterberg resource estimate and the Waterberg DFS update, optimizing the mine plan and development schedule, the anticipated Stage Two Budget time period and work program, further processing of rock material to determine dry-stack tailings characteristics and provide additional data, the possible implementation of dry stack tailings methods and results on water consumption, budgeted expenditures, the advancement of the Waterberg Project to a development and construction decision, that the Waterberg Project if developed is projected to be one of the largest and lower cost underground platinum group metals mines globally, and the Company's other future plans and expectations. Although the Company believes any forward-looking statements in this news release are reasonable, it can give no assurance that the expectations and assumptions in such statements will prove to be correct.

本新聞稿包含加拿大證券法所指的前瞻性資訊,以及美國證券法所指的前瞻性聲明(統稱為「前瞻性聲明」)。前瞻性陳述通常由諸如以下詞語來標識:「相信」,「期望」,「預期」,「意圖」,「估計」,「可能」,「計劃」,「假設」和類似的表達式,或者是那些,其性質上是指未來事件。所有不是歷史事實陳述的陳述都是前瞻性陳述。本新聞稿中的前瞻性聲明包括但不限於有關要鑽孔的聲明,改善對 Waterberg 礦床的地質和經濟潛力的了解,礦產資源塊轉化為更高的信心水平的可能性,可能識別包含在早期礦山計劃中的額外噸位,更新的 Waterberg 資源估計和 Waterberg DFS 更新,優化預算階段的開發時間表,預計的第二階段開發計劃和工作計劃、進一步加工岩材以確定乾堆尾礦特性并提供附加數據,可能實施干堆尾礦方法和結果對用水量、預算支出、Waterberg 項目的進步向發展和施工決策,即 Waterberg 項目如果開發將成為全球最大、成本較低的地下鉑金集團金屬礦場之一,以及公司未來的其他計劃和預期。儘管本公司認為本新聞稿中的任何前瞻性陳述均屬合理,但不能保證該等陳述中的期望和假設將被證明是正確的。

The Company cautions investors that any forward-looking statements by the Company are not guarantees of future results or performance and that actual results may differ materially from those in forward-looking statements as a result of various factors, including possible adverse impacts due the global outbreak of COVID-19, the Company's inability to generate sufficient cash flow or raise additional capital, and to comply with the terms of any new indebtedness; additional financing requirements; and any new indebtedness may be secured, which potentially could result in the loss of any assets pledged by the Company; the Company's history of losses and negative cash flow; the Company's properties may not be brought into a state of commercial production; uncertainty of estimated production, development plans and cost estimates for the Waterberg Project; discrepancies between actual and estimated mineral reserves and mineral resources, between actual and estimated development and operating costs, between actual and estimated metallurgical recoveries and between estimated and actual production; fluctuations in the relative values of the U.S. Dollar, the Rand and the Canadian Dollar; volatility in metals prices; the uncertainty of alternative funding sources for Waterberg JV Co.; the Company may become subject to the U.S. Investment Company Act; the failure of the Company or the other shareholders to fund their pro rata share of funding obligations for the Waterberg Project; any disputes or disagreements with the other shareholders of Waterberg JV Co. or Mnombo; the ability of the Company to retain its key management employees and skilled and experienced personnel; conflicts of interest; litigation or other administrative proceedings brought against the Company; actual or alleged breaches of governance processes or instances of fraud, bribery or corruption; exploration, development and mining risks and the inherently dangerous nature of the mining industry, and the risk of inadequate insurance or inability to obtain insurance to cover these risks and other risks and uncertainties; property and mineral title risks including defective title to mineral claims or property; changes in national and local government legislation, taxation, controls, regulations and political or economic developments in Canada and South Africa; equipment shortages and the ability of the Company to acquire necessary access rights and infrastructure for its mineral properties; environmental regulations and the ability to obtain and maintain necessary permits, including environmental authorizations and water use licences; extreme competition in the mineral exploration industry; delays in obtaining, or a failure to obtain, permits necessary for current or future operations or failures to comply with the terms of such permits; risks of doing business in South Africa, including but not limited to, labour, economic and political instability and potential changes to and failures to comply with legislation; the Company's common shares may be delisted from the NYSE American or the TSX if it cannot maintain compliance with the applicable listing requirements; and other risk factors described in the Company's most recent Form 40-F annual report, Annual Information Form and other filings with the U.S. Securities and Exchange Commission ("SEC") and the Canadian securities regulators, which may be viewed at www.sec.gov and , respectively. Proposed changes in the mineral law in South Africa if implemented as proposed would have a material adverse effect on the Company's business and potential interest in projects. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether because of new information, future events or results or otherwise.

本公司提醒投資者,本公司的任何前瞻性陳述並不保證未來業績或表現,實際業績可能與由於各種因素(包括全球爆發 COVID-19)可能造成的不良影響而有重大差異,公司無法產生足夠的現金流或籌集額外資本,以及遵守任何新的債務條款;任何新債務可能是新的融資要求;安全,這潛在可能導致公司承諾的任何資產損失; 公司的損失和負現金流的歷史; 公司的物業不得進入商業生產狀態; Waterberg 項目的估計生產,開發計劃和成本估計的不確定性; 實際和估計的礦產儲量和礦產資源之間的差異,實際和估計的冶金生產和預計生產波動之間的差異; 實際和估計的冶金生產之間的差異; 實際和估計的冶金生產之間的差異。相對的美元、蘭特和加拿大元的價值;金屬價格的波動性;Waterberg JV Co. 的替代資金來源的不確定性;公司可能受到美國投資公司法的約束;公司或其他股東未能為 Waterberg Project 提供資金義務;與 Waterberg 或 Mnoberg 其他股東的任何爭議或分歧;與 Waterberg 或 Mnoberg 的其他股東有能力提供任何爭議或分歧;公司保留其關鍵管理員工和熟練和經驗豐富的人員; 衝突利益;針對本公司提出的訴訟或其他行政訴訟;實際或指稱違反治理程序或欺詐、賄賂或腐敗的情況;勘探、開發和採礦風險以及採礦業本身危險性質,以及保險不足或無法獲得保險以涵蓋這些風險和其他風險和不確定性的風險;財產和礦產所有權風險,包括國家稅務或地方財產權變更的不良所有權的風險;,加拿大和南非的管制、法規和政治或經濟發展;設備短缺以及本公司為其礦產性獲得必要的准入權和基礎設施的能力;環境法規以及獲得和維護必要許可證的能力,包括環境授權和用水許可證;在礦物勘探行業中的極端競爭;延遲獲得或未能獲得當前或將來運營所需的許可證;符合該等失敗條款的規定。許可;在南非經營業務的風險,包括但不限於勞工、經濟和政治不穩定以及可能發生變化和未能遵守立法的風險;公司的普通股若未能維持符合適用的上市規定,可能會從 NYSE American 或多倫多證券交易所除牌;以及其他在美國證券交易所的年度報告、年度報告和證券交易委員會的其他風險因素。(」「) 和加拿大證券監管機構,可分別在 www.sec.gov 上查看。南非礦產法的建議修訂如果按建議實施,將對公司的業務和項目的潛在利益產生重大不利影響。任何前瞻性陳述僅在其製作日起發言,除適用證券法例可能要求外,本公司不承擔任何更新前瞻性聲明的意圖或義務,不論是因為新資訊、未來事件或結果或其他原因。

The technical and scientific information contained herein has been prepared in accordance with NI 43-101, which differs from the standards adopted by the SEC. Accordingly, the technical and scientific information contained herein, including any estimates of mineral reserves and mineral resources, may not be comparable to similar information disclosed by U.S. companies subject to the disclosure requirements of the SEC.

本文所包含的技術與科學資訊是依照 NI 43-101 所製備的,不同於 SEC 所採用的標準。因此,本文中包含的技術和科學資訊(包括任何礦產儲量和礦產資源的估計)可能與美國公司在符合 SEC 披露規定的情況下所披露的類似資訊相比。