Summary by Futu AI
CLP HOLDINGS released its annual report for 2024, with total generation and storage capacity reaching 22,582 megawatts, of which Wind Power capacity is 4,436 megawatts. The total amount of electrical sales reached 36,125 million kilowatt-hours, an increase of 2.1% year-on-year; regulated business profit reached 11.696 billion Hong Kong dollars, and net fixed Assets amounted to 143.124 billion Hong Kong dollars. The customer base in Hong Kong expanded to 2.83 million households, with Wind Power certificate sales reaching 0.34 billion kilowatt-hours.The company successfully put into operation the D2 Gas Generator Unit (600 megawatts) at the Longguo Beach Power Plant in April 2024, while retiring three coal-fired Generator units (A1, A2, A3) at the Castle Peak Power Plant, demonstrating CLP's commitment to accelerating energy transition. The natural gas consumption for...Show More