Bunker Hill Announces Updated Forecast for Mine Restart and Revised Financing Plan
Bunker Hill Announces Updated Forecast for Mine Restart and Revised Financing Plan
KELLOGG, Idaho and VANCOUVER, British Columbia , Dec. 13, 2024 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. ("Bunker Hill" or the "Company") (TSXV:BNKR |OTCQX:BHLL) announces that the Bunker Hill Mine restart project, which is approximately 64% complete with 98% of procurement completed, has undergone a strategic review resulting in an updated timeline and capital requirements.
愛達荷州凱洛格和不列顛哥倫比亞省溫哥華,2024年12月13日(環球新聞專線)——邦克山礦業公司(「邦克山」 或 「公司」)(多倫多證券交易所股票代碼:BNKR |OTCQX: BHLL)宣佈,邦克山礦重啓項目已完成約64%,採購已完成98%,已完成98%的採購,並對時間表和資本要求進行了更新。
Pursuant to this review, the Company now forecasts a total restart expenditure (excluding working capital) of $103 million, up from the previously forecasted $67 million and the $56 million in the 2022 Pre-Feasibility Study (the "PFS"), with the restart project anticipated to be delayed by up to four months. To provide sufficient project finance for the ongoing development of the Bunker Hill Mine, the Company intends to draw down on the $21 million standby facility (the "Standby Facility") provided by Sprott Private Resource Streaming and Royalty Corp. and finalize the ongoing discussions with its strategic partners for potential offtake or similar financing for an additional $30 million.
根據本次審查,該公司現在預計重啓總支出(不包括營運資金)爲1.03億美元,高於先前預測的6700萬美元和2022年預可行性研究(「PFS」)中的5,600萬美元,重啓項目預計將推遲多達四個月。爲了爲邦克山礦的持續開發提供充足的項目融資,該公司打算提取Sprott Private Resource Streaming and Royalty Corp. 提供的2100萬美元備用貸款(「備用設施」),並與戰略合作伙伴完成正在進行的討論,討論可能的承購或類似的額外3000萬美元融資。
Sam Ash, President and CEO, commented: "This revised plan takes full account of the many challenges facing the project and the rest of the US mining industry. Work onsite continues round the clock at the highest intensity possible to complete mechanical installation and commissioning and deliver the demanding restart plan. The adjustment we're announcing reflects the outcome of weeks of intense work by the small Bunker team, Gypsy LLC, our procurement, construction, and management contractor and their many supporters to counter the worst effects of inflation, scope changes since the PFS, and an unplanned contractor change. We are pleased to be able to draw upon the Standby Facility and conclude offtake and associated financing discussions to ensure that profitable and sustainable operations may commence by the revised start date of Q2 2025. We wish to thank our partners at Sprott Private Resource Streaming and Royalty Corp. and our many skilled contractors working on this critical US project for their steadfast and enduring support."
總裁兼首席執行官山姆·阿什評論說:「修訂後的計劃充分考慮了該項目和美國其他採礦業面臨的許多挑戰。以儘可能高的強度全天候進行現場工作,以完成機械安裝和調試並提供要求苛刻的重啓計劃。我們宣佈的調整反映了小型Bunker團隊、Gypsy LLC、我們的採購、施工和管理承包商及其衆多支持者爲應對通貨膨脹、自PFS以來範圍變化和計劃外承包商變更的最壞影響而進行的數週緊張工作的結果。我們很高興能夠利用備用資金並結束承購和相關的融資討論,以確保在修訂後的2025年第二季度開始日期之前開始盈利和可持續的運營。我們要感謝我們在Sprott Private Resource Streaming and Royalty Corp. 的合作伙伴以及我們在這個關鍵美國項目上工作的許多熟練承包商給予的堅定而持久的支持。」
STRATEGIC REVIEW – ACTIVITY AND CONCLUSIONS
戰略審查——活動和結論
Over the past eight weeks, the Company has reviewed the impact of the following key factors on the restart plan, seeking ways to mitigate them and incorporate them within the revised forecast:
在過去的八週中,公司審查了以下關鍵因素對重啓計劃的影響,尋求緩解這些影響並將其納入修訂後的預測的方法:
-
Input Cost Inflation—As widely reported across the US Mining Industry, the cost of skilled construction labor (specifically electricians) has increased by 53% over the last 12 months, from an average of $75/hour to $114/hour. The cost of structural steel has also increased by 40%, copper (a proxy for electrical fittings) by 40%, and concrete by 20%. These are extraordinary numbers that deeply impact every aspect of the project.
With labor being the primary input cost in the project's mechanical installation and commissioning phases, this has been the most challenging to mitigate. Efforts have been made to bring some of this work in-house, but these have not significantly impacted total cost projections, particularly given the impact of steel, concrete, electrical and other inflation (as crystallized in the recent and final procurement orders).
- 投入成本通貨膨脹——正如美國採礦業廣泛報道的那樣,熟練建築勞動力(特別是電工)的成本在過去12個月中增長了53%,從平均每小時75美元增加到每小時114美元。結構鋼的成本也增加了40%,銅(電氣配件的替代品)增加了40%,混凝土的成本增加了20%。這些非同尋常的數字對項目的方方面面產生了深遠影響。
由於勞動力是項目機械安裝和調試階段的主要投入成本,這是最難緩解的。已努力將其中一些工作納入內部工作,但這些工作並未對總成本預測產生重大影響,特別是考慮到鋼鐵、混凝土、電氣和其他通貨膨脹的影響(如最近的和最終的採購訂單所示)。
-
Filter Press Scope Change - As reported in the news release dated May 21, 2024 the Company chose to change the Tailings Management System envisaged in the 2022 PFS and starting budget, in order to improve long-term efficiency and sustainability, following tailings filtration testing. The more effective and expensive filter press (as compared to the $5 million disk filter system described in the 2022 PFS) passed the 90% engineering milestone in October 2024. This final design and associated inflation-effected procurement through November resulted in the final cost forecast increase from $10 million to $18 million.
-
Specialist Contractor Walk-Out - In August 2024, the specialist contractor conducting the auger-cast deep piers for the tailings filter press demobilized unexpectedly to pursue other work in North America. Given the tight market for this specialty construction work, securing and mobilizing a replacement contractor for this deep pier construction onto the mine site was challenging passing on delays to the construction timeline.
To mitigate this unexpected schedule delay, the Company conducted an engineering study to consider the deferral of the construction of the Tailings Filter Press into 2026, with tailings instead being pumped directly from the Kellogg Yard to the paste plant in the Wardner operating base and into voids underground at start-up. After conducting trade-off analysis, it was determined that this phased solution was not workable and that it would be more prudent to continue the complete construction as planned, albeit on a delayed timeline. It was judged to be far better to have the optimal system at restart geared to serving the 1,800 tons per day plan, than a potentially risky work-around that would put initial cash flow at risk.
- 壓濾機範圍變更——正如2024年5月21日的新聞稿中所報道的那樣,在尾礦過濾測試之後,公司選擇更改2022年PFS和起始預算中設想的尾礦管理系統,以提高長期效率和可持續性。更有效、更昂貴的壓濾機(與2022年PFS中描述的500萬美元盤式過濾系統相比)在2024年10月突破了90%的工程里程碑。截至11月,這一最終設計以及受通貨膨脹影響的相關採購使最終成本預測從1,000萬美元增加到1,800萬美元。
- 專業承包商退出——2024年8月,爲尾礦壓濾機進行螺旋鑄造深層碼頭的專業承包商出人意料地復員,前往北美從事其他工作。鑑於這種專業建築工程的市場緊張,爲礦場的深碼頭施工找到並調動替代承包商是一項艱鉅的任務,將延誤推遲到施工時間表上。
爲了緩解這種意想不到的計劃延遲,該公司進行了一項工程研究,考慮將尾礦壓濾機的建造推遲到2026年,改爲將尾礦直接從凱洛格造船廠泵送到沃德納運營基地的漿料廠,並在啓動時進入地下空隙。經過權衡分析,確定這種分階段的解決方案不可行,更爲謹慎的做法是繼續按計劃完成施工,儘管時間表有所延遲。據認爲,在重啓時讓最佳系統能夠滿足每天1,800噸的計劃要比將初始現金流置於風險之中的具有潛在風險的變通辦法要好得多。
Taking account of these key factors and any mitigating actions, the review determined that the project restart would be delayed until at least Q2 2025 and that the total project expenditure (including working capital) is expected to increase by approximately $50 million.
考慮到這些關鍵因素和任何緩解措施,審查確定項目重啓將至少推遲到2025年第二季度,項目總支出(包括營運資金)預計將增加約5000萬美元。
RESTART PLAN UPDATE
重新啓動計劃更新
Processing Plant - 66% complete. The mechanical installation of the final elements of the processing plant is continuing, with the phased commissioning of the circuit starting by the end of December 2024 following the plant's connection to the grid power via the Bunker Hill transformer. The external conveyor network is being installed connecting the crusher, ore silo, plant and concentrate load-out facility. Inside the main building piping, pumps, electrical infrastructure and working mezzanine platforms are installed in stages.
加工廠-已完成 66%。加工廠最後部件的機械安裝仍在繼續,在工廠通過邦克山變壓器接入電網後,電路將於 2024 年 12 月底開始分階段調試。正在安裝連接破碎機、礦石筒倉、設備和濃縮物裝載設施的外部輸送網絡。主樓內部的管道、泵、電氣基礎設施和工作夾層平台是分階段安裝的。
Figure 1: Conveyor installation
圖 1:輸送機安裝
Figure 2: Mezzanine floor and equipment installation
圖 2:夾層樓層和設備安裝
Tailings Filter Press - 38% Complete. The concrete foundations for the tailings filter press are laid in stages upon the deep piers. This is concurrent with the construction of the tailings storage tank and associated infrastructure and off-site, the final construction of the various components of the facility.
尾礦壓濾機-已完成 38%。尾礦壓濾機的混凝土基礎是分階段在深碼頭上鋪設的。這與尾礦儲罐和相關基礎設施的建造以及設施各部分的最終施工在場外同時進行。
Figure 3: Rendering of the final tailings filter press design
圖 3:最終尾礦壓濾機設計效果圖
Figure 4: Tailings storage tank construction (December 2024)
圖 4:尾礦儲罐的建造(2024 年 12 月)
Underground - 80% Complete. Conducted from the Wardner Operating Facility, the underground development continues to be on track and budget. Access to five mining stopes has already been prepared in the underground area of the mine. These are ready to be mined now. Refurbishment of the access ramp to level 8 mining areas is 75% complete. Work is currently focused on improving the ramp's geotechnical strength as it cuts through the Cate Fault; and thereby enable longer life mining than that envisaged in the 2022 PFS. Stockpiling of ore underground during the ramp refurbishment will commence by the end of 2024.
地下-80% 已完成。地下開發由Wardner運營設施進行,繼續按計劃和預算進行。礦山地下區域的五個採礦停靠點已經準備就緒。這些現在可以開採了。通往8級礦區的入口坡道的翻新已完成75%。目前的工作重點是提高坡道穿過凱特斷層時的岩土工程強度;從而使採礦壽命比2022年PFS中設想的更長。在坡道翻新期間,將在2024年底之前開始在地下儲存礦石。
Figure 5: Steel Sets supporting ramp through Cate Fault
圖 5:鋼結構支撐坡道穿過 Cate Fault
Mine Planning - This revised forecast incorporates the Company's optimization efforts conducted over the prior months to ensure the most sustainable and profitable restart operation possible while mitigating the impact of cost increases. The plan update includes an adjusted mine plan to maximize cash flows from year one.
礦山規劃-修訂後的預測納入了公司在過去幾個月中開展的優化工作,以確保儘可能實現最可持續和最有利可圖的重啓運營,同時減輕成本增加的影響。計劃更新包括調整後的礦業計劃,以最大限度地提高第一年的現金流。
Resource and Reserve Expansion - This revised forecast incorporates more drilling and technical work into the plan. Specifically, it incorporates the identified silver targets in the upper part of the mine into the early mine plan and technical studies for Bunker 2.0: the move to 2,500 tons per day. The Company is processing the data gathered from the 2024 drilling campaign and intends to issue a Resource and Reserve update as planned in Q1 2025, as well as provide periodic updates on these results over the next few weeks.
資源和儲量擴大-修訂後的預測在計劃中納入了更多的鑽探和技術工作。具體而言,它將礦山上部確定的白銀目標納入了Bunker 2.0的早期礦山計劃和技術研究:將目標提高到每天2,500噸。該公司正在處理從2024年鑽探活動中收集的數據,並打算按計劃在2025年第一季度發佈資源和儲量更新,並在未來幾周內定期提供這些結果的最新信息。
FINANCING PLAN
融資計劃
The Company intends to commence drawing in tranches upon the Standby Facility provided from December 12, 2024. The first tranche will provide $5 million in working capital. The ongoing negotiations with various financing partners to secure a $30 million financing package are expected to be concluded by the end of January 2025.
該公司打算從2024年12月12日起開始分批提取備用設施。第一筆資金將提供500萬美元的營運資金。與各融資夥伴爲獲得3000萬美元的一攬子融資而正在進行的談判預計將於2025年1月底結束。
Concurrent with this, the Company will continue to advance the process required to unlock the $150 million facility from US EXIM by the end of 2025 which the Company would utilize to refinance the existing debt and increase the mine's expected production capacity to 2,500 tons per day.
與此同時,該公司將繼續推進到2025年底從美國進出口市場解鎖1.5億美元設施所需的程序,公司將利用該設施爲現有債務再融資,並將該礦的預期產能提高到每天2,500噸。
Even with the Company's plans to secure the necessary financing for the project restart pursuant to the updated forecast, there is no certainty that the Company will be able to raise the funds required to complete the necessary development work needed to restart operations and advance the ongoing mine plan adjustments. While the Company anticipates operations to commence in the second quarter of 2025, there is no certainty that this will be the case.
儘管根據最新的預測,該公司計劃爲項目重啓提供必要的融資,但仍無法確定該公司能否籌集完成重啓運營和推進正在進行的採礦計劃調整所需的必要開發工作所需的資金。儘管該公司預計將在2025年第二季度開始運營,但尚不確定情況是否會如此。
CORPORATE UPDATE WEBINAR
企業最新動態網絡研討會
The Company will host a webinar on Friday, December 13, 2024 at 9:00am PST/12:00pm EST featuring a presentation from Bunker Hill's President and CEO Sam Ash, Executive Chairman Richard Williams and CFO Gerbrand Van Heerden. A recording of the webinar will be available on the Company's website.
該公司將於太平洋標準時間2024年12月13日星期五上午9點/美國東部時間中午12點舉辦網絡研討會,屆時邦克山總裁兼首席執行官山姆·阿什、執行董事長理查德·威廉姆斯和首席財務官格布蘭德·範·海爾登將發表演講。網絡研討會的錄音將在公司網站上公佈。
Attendees can register for the webinar using the following link:
與會者可以使用以下鏈接註冊網絡研討會:
ABOUT BUNKER HILL MINING CORP.
關於邦克山礦業公司
Under Idaho-based leadership, Bunker Hill intends to sustainably restart and develop the Bunker Hill Mine as the first step in consolidating and then optimizing a number of mining assets into a high-value portfolio of operations, centered initially in North America. Information about the Company is available on its website, www.bunkerhillmining.com, or within the SEDAR+ and EDGAR databases.
在總部位於愛達荷州的領導下,Bunker Hill打算可持續地重啓和開發邦克山礦,這是將一些礦業資產整合並優化爲最初以北美爲中心的高價值運營組合的第一步。有關該公司的信息可在其網站www.bunkerhillmining.com上或SEDAR+和EDGAR數據庫中查閱。
On behalf of the Board of Directors of Bunker Hill Mining Corp.
代表邦克山礦業公司董事會
Sam Ash
President and Chief Executive Officer
山姆·阿什
總裁兼首席執行官
For additional information, please contact:
如需更多信息,請聯繫:
Brenda Dayton
Vice President, Investor Relations
T: 604.417.7952
E: brenda.dayton@bunkerhillmining.com
布倫達·代頓
投資者關係副總裁
T: 604.417.7952
E: brenda.dayton@bunkerhillmining.com
Cautionary Statements
警示聲明
Neither the TSX Venture Exchange (the "TSX-V") nor its Regulation Services Provider (as that term is defined in the policies of the TSX-V) accepts responsibility for the adequacy or accuracy of this news release.
多倫多證券交易所風險投資交易所(「TSX-V」)及其監管服務提供商(該術語在多倫多證券交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。
Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such forward-looking statements are within the meaning of that term in Section 27A of the Securities Act and Section 21E of the U.S. Securities Exchange Act of 1934, as amended, as well as within the meaning of the phrase 'forward-looking information' in the Canadian Securities Administrators' National Instrument 51-102 – Continuous Disclosure Obligations (collectively, "forward-looking statements"). Forward-looking statements are not comprised of historical facts. Forward-looking statements include estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", "plan" or variations of such words and phrases.
本新聞稿中的某些陳述是前瞻性的,涉及許多風險和不確定性。此類前瞻性陳述符合《證券法》第27A條和經修訂的1934年《美國證券交易法》第21E條中該術語的含義,也符合加拿大證券管理局國家工具51-102——持續披露義務(統稱爲 「前瞻性陳述」)中 「前瞻性信息」 一詞的含義。前瞻性陳述不包含歷史事實。前瞻性陳述包括描述公司未來計劃、目標或目標的估計和陳述,包括大意爲公司或管理層預計將出現既定條件或結果的言論。前瞻性陳述可以用 「相信」、「預期」、「預期」、「估計」、「可能」、「可能」、「將」、「將」、「計劃」 等術語或此類詞語和短語的變體來識別。
Forward-looking statements in this news release include, but are not limited to, statements regarding: the Company's objectives, goals or future plans, including the restart and development of the Bunker Hill Mine and the updated timeline and forecast and anticipated capital requirements in connection therewith; the achievement of future short-term, medium-term and long-term operational strategies and objectives and the expected timing thereof, including with respect to planned production; the Company raising the required funds for the planned project restart through its project finance initiatives, including by way of debt, equity, offtake or similar financings; and the expected budget and estimated completion time for the underground development of the Bunker Hill Mine. Forward-looking statements reflect material expectations and assumptions, including, without limitation, expectations and assumptions relating to: Bunker Hill's ability to receive sufficient project financing for the restart and development of the Bunker Hill Mine on acceptable terms or at all; the revised forecast, capital requirements and updated timeline for the project restart resulting in planned production by Q2 2025; the future price of metals; and the stability of the financial and capital markets. Factors that could cause actual results to differ materially from such forward-looking statements include, but are not limited to, those risks and uncertainties identified in public filings made by Bunker Hill with the U.S. Securities and Exchange Commission (the "SEC") and with applicable Canadian securities regulatory authorities, and the following: the Company's ability to operate as a going concern and its history of losses; the Company's ability to raise sufficient project financing for the restart and development of the Bunker Hill Mine on acceptable terms or at all, including through equity or debt financings, concentrate offtake financings or otherwise; the Company requiring more capital expenditures than anticipated in the updated forecast, resulting in delays in the updated timeline; the fluctuating price of commodities; capital market conditions; restrictions on labor and its effects on international travel and supply chains; failure to identify mineral resources; failure to convert estimated mineral resources to reserves; the preliminary nature of metallurgical test results; the Company's ability to restart and develop the Bunker Hill Mine and the risks of not basing a production decision on a feasibility study of mineral reserves demonstrating economic and technical viability, resulting in increased uncertainty due to multiple technical and economic risks of failure which are associated with this production decision including, among others, areas that are analyzed in more detail in a feasibility study, such as applying economic analysis to resources and reserves, more detailed metallurgy and a number of specialized studies in areas such as mining and recovery methods, market analysis, and environmental and community impacts and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit, with no guarantee that production will begin as anticipated or at all or that anticipated production costs will be achieved; failure to commence production would have a material adverse impact on the Company's ability to generate revenue and cash flow to fund operations; failure to achieve the anticipated production costs would have a material adverse impact on the Company's cash flow and future profitability; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; political risks; changes in equity markets; uncertainties relating to the availability and costs of financing needed in the future; the inability of the Company to budget and manage its liquidity in light of the failure to obtain additional financing, including the ability of the Company to complete the payments pursuant to the terms of the agreement to acquire the Bunker Hill Mine complex; inflation; changes in exchange rates; changes in labor costs and availability of skilled labor and specialists; fluctuations in commodity prices; delays in the development of projects; and capital, operating and reclamation costs varying significantly from estimates and the other risks involved in the mineral exploration and development industry. Although the Company believes that the assumptions and factors used in preparing the forward-looking statements in this news release are reasonable, undue reliance should not be placed on such statements or information, which only applies as of the date of this news release, and no assurance can be given that such events will occur in the disclosed time frames or at all, including as to whether or when the Company will achieve its project finance initiatives, or as to the actual size or terms of those financing initiatives or as to whether and when the Company will achieve its operational and construction targets. The Company disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise, other than as required by law. No stock exchange, securities commission or other regulatory authority has approved or disapproved the information contained herein.
本新聞稿中的前瞻性陳述包括但不限於以下方面的陳述:公司的目標、目標或未來計劃,包括邦克山礦的重啓和開發以及最新的時間表和預測以及與之相關的預期資本需求;未來短期、中期和長期運營戰略和目標的實現及其預期時機,包括計劃生產;公司爲計劃項目重啓籌集所需資金通過其項目融資舉措,包括債務、股權、承購或類似融資;以及邦克山礦地下開發的預期預算和預計完工時間。前瞻性陳述反映了實質性預期和假設,包括但不限於以下方面的預期和假設:邦克希爾獲得足夠的項目融資,以可接受的條件或完全可以接受的條件重啓和開發;修訂後的預測、資本要求和最新的項目重啓時間表,從而計劃於2025年第二季度生產;金屬的未來價格;以及金融和資本市場的穩定。可能導致實際業績與此類前瞻性陳述存在重大差異的因素包括但不限於邦克希爾在向美國證券交易委員會(「SEC」)和適用的加拿大證券監管機構提交的公開文件中確定的風險和不確定性,以及以下方面:公司持續經營的能力及其虧損記錄;公司爲重啓和開發Bunker Bunker Hill籌集足夠項目融資的能力以可接受的條件進行 Ker Hill Mine或者根本如此,包括通過股權或債務融資、集中承購融資或其他方式;公司需要的資本支出超過最新預測中的預期,導致更新的時間表延遲;大宗商品價格波動;資本市場狀況;勞動力限制及其對國際旅行和供應鏈的影響;未能確定礦產資源;未能將估計的礦產資源轉換爲儲量;冶金測試結果的初步性質;公司的重啓能力並開發邦克山礦,以及不以顯示經濟和技術可行性的礦產儲量可行性研究作爲生產決策基礎的風險,由於與該生產決策相關的多種技術和經濟失敗風險,包括在可行性研究中更詳細分析的領域,例如對資源和儲量進行經濟分析,更詳細的冶金以及採礦和開採等領域的許多專業研究,從而增加不確定性方法、市場分析以及環境和社區影響,因此,實現任何特定水平的礦物回收或回收成本的不確定性可能會增加,包括與開發商業可開採礦牀相關的風險增加,無法保證會按預期開始生產,也無法保證實現預期的生產成本;未能開始生產將對公司創造收入和現金流爲運營提供資金的能力產生重大不利影響;未能實現預期的生產成本將對公司的現金流和未來的盈利能力產生重大不利影響;延遲獲得或未能獲得所需的政府、環境或其他項目批准;政治風險;股票市場的變化;與未來所需融資的可用性和成本有關的不確定性;由於未能獲得額外融資,包括公司完成付款的能力,公司無法預算和管理其流動性根據收購邦克山礦綜合體的協議條款;通貨膨脹;匯率變動;勞動力成本和熟練勞動力和專家供應的變化;大宗商品價格的波動;項目開發的延遲;資本、運營和回收成本與估計以及礦產勘探和開發行業所涉及的其他風險有很大差異。儘管公司認爲本新聞稿中編制前瞻性陳述時使用的假設和因素是合理的,但不應過分依賴此類陳述或信息,這些陳述或信息僅適用於本新聞發佈之日,也無法保證此類事件將在披露的時間範圍內發生,或根本無法保證此類事件將在披露的時間範圍內發生,包括公司是否或何時實現其項目融資計劃,或這些融資計劃的實際規模或條款,或關於公司是否以及何時將實現其運營和建設目標。除非法律要求,否則公司不打算或義務更新或修改任何前瞻性信息,無論這些信息是由於新信息、未來事件還是其他原因造成的。沒有任何證券交易所、證券委員會或其他監管機構批准或不批准此處包含的信息。
Readers are cautioned that the foregoing risks and uncertainties are not exhaustive. Additional information on these and other risk factors that could affect the Company's operations or financial results are included in the Company's annual report and may be accessed through the SEDAR+ website () or through EDGAR on the SEC website (www.sec.gov).
提醒讀者,上述風險和不確定性並非詳盡無遺。有關這些風險因素和其他可能影響公司運營或財務業績的風險因素的更多信息包含在公司的年度報告中,可通過SEDAR+網站()或通過美國證券交易委員會網站(www.sec.gov)上的EDGAR進行訪問。
Photos accompanying this announcement are available at:
本公告附帶的照片可在以下網址獲得:
譯文內容由第三人軟體翻譯。