Monument Announces Updates at the Selinsing Gold Mine and Murchison Gold Project
Monument Announces Updates at the Selinsing Gold Mine and Murchison Gold Project
VANCOUVER, British Columbia, Dec. 09, 2024 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or the "Company") announces progress updates at the Selinsing Gold Mine in Malaysia and at the Murchison Gold Project in Western Australia.
溫哥華,英屬哥倫比亞,2024年12月09日(環球新聞)-- Monument Mining Limited(TSX-V: MMY 和 FSE: D7Q1)("Monument"或"公司")宣佈在馬來西亞Selinsing黃金礦和澳洲西部Murchison黃金項目的進展更新。
President and CEO Cathy Zhai commented, "We are pleased with the continued progress at the Selinsing Gold Mine to optimize the gold treatment plant, especially the bigger filter press to be installed to enhance the production respectively in mid-January 2025. Additionally, we are excited to announce the resumption of development work at the Murchison Gold Project."
總裁兼首席執行官Cathy Zhai評論道:"我們對Selinsing黃金礦在優化黃金處理廠方面的持續進展感到滿意,特別是在2025年1月中旬將安裝更大的濾壓機以提高生產。此外,我們很高興地宣佈Murchison黃金項目的開發工作將恢復。"
Selinsing Update
Selinsing更新
Figure 1: Selinsing Flotation Plant
圖1:Selinsing浮選廠
Figure 1 is available at
圖1可用在
The Company continues to improve operational efficiencies and effectiveness at Selinsing Gold Mine through removal of certain bottlenecks from the processing plant and improvements of mining cycle harmonization.
公司繼續通過消除處理廠的某些瓶頸以及改善礦業週期協調性,來提高Selinsing黃金礦的運營效率和有效性。
Plant Process Improvements
工廠流程改進
Numerous improvements were made in the flotation circuit to help improve recovery. The addition of soda ash continued as pH modifier and bulk orders were initiated for delivery to the repurposed lime silo to facilitate better pH control during the processing of partially oxidised transition ore. Measurement and control of the oxidation – reduction potential (ORP) was implemented by the precise dosing of sodium sulphide. Froth stability was improved by the introduction of ethylene glycol frother. Flotation recoveries have improved in October with a reconciled 87.2% reported for the month and over 90% achieved for some of the fresh ores processed. The antimony content of the Buffalo Reef ore has proved to be higher than expected and stibnite recovery has been enhanced by the addition of lead nitrate. Improved payabilities have been realized with the high levels of antimony in the flotation concentrate.
爲了提高回收率,浮選迴路進行了多項改進。繼續添加蘇打粉作爲pH調節劑,並下達了大宗訂單,以便將其送至重新利用的石灰倉,促進在處理部分氧化的過渡礦石時實現更好的pH控制。通過精確投加硫化鈉,實現了氧化還原電位(ORP)的測量和控制。通過引入乙二醇起泡劑,泡沫穩定性得到了改善。10月份浮選回收率有所提高,該月份報告的回收率爲87.2%,而一些處理的新鮮礦石回收率超過90%。Buffalo Reef礦石的銻含量被證明高於預期,添加鉛硝酸鹽後改善了銻的回收。由於浮選濃縮物中高水平的銻,實現了更好的支付能力。
The performance of the filter press improved with better concentrate quality, pH adjustment in the concentrate surge tank and replacement of filter plates. Eight new filter plates from the manufacturers McLanahan were installed on the filter press and the local repair of worn plates continued. Worn-out filter cloths were replaced as required.
過濾機的性能得到了改善,得益於更好的濃縮液質量、濃縮液調節槽中的pH值調整以及過濾板的更換。來自制造商McLanahan的八塊新過濾板被安裝在過濾機上,局部維修磨損的板繼續進行。根據需要更換了磨損的濾布。
A bigger capacity filter press was designed and built by a major manufacturer and was delivered to site, installation has been scheduled and expected to be completed in early January 2025, pending completion of all civil works that commenced in September 2024. Up to date procurement of associated new ancillary equipment is in progress with long lead items being ordered. Concrete was poured for the extension to the air services building, air receivers, filter feed tank and filter press bunker. The air compressor, air receivers and dryer were delivered to site and installed. The filter feed tank was fabricated on site and lifted into position. The powerline and various pipelines were rerouted away from the footprint of the new filter press to allow excavations to be completed and foundation work to progress.
一臺更大容量的過濾機由一家主要製造商設計並建造,已送達現場,安裝已安排,並預計在2025年1月初完成,前提是所有自2024年9月開始的土建工程完成。相關的新輔助設備的採購正在進行中,長交貨期的項目已經下單。混凝土已爲空氣服務建築的擴展、空氣接收器、過濾進料槽和過濾機倉庫澆築。空氣壓縮機、空氣接收器和乾燥機已送達現場並安裝。過濾進料槽在現場製造並被抬入位置。電力線和各種管道已從新過濾機的佔地面積重新改道,以便完成挖掘和基礎施工的進展。
Tailings Storage Facility
尾礦儲存設施
A buttress along the toe of the main embankment is required to raise the factor of safety ahead of the next construction raise planned for 2025. The construction was completed using waste material from the Buffalo Reef pits. A bathymetric and drone survey was carried out to determine the in-situ dry density of deposited tailings and to confirm the remaining tailings capacity for the timing of the next raise.
在主堤的腳部需要一個支撐體,以提高安全係數,以便於計劃在2025年進行的下一個施工提升。該施工使用了來自水牛礁礦坑的廢料完成。進行了水下測量和無人機調查,以判斷沉積尾礦的原位幹密度,並確認下一個提升的尾礦剩餘容量。
Mining and Ore Stockpile Buildup
採礦和礦石堆積
Mining continued at Buffalo Reef pits BRC2, BRC3 and BRC4. Deliveries of both fresh and transition ore continued, and the run of mine (ROM) sulphide ore stockpile is around 240,000 tonnes, adequate for 3 months' plant feed, but not beyond to avoid oxidation.
在Buffalo Reef礦區的BRC2、BRC3和BRC4繼續進行採礦。新鮮礦石和過渡礦石的交付持續進行,運行的礦石(ROM)硫化礦石堆積約爲240,000噸,足夠供3個月的工廠使用,但不能超過以免氧化。
Figure 2: Mining at Selinsing
圖2:在Selinsing的採礦
Figure 2 is available at
圖2可在此處獲得
The method of reverse circulation grade control ("RCGC") drilling was tested to a vertical depth of 20 metres over an area within BRC2. The assay results have been compared to the assay results at the same area from the conventional blast hole drilling ("BHGC") currently in use, which shows that both methods are comparable and RCGC drilling respectably will provide longer term forecasting of concentrate production while also improve the accuracy of the medium-term mine planning as compared to the current resource model.
反循環等級控制 ("RCGC") 鑽探方法已在 BRC2 區域內進行到 20 米的垂直深度測試。化驗結果已與目前使用的傳統爆破孔鑽探 ("BHGC") 在同一區域的化驗結果進行比較,顯示兩種方法具有可比性,並且 RCGC 鑽探可以提供更長時期的精礦生產預測,同時提高中期礦山規劃的準確性,相較於當前的資源模型。
Exploration drilling activity is planned to commence in January 2025. The program will be announced accordingly and will be focused on upgrading the existing resources under the Buffalo Reef ore body to potentially expand the life of mine. It will also include some step out drill holes to test the mineralization extension that may potentially increase the current resources. The drilling work will be conducted by an in-house drill team with two drilling machines, currently being serviced and equipped with the necessary consumables, accessories, and spares.
勘探鑽探活動計劃於 2025 年 1 月開始。該計劃將相應公佈,重點是升級 Buffalo Reef 礦體下的現有資源,以潛在擴展礦山的生命週期。它還將包括一些擴展鑽孔,以測試可能增加當前資源的礦化延伸。鑽探工作將由內部鑽探團隊進行,使用兩臺正在維護中的鑽探機器,並配備必要的消耗品、配件和備件。
Murchison Gold Project Update
Murchison 黃金項目更新
The Company has resumed technical and financial studies to research the re-start of operations at its Murchison Gold Project. While the Company's recent focus has been on optimizing production from its Selinsing Gold Mine, it is also looking to update the Mineral Resource base at its Australian gold assets.
公司已恢復對其 Murchison 黃金項目運營重啓的技術和財務研究。雖然公司最近的重點是優化 Selinsing 黃金礦的生產,但它也在尋求更新其澳大利亞黃金資產的涉礦概念基礎。
At Burnakura, the Company has previously received all required approvals to recommence production and has been regularly renewing the corresponding environmental compliance permits for the approved plan. However, since that time the gold price has risen considerably, thus a review is needed of the Resources as well as updated capital and production costs on the project to re-optimize future production. Corresponding updates in permitting may be required but would only be amendments to already approved licenses. Due to this fact, Monument has considerable optionality on how to proceed with the re-start.
在Burnakura,公司之前已經獲得所有所需的批准,以重新開始生產,並且定期更新相應的環保合規許可證。然而,自那時以來,黃金價格大幅上升,因此需要對資源進行審查,並更新項目的資本和生產成本,以重新優化未來的生產。相應的許可更新可能是必要的,但僅是對已批准許可證的修訂。由於這一事實,Monument在如何進行重新啓動方面有相當大的選擇性。
The Company will be commencing studies into different options to commence production including the current capacity of 260,000 tpa (tonnes per annum) and a potential upgrade to a production rate of 750,000 tpa. Economic viability will be consequent on the updated Mineral Resource Estimates and the optimized production profiles from mining studies across both project areas. Local third parties have also expressed interest in having ore processed in the Burnakura plant. Evaluation of such options may be included in the eventual re-start schedule depending on the capability and capacity of these third parties to commit to a complementary production schedule. Any updates in regulatory permitting and licensing requirements will be honed from the results of optimized mining studies.
公司將開始研究不同的選項以啓動生產,包括當前的年產能力爲260,000噸以及潛在的升級到750,000噸的生產速率。經濟可行性將取決於更新的涉礦概念估算和兩個項目區域的優化生產概況。當地第三方也表示有興趣在Burnakura工廠進行礦石加工。根據這些第三方能夠承諾互補生產時間表的能力和容量,這些選項的評估可能會被納入最終的重新啓動時間表中。任何監管許可和許可要求的更新將從優化的礦業研究結果中提煉出來。
At Gabanintha, there are six historical open pits with high grade mineralization open at depth and along strike. To firm up the historical figures and extend the known mineralization, the company plans to systematically drill five of the deposits as well as conduct metallurgical testwork on potential ore-grade material from the deposits to help optimize gold recovery. Several promising exploration targets will also be tested. Drilling will commence as soon as all required permits are received. With 95% of historical drilling on the project only reaching 100m depth and several attractive exploration targets to be examined, there is significant potential for an increased Resource inventory.
在Gabanintha,有六個歷史開放礦坑,具有高品位的礦化,在深度和延伸方向上開放。爲了確認歷史數據並擴展已知礦化,公司計劃系統地對五個礦牀進行鑽探,並對來自礦牀的潛在礦石材料進行冶金測試,以幫助優化黃金回收。還將測試一些有前景的勘探目標。一旦收到所有所需許可證,將馬上開始鑽探。由於該項目95%的歷史鑽探僅達到10000萬深度,還有幾個有吸引力的勘探目標待考察,因此增加資源儲備的潛力顯著。
The Company has been actively engaging with local and regional stakeholders for the purposes of building productive relationships for the life of the project and to provide beneficial long-term solutions for end of mine life land uses.
公司一直積極與當地和區域利益相關者進行溝通,以建立項目生命週期內的有效關係,併爲礦山關閉後的土地使用提供有益的長期解決方案。
About Monument
關於紀念碑
Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) is an established Canadian gold producer that 100% owns and operates the Selinsing Gold Mine in Malaysia and the Murchison Gold Project in the Murchison area of Western Australia. It has 20% interest in Tuckanarra Gold Project jointly owned with Odyssey Gold Ltd in the same region. The Company employs approximately 250 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.
紀念碑採礦有限公司(TSX-V: MMY,FSE: D7Q1)是一家已建立的加拿大黃金生產商,100%擁有並運營位於馬來西亞的Selinsing金礦和位於澳洲西部Murchison地區的Murchison黃金項目。它在同一地區與Odyssey Gold Ltd共同擁有Tuckanarra黃金項目,持有20%的股份。公司在這兩個區域僱傭約250名員工,並致力於爲員工和周邊社區提供最高標準的環保管理、社會責任以及健康和安全保障。
Cathy Zhai, President and CEO
Monument Mining Limited
Suite 1580 - 1100 Melville Street
Vancouver, BC V6E 4A6
Cathy Zhai,董事長兼首席執行官
豐碑礦業有限公司
梅爾維爾街1100號1580套間
加拿大不列顛哥倫比亞省溫哥華 V6E 4A6
FOR FURTHER INFORMATION visit the company web site at or contact:
欲了解更多信息,請訪問公司網站或聯繫:
Richard Cushing, MMY Vancouver T: +1-604-638-1661 x102 rcushing@monumentmining.com
Richard Cushing, MMY 溫哥華 T: +1-604-638-1661 x102 rcushing@monumentmining.com
"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."
"無論是TSX創業公司交易所還是其監管服務提供商(按照TSX創業公司交易所政策中的定義)對此發佈的 adequacy 或準確性不承擔任何責任。"
Disclaimer Regarding Forward-Looking Statements
關於未來聲明的免責聲明
This news release includes statements containing forward-looking information about Monument, its business and future plans ("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or future events that are not historical facts and include the Company's plans with respect to its mineral projects, expectations regarding the completion of the ramp-up period to target production level at Selinsing and the timing thereof, expectations regarding the Company's continuing ability to source explosives from suppliers, expectations regarding completion of the proposed storage shed and ammonium nitrate depot and the timing thereof, and the timing and results of the other proposed programs and events referred to in this news release. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward-looking statements in this news release are subject to various risks, uncertainties and other factors that could cause actual results or achievements to differ materially from those expressed or implied by the forward-looking statements. These risks and certain other factors include, without limitation: risks related to general business, economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timing of development activities, including those related to the ramp-up process at Selinsing and the completion of the proposed storage shed and ammonium nitrate depot; uncertainties and risks related to the Company's ability to source explosives from suppliers; foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at . Material factors and assumptions used to develop forward-looking statements in this news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows which may be generated from the operations, general economic factors and other factors that may be beyond the control of Monument; assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding the future price of gold of other minerals; the timing and amount of estimated future production; assumptions regarding the timing and results of development activities, including the ramp-up process at Selinsing and the completion of the proposed storage shed and ammonium nitrate depot; expectations that the Company will continue to be able to source explosives from suppliers in a timely manner; costs of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at . Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.
本新聞稿包括關於Monument及其業務和未來計劃("未來聲明")的前瞻性信息。前瞻性聲明是指那些涉及預期、計劃、目標或未來事件的聲明,這些內容並非歷史事實,包括公司在其礦產項目上的計劃、關於在Selinsing達到目標生產水平的加速期完成的預期及其時間、關於公司持續從供應商那裏採購炸藥的預期、關於擬建儲藏棚和硝酸銨倉庫的完成及其時間的預期,以及本新聞稿提到的其他擬議項目和事件的時間和結果。一般來說,前瞻性信息可以通過使用前瞻性術語來識別,例如 "計劃"、"預期"或 "不預期"、"被期待"、"預算"、"計劃"、"預計"、"預測"、"意圖"、"預計"或 "不預計",或者 "相信",或這些詞和短語的變體,或者說明特定的行動、事件或結果 "可能"、"可以"、"會"、"也許"或 "將被採取"、"發生"或 "實現"。本新聞稿中的前瞻性聲明受到各種風險、不確定性和其他因素的影響,這些因素可能導致實際結果或成就與前瞻性聲明中表達或暗示的內容有實質性差異。這些風險及某些其他因素包括但不限於:與一般業務、經濟、競爭、地緣政治和社會不確定性相關的風險;有關當前勘探活動結果的不確定性;與開發活動的進展和時間安排的不確定性,包括與Selinsing上升過程相關的活動以及擬建儲藏棚和硝酸銨倉庫的完成;與公司從供應商處採購炸藥能力相關的不確定性和風險;海外運營風險;以及採礦行業固有的其他風險和在公司管理討論和分析以及公司項目的技術報告中描述的其他風險,所有這些均可在SEDAR上的公司資料下獲取。本新聞稿中用於制定前瞻性聲明的重要因素和假設包括:關於每盎司黃金生產預計現金成本的預期和從運營中可能產生的預計現金流,一般經濟因素及其他可能超出Monument控制的因素;關於公司項目勘探結果的假設和預期;關於其他礦物未來價格的假設;關於預計未來生產的時間和數量的假設;關於開發活動的時間和結果的假設,包括Selinsing的加速過程以及擬建儲藏棚和硝酸銨倉庫的完成;預計公司將繼續能及時從供應商處採購炸藥;未來活動的成本;資本和運營支出;勘探活動的成功;採礦或加工問題;匯率;以及公司管理討論和分析和公司項目技術報告中描述的所有因素和假設,所有這些均可在SEDAR上的公司資料下獲取。儘管公司已嘗試識別可能導致實際結果與前瞻性聲明中包含的結果有實質性差異的重要因素,但仍可能存在其他因素導致結果未如預期、估計或計劃。無法保證該等聲明將被證明是準確的,因爲實際結果和未來事件可能明顯偏離該等聲明中預計的內容。因此,讀者不應對前瞻性聲明寄予過高的期望。除非根據適用的證券法律,否則公司不承擔更新任何前瞻性聲明的責任。
譯文內容由第三人軟體翻譯。