share_log

IAMGOLD Provides Westwood Updated Mine Plan and Mineral Resource & Mineral Reserve Estimates

IAMGOLD Provides Westwood Updated Mine Plan and Mineral Resource & Mineral Reserve Estimates

iamgold 提供了Westwood的最新礦山規劃及涉礦概念與礦藏儲量評估
newsfile ·  12/05 20:00

All monetary amounts are expressed in U.S. dollars, unless otherwise indicated.

除非另有說明,否則所有貨幣金額均以美元表示。

Toronto, Ontario--(Newsfile Corp. - December 5, 2024) - IAMGOLD Corporation (NYSE: IAG) (TSX: IMG) ("IAMGOLD" or the "Company") is pleased to provide updated Mineral Resource and Mineral Reserve ("MRMR") estimates and an accompanying updated life of mine ("LOM") plan for the Company's Westwood Complex (the "Project" or "Westwood"), located in Quebec, Canada. IAMGOLD will file an updated NI 43-101 technical report for the updated MRMR and LOM plan on SEDAR at within 45 days of the date of this news release. The MRMR estimates were prepared in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") Definition Standards incorporated by reference in National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

安大略省多倫多--(資訊公司 - 2024年12月5日)- iamgold公司(紐交所:IAG)(tsx:IMG)("iamgold"或"公司")很高興提供更新的涉礦概念和礦藏("mrmr")估算,以及公司西木複合體("項目"或"西木")的生命週期計劃("lom")的更新。該複合體位於加拿大魁北克省。iamgold將在本新聞稿發佈日起45天內在sedar上提交更新後的NI 43-101技術報告,包含更新的mrmr和lom計劃。mrmr的估算根據加拿大礦業、冶金和石油學會("cim")的定義標準編制,引用於國家工具43-101 - 礦產項目的披露標準("ni 43-101")。

Highlights of updated Technical Report

更新技術報告的亮點

  • Update life of mine from 2025 to 2032, driven by underground Mineral Reserves at Westwood of 2.6 million tonnes ("Mt") averaging 11.45 grams per tonne gold ("g/t Au") containing 955,400 ounces.

  • Overall LOM production of 925,000 ounces of gold ("oz Au"), with an annual average gold production of approximately 146,000 oz Au in the first three years (2025 to 2027).

  • Average recoveries of 95% from the processing plant with capacity of 1.0 Mt per year. Mine plan envisions adjusting to a batch processing schedule to manage excess capacity as Grand Duc open pit supplementary ore feed ends.

  • Average estimated operating costs over the LOM (2025-2032) on a unit basis for Westwood Complex estimated at $239.91/t processed.

  • Total sustaining capital expenditures over life of mine estimated at $260.7 million.

  • Measured and Indicated Mineral Resources (inclusive of those Mineral Resources converted to Mineral Reserves):

    • - Westwood: 3.97 Mt grading 12.80 g/t Au containing 1.6 million ounces;

    • - Grand Duc: 3.01 Mt grading 1.25 g/t Au containing 121,000 ounces.

  • Inferred Mineral Resources:

    • - Westwood: 4.29 Mt grading 13.03 g/t Au containing 1.8 million ounces;

    • - Grand Duc: 0.08 Mt grading 1.28 g/t Au containing 3,300 ounces.

  • Grand Duc mine life assumed to conclude in 2025 with processing completed in 2027. The Grand Duc deposit remains open westward and locally to the east.

  • Westwood deposit remains open at depth, westward and locally to the east along the untested mineralized Westwood, North and Zone-2 corridors.

  • 生命週期更新,從2025年至2032年,由西木的260萬噸("mt")地下礦藏驅動,平均每噸金礦含11.45克("g/t Au"),包含955,400盎司。

  • 生命週期總生產量預計爲925,000盎司黃金("oz Au"),前三年(2025年至2027年)年均黃金生產量約爲146,000 oz Au。

  • 加工廠的平均回收率爲95%,年處理能力爲1.0萬噸。礦山計劃設想調整爲批量處理計劃,以管理隨着格朗德杜克露天礦補充礦石供應結束而產生的過剩產能。

  • 西木複合體在生命週期(2025-2032)上的單位運行成本估算爲每處理239.91美元/噸。

  • 整個生命週期的總維持資本支出估算爲26070萬美元。

  • 已計量和指示的涉礦概念(包括轉爲礦產儲量的那些涉礦概念):

    • - Westwood: 3.97萬噸,品位12.80克/噸黃金,包含160萬盎司;

    • - Grand Duc: 3.01萬噸,品位1.25克/噸黃金,包含121,000盎司。

  • 推測的涉礦概念:

    • - Westwood: 4.29萬噸,品位13.03克/噸黃金,包含180萬盎司;

    • - Grand Duc: 0.08萬噸,品位1.28克/噸黃金,包含3,300盎司。

  • Grand Duc礦的壽命預計在2025年結束,處理工作將在2027年完成。Grand Duc儲量在西部和東部局部地區仍然開放。

  • Westwood儲量在深度、西部和東部局部區域仍然開放,沿着未經測試的礦化Westwood、North和Zone-2走廊。

"The transformation of Westwood is among the top mining success stories in our industry," commented Renaud Adams, President and Chief Executive Officer of IAMGOLD. "The ability of our teams to re-engineer, rebuild, and resume full underground mining activities was the result of tireless commitment, teamwork, and a steadfast commitment to safety. The updated mine plan demonstrates the ability of Westwood to continue to expand underground operating areas, with a mine plan based on reserves of nearly a million ounces and mining assumptions at a $1,500 per ounce reserve gold price. This plan provides a good frame of reference for our stakeholders, and it is worth highlighting that underground mining activities at Westwood have historically extracted a significant portion of resources alongside reserves during day-to-day operations - particularly during periods of higher gold spot prices. Financially, in the last two quarters, we have seen Westwood begin to generate significant value, reporting total mine-site free cash flow of $42.6 million in this period. As mining continues to upgrade ounces and open up new mining areas through improved ground control methods and seismicity mitigation measures, we see high potential for further mine life extension and expansion of the current mineralized envelope."

"Westwood的轉型是我們行業中最成功的礦業故事之一,"IAMGOLD的總裁兼首席執行官Renaud Adams評論道。"我們團隊重新設計、重建並恢復全面地下開採活動的能力,得益於不懈的努力、團隊合作和對安全的堅定承諾。更新後的礦山計劃證明了Westwood繼續擴展地下作業區域的能力,該礦井計劃基於近一百萬盎司的儲量和每盎司1,500美元的金價假設。這個計劃爲我們的利益相關者提供了良好的參考框架,值得強調的是,Westwood的地下采礦活動在日常運營中歷史上提取了顯著的資源和儲量 - 尤其是在黃金現貨價格較高的時段。財務方面,在過去兩個季度中,我們看到Westwood開始創造顯著價值,在此期間報告的礦山現場自由現金流爲4260萬。這一過程伴隨着通過改進的地面控制方法和抗震措施繼續升級盎司並開闢新的採礦區域,我們看到了進一步延長礦山壽命和擴展當前涉礦概念的高潛力。

IAMGOLD holds a 100% interest in the Westwood Complex. The Project consists of two property areas, Doyon-Westwood and Fayolle. The Doyon-Westwood property includes the Westwood underground mine, and Grand Duc open pit, collectively the Westwood Complex. The Westwood mine has been in operation since 2014, when commercial production was declared, and Grand Duc since October 2019. Open pit operations at the Fayolle deposit commenced in February 2023 and the deposit was mined out in June 2024. The Fayolle open pit and associated infrastructure were being reclaimed at the Report effective date.

IAMGOLD對Westwood綜合體持有100%的權益。該項目包括兩個物業區域,Doyon-Westwood和Fayolle。Doyon-Westwood物業包括Westwood地下礦和Grand Duc露天礦,共同構成Westwood綜合體。Westwood礦自2014年開始運營,當時宣告商業生產,而Grand Duc自2019年10月起運營。Fayolle礦的露天開採於2023年2月開始,直到2024年6月該礦被開採完畢。Fayolle露天礦及相關基礎設施在報告生效日期時正在進行修復。

Mineral Resources

礦業資產

Table 1 - Mineral Resource Statement, Westwood Mine

表1 - 涉礦概念聲明,Westwood礦

Class Tonnes Gold Grade
(g/t Au)
Contained Ounces
Measured 777,000 13.09 327,000
Measured (Stockpiles) 4,000 8.64 1,200
Indicated 3,190,000 12.74 1,306,700
Measured + Indicated 3,971,000 12.80 1,634,900
Inferred 4,289,000 13.03 1,797,400
類別 金品位
(每噸含金克數)
包含的盎司
測量 777,000 13.09 327,000
測量(庫存) 4,000 8.64 1,200
指示資源 3,190,000 12.74 1,306,700
已知和指示資源總計 3,971,000 12.80 1,634,900
詳見2024年4月3日新聞稿 4,289,000 13.03 1,797,400

Notes:

注:

  1. The effective date of the Mineral Resource estimate is 30 September, 2024.
  2. The Qualified Person for the estimate excepting stockpiles is Martin Perron, P.Eng., from Norda Stelo Inc. The Qualified Person for the stockpile estimate is Mr. Louis Nkoy Manda Mbomba, P.Eng., an IAMGOLD employee.
  3. Mineral Resources are reported inclusive of Mineral Reserves. Mineral Resources that are not converted to Mineral Reserves have not demonstrated economic viability.
  4. The estimate encompasses 128 mineralized lenses in three zones (Corridor North, Westwood, and Zone 2 Extension) using the grade of the adjacent material when assayed or a value of zero when not assayed. Three dilution buffer zones encompassing all mineralized zones (one for each zone) were created to better reflect the internal dilution within the constraining shapes.
  5. High-grade capping supported by statistical analysis was done on raw assay data before compositing. It was established on a zone-by-zone basis, varying from 75-500 g/t Au for mineralized zones and 10-20 g/t Au for the dilution buffer zones. Composites (1.0 m) were calculated within the zones using the grade of the adjacent material when assayed or a value of zero when not assayed.
  6. The estimate was completed using a sub-block model in Isatis.neo 2024.04. The parent block size was 4 x 1 x 4 m (subblocks of 1 x 0.5 x 1 m).
  7. Grade interpolation was obtained by multiple-indicator kriging for 13 lenses and ordinary kriging for all remaining lenses and buffers using hard boundaries.
  8. Density values were assigned by lens group. Densities of 2.9, 3.7, 3.1, 3.0, 3.0 and 3.1 g/cm3 were assigned to groups A, B, C, E, F and G, respectively. A value of 2.8 g/cm3 was assigned to the Corridor North buffer, 2.9 g/cm3 to the Westwood buffer and 2.9 g/cm3 to the Zone 2 Extension buffer.
  9. The mineral resource estimate is classified as Measured, Indicated, and Inferred. The Inferred Mineral Resource category is defined with a minimum of two drill holes in areas where the drill spacing is <75 m, and reasonable geological and grade continuity have been demonstrated. The Indicated Mineral Resource category is defined with a minimum of two drill holes in areas where the drill spacing is <15 m, and reasonable geological and grade continuity have been demonstrated. Measured Mineral Resources were classified when Indicated Mineral Resources are present within 10 m of an underground opening within a mineralized zone. The initial resource classification was edited with a mix of automated and manual methods to eliminate isolated blocks of one confidence category, considering the spatial continuity of drill holes, and was run in each mineralized solid to upgrade inferred blocks, or downgrade indicated blocks locally, as needed. The measured resources from the original classification were checked and confirmed with the mining development data. The Measured Mineral Resources from the original classification were not smoothed to prevent downgrading the classification.
  10. The Mineral Resource estimate is locally constrained within Deswik Stope Optimizer shapes using a minimal mining width of 2.4 m for long hole stoping. It is reported at a cut-off grade of 5.7 g/t Au. The following parameters were used: mining cost = $200.16/t; processing cost = $24.65/t; G&A = $41.11/t; sustaining capital cost = $80.22/t; refining costs = $4.56/oz; gold price = US$1,800.00/oz; US$/C$ exchange rate = 1.25; and process recovery = 95.0%. The cut-off grades should be re-evaluated in light of future prevailing market conditions (metal prices, exchange rates, mining costs etc.).
  11. The number of metric tonnes was rounded to the nearest thousand, as required by Form 43-101F1, and any discrepancies in the totals are due to rounding effects. The metal contents are presented in troy ounces (tonnes x grade / 31.10348) rounded to the nearest hundred. Numbers may not add up due to rounding.
  12. The Qualified Person is not aware of any known environmental, permitting, legal, political, title-related, taxation, socio-political, or marketing issues that could materially affect the Mineral Resource estimate.
  1. 礦產資源估算的生效日期是2024年9月30日。
  2. 除了庫存外,估算的合格人員是來自Norda Stelo Inc.的馬丁·佩龍,P.Eng.;庫存估算的合格人員是IAMGOLD員工路易斯·恩科伊·曼達·姆邦巴先生,P.Eng.
  3. 礦產資源的報告包含礦產儲量。未轉化爲礦產儲量的礦產資源未能證明其經濟可行性。
  4. 該估計包括三個區域(北走廊、西伍德和2區延伸)中128個礦化透鏡,使用相鄰材料的品位(進行分析時)或未進行分析時的值爲零。創建了三個稀釋緩衝區(每個區域一個),以更好地反映約束形狀內的內部稀釋。
  5. 高品位的上限根據統計分析對原始分析數據進行了處理,該處理在每個區域基礎上進行,礦化區的範圍爲75-500克/噸黃金,稀釋緩衝區爲10-20克/噸黃金。計算了(1.0米)複合材質,使用了相鄰材料的品位(進行分析時)或未進行分析時的值爲零。
  6. 該估算是在Isatis.neo 2024.04中使用子塊模型完成的。母塊尺寸爲4 x 1 x 400萬(子塊爲1 x 0.5 x 1米)。
  7. 通過多個指標克里金法(kriging)獲得了13個透鏡的品位插值,其他透鏡和緩衝區則使用常規克里金法,並採用硬邊界。
  8. 密度值按透鏡組分配。A億組分配了2.9、3.7、3.1、3.0、3.0和3.1克/立方厘米的密度,走廊北緩衝區分配2.8克/立方厘米,西伍德緩衝區分配2.9克/立方厘米,2區延伸緩衝區分配2.9克/立方厘米。
  9. 礦產資源的估算分爲已測、指示和推斷。推斷礦產資源類別定義爲在鑽孔間距小於7500萬的區域內至少有兩個鑽孔,並且已證明合理的地質和品位連續性。指示礦產資源類別定義爲在鑽孔間距小於1500萬的區域內至少有兩個鑽孔,並且已證明合理的地質和品位連續性。已測礦產資源在指示礦產資源存在於礦化區內距離地下開口1000萬以內時進行分類。初始資源分類通過自動和手動方法的混合進行編輯,以消除孤立的單一置信度類別礦塊,考慮鑽孔的空間連續性,並在每個礦化體內進行運行,以提升推斷礦塊或在需要時本地降低指示礦塊。原始分類中的已測資源進行了覈查和確認,並與採礦開發數據進行了對比。原始分類中的已測礦產資源沒有進行平滑處理,以防止降低分類。
  10. The Mineral Resource estimate is locally constrained within Deswik Stope Optimizer shapes using a minimal mining width of 240萬 for long hole stoping. It is reported at a cut-off grade of 5.7 g/t Au. The following parameters were used: mining cost = $200.16/t; processing cost = $24.65/t; G&A = $41.11/t; sustaining capital cost = $80.22/t; refining costs = $4.56/oz; gold price = US$1,800.00/oz; US$/C$ exchange rate = 1.25; and process recovery = 95.0%. The cut-off grades should be re-evaluated in light of future prevailing market conditions (metal prices, exchange rates, mining costs etc.).
  11. The number of metric tonnes was rounded to the nearest thousand, as required by Form 43-101F1, and any discrepancies in the totals are due to rounding effects. The metal contents are presented in troy ounces (tonnes x grade / 31.10348) rounded to the nearest hundred. Numbers may not add up due to rounding.
  12. The Qualified Person is not aware of any known environmental, permitting, legal, political, title-related, taxation, socio-political, or marketing issues that could materially affect the Mineral Resource estimate.

Table 2 - Mineral Resource Statement, Grand Duc

Table 2 - Mineral Resource Statement, Grand Duc

Class Tonnes Gold Grade
(g/t Au)
Contained Ounces
Measured (stockpiles) 268,000 0.64 5,500
Indicated 2,740,000 1.31 115,600
Measured + Indicated 3,008,000 1.25 121,000
Inferred 80,000 1.28 3,300
類別 黃金等級
(每噸含金克數)
包含的盎司
測量(庫存) 268,000 0.64 5,500
指示資源 2,740,000 1.31 115,600
已知和指示資源總計 3,008,000 根據公司的固定費用覆蓋率,利率爲1.25% 至 1.75%每年,或者(b)有一個「備選主板利率」,並可減少至0.75%每年,取決於公司的固定費用覆蓋率。截至2021年7月3日,公司的基於LIBOR的利率爲% (對於$),公司的主板基準利率爲% (對於$)。根據未取出的貸款利率,每月應支付承諾費,利率爲%每年。根據與摩根大通銀行(「貸款協議」)的信貸協議的條款,現金收據將被存入鎖匣中,並由公司自行決定,除非處於「現金控制期」,在此期間,現金收據將用於減少貸款協議下的應付金額。現金控制期在事件違約或可用餘額連續三個工作日低於$時觸發,並將繼續到先前的連續天數中存在任何違約事件且多餘的可用餘額始終大於$(這樣的觸發器根據公司的循環承諾進行調整)。此外,如果依據信貸協議所定義的「額外可用餘額」小於$,則公司應維持最低固定費用覆蓋率爲1.0至1.0 (觸發器根據公司的循環承諾進行調整)。截至2021年7月3日,公司的可用餘額爲$25,764。信貸協議要求我們在判斷任何應支付股息或進行任何普通股分配時獲得摩根大通銀行的事先書面同意。信貸設施於2022年12月16日到期。 121,000
詳見2024年4月3日新聞稿 80,000 1.28 3,300

Notes:

注:

  1. Mineral Resources are reported at an effective date of 30 September, 2024. The Qualified Person for the estimate is Mr. Abderrazak Ladidi, P.Geo. an IAMGOLD employee.
  2. Measured Mineral Resources are reported in place as stockpiles. Indicated and Inferred Mineral Resources are in situ.
  3. Mineral Resources are reported inclusive of Mineral Reserves. Mineral Resources that are not converted to Mineral Reserves have not demonstrated economic viability
  4. Mineral Resources are reported using the 2014 CIM Definition Standards.
  5. Mineral Resources are reported assuming a gold price of US$1,800 and a US$:C$ exchange rate of 1.25. Mineral Resources are constrained within an optimized open pit shell, which use input assumptions including: mining costs of $12.71/t mineralization and variable waste costs ranging from $4.07-$5.71, process costs of $19.29/t and metallurgical recoveries that average 92%. Mineral Resources that are not in stockpiles are reported at a cut-off of 0.54 g/t Au. Mineral Resources in stockpiles have variable cut-offs, depending on the stockpile, which range from 0.54-0.9 g/t Au.
  6. The number of metric tonnes was rounded to the nearest thousand and any discrepancies in the totals are due to rounding effects. The metal contents are presented in troy ounces (tonnes x grade / 31.10348) rounded to the nearest hundred. Numbers may not add up due to rounding.
  1. 礦產資源報告的有效日期爲2024年9月30日。合格評估師爲iamgold員工Abderrazak Ladidi先生P.Geo。
  2. 測量礦產資源報告爲庫存狀態。 指示礦產資源和推測礦產資源爲原位。
  3. 礦產資源報告包括礦石儲量。尚未轉化爲礦石儲量的礦產資源未能證明經濟可行性。
  4. 礦產資源根據2014年CIM定義標準進行報告。
  5. 礦產資源的報告假定黃金價格爲1800美元,美元對加元的匯率爲1.25。礦產資源受到優化開放坑殼的限制,使用的輸入假設包括:礦石開採成本爲每噸12.71美元,廢料成本在4.07到5.71美元之間,工藝成本爲每噸19.29美元,冶金回收率平均爲92%。未在庫存中的礦產資源的截止點爲0.54克/噸黃金。庫存中的礦產資源有可變的截止點,具體取決於庫存,範圍爲0.54-0.9克/噸黃金。
  6. 公噸數四捨五入至最近千位,任何總數不一致均爲四捨五入效應。金屬含量以特洛伊盎司表示(噸 x 品位 / 31.10348),四捨五入至最近百位。由於四捨五入,數字可能無法相加。

Mineral Reserves

礦產儲量

Table 3 - Mineral Reserves Statement, Westwood

表3 - 涉礦概念儲量聲明,Westwood

Confidence Category Tonnage Gold Grade
(g/t Au)
Contained
Ounces
Proven 721,000 12.60 292,000
Probable 1,870,000 11.02 662,200
Stockpiles (Proven) 4,000 8.64 1,200
Total Proven + Probable 2,595,000 11.45 955,400
置信類別 礦石噸數 黃金等級
(每噸含金克數)
包含
盎司
已探明 721,000 12.60 292,000
很可能 1,870,000 11.02 662,200
存量(已證實) 4,000 8.64 1,200
總已證實 + 可能 2,595,000 11.45 955,400

Notes:

注:

  1. Mineral Reserves are reported at the point of delivery to the process plant with an effective date of 30 September, 2024. The Qualified Person for the estimate is Mr. Louis Nkoy Manda Mbomba, P.Eng., an IAMGOLD employee.
  2. Mineral Reserves are reported using the 2014 CIM Definition Standards.
  3. Mineral Reserves are reported using a gold price of US$1,500/oz Au and assume a C$:US$ exchange rate of 1.25. Mineral Reserves are constrained within mineable shapes, that use input assumptions including long-hole open stope mining methods, mining costs of $200.16/t, process costs of $24.65/t, general and administrative costs of $41.11/t, Sustaining capital cost of $80.22/t, gold treatment and refining costs of $4.56/t, minimum mining width of 2.4 m, dilution assumption of 63% at 0.5 g/t Au, mining recovery of 85%, and metallurgical recoveries averaging 95%. Mineral Reserves are reported at a 6.82 g/t Au cut-off, which is inclusive of a 10% mine call factor.
  4. Table numbers have been rounded. Totals may not sum due to rounding
  1. 礦藏儲備在送達處理廠時報告,有效日期爲2024年9月30日。估算的合格人員爲IAMGOLD員工路易斯·恩科伊·滿達·姆博姆巴(Louis Nkoy Manda Mbomba),工程師。
  2. 礦藏儲備使用2014年CIm定義標準進行報告。
  3. 礦藏儲備使用1500美元/盎司黃金的價格進行報告,並假設C$:US$匯率爲1.25。礦藏儲備被限制在可開採的形狀內,使用的輸入假設包括長孔開放法採礦方法,採礦成本爲200.16美元/噸,處理成本爲24.65美元/噸,管理和行政成本爲41.11美元/噸,持續資本成本爲80.22美元/噸,黃金處理和精煉成本爲4.56美元/噸,最小採礦寬度爲240萬,稀釋假設爲63%在0.5克/噸Au,採礦回收率爲85%,冶金回收率平均爲95%。礦藏儲備的報告在6.82克/噸Au的邊際回收水平,包含10%的礦山調用因子。
  4. 表格數字已四捨五入。由於四捨五入,合計可能不相加。

Table 4 - Mineral Reserves Statement, Grand Duc

表4 - 礦藏儲備聲明,Grand Duc

Confidence Category Tonnage Gold Grade
(g/t Au)
Contained
Ounces
Proven - - -
Probable 1,445,000 1.09 50,900
Stockpiles (Proven) 268,000 0.64 5,500
Total Proven + Probable 1,713,000 1.02 56,300
信心類別 礦石噸數 金品位
(每噸含金克數)
包含
盎司
已探明 - - -
很可能 1,445,000 1.09 50,900
儲備量(已探明) 268,000 0.64 5,500
總已探明+可能儲量 1,713,000 1.02 56,300

Notes:

注:

  1. Mineral Reserves are reported at the point of delivery to the process plant with an effective date of 30 September, 2024. The Qualified Person for the estimate is Mr. Louis Nkoy Manda Mbomba, P.Eng., an IAMGOLD employee.
  2. Mineral Reserves are reported using the 2014 CIM Definition Standards.
  3. Mineral Reserves are reported using a gold price of US$1,800/oz Au and assume a US$:C$ exchange rate of 1.25. Mineral Reserves are constrained within an optimized open pit shell, which use input assumptions including: mining costs of $12.71/t of ore and variable waste costs ranging from $4.07-5.71/t, process costs of $19.29/t, 10% dilution, bench face angles that range from 70o (north)-75o(south), and metallurgical recoveries that average 92%. Mineral Reserves are reported at a cut-off of 0.54 g/t Au.
  4. Table numbers have been rounded. Totals may not sum due to rounding.
  1. 礦藏儲量在交付至工藝廠時報告,生效日期爲2024年9月30日。估算的合格人士是iamgold的員工路易斯·恩科伊·曼達·姆博姆巴(Louis Nkoy Manda Mbomba),工程師。
  2. 礦藏儲量根據2014年CIM定義標準報告。
  3. 礦藏儲量使用了1800美元/盎司的黃金價格,並假設美金兌加元匯率爲1.25。礦藏儲量侷限於優化的露天礦殼內,輸入假設包括:礦山成本爲每噸礦石12.71美元和變化的廢石成本範圍爲每噸4.07-5.71美元,工藝成本爲每噸19.29美元,稀釋率爲10%,臺階面角度範圍爲70度(北)至75度(南),金屬回收率平均爲92%。礦藏儲量按0.54克/噸的截止值報告。
  4. 表格數字已四捨五入。由於四捨五入,合計可能無法相加。

Table 5 - Westwood MRMR Comparison Summary1

表5 - Westwood MRMR 比較摘要1


Updated Technical Report2,3 Dec. 31, 2023 MRMR Estimates2,4


(as of Sep 30, 2024)


Tonnage Grade Ounces Tonnage Grade Ounces Au

(000 t) (g/t Au) (000 oz) (000 t) (g/t Au) (000 oz) (000 oz) %
Westwood







Proven 721,000 12.60 292,000 382,000 10.40 128,000 +164,000 +128%
Probable 1,870,000 11.02 662,200 2,982,000 10.65 1,021,000 -358,800 -35%
Stockpiles (proven) 4,000 8.64 1,200 - - - +1,200
Subtotal 2,595,000 11.45 955,400 3,364,000 10.62 1,149,000 -193,600 -17%
Grand Duc







Proven - - - - - - -
Probable 1,445,000 1.09 50,900 1,460,000 1.17 55,000 -4,100 -7%
Stockpiles (proven) 268,000 0.64 5,500 465,000 0.69 10,000 -4,500 -45%
Subtotal 1,713,000 1.02 56,300 1,925,000 1.05 65,000 -8,700 -13%
Total Proven + Probable 4,308,000 7.30 1,011,700 5,289,000 7.14 1,214,000 -202,300 -17%
Westwood + Grand Duc







Measured (Stockpiles) 272,000 0.76 6,700 - - - +6,700
Measured 777,000 13.09 327,000 1,158,000 7.85 292,000 +35,000 +12%
Indicated 5,930,000 7.46 1,422,300 7,257,000 9.14 2,133,000 -710,700 -33%
Total Measured + Indicated 6,979,000 7.83 1,756,000 8,415,000 8.96 2,425,000 -669,000 -28%
Inferred 4,369,000 12.82 1,800,700 1,465,000 15.78 743,000 +1,057,700 +142%

更新的技術報告2,3 截至2023年12月31日 MRMR 估算2,4


(截至2024年9月30日)


噸位 級別 盎司 噸位 級別 盎司 黃金

(000 噸) (每噸含金克數) (000盎司) (000 噸) (每噸含金克數) (000盎司) (000盎司) %
西伍德







已探明 721,000 12.60 292,000 382,000 10.40 128,000 +164,000 +128%
很可能 1,870,000 11.02 662,200 2,982,000 10.65 1,021,000 -358,800 -35%
已探明庫存 4,000 8.64 1,200 - - - +1,200
小計 2,595,000 11.45 955,400 3,364,000 10.62 1,149,000 -193,600 -17%
大公







已探明 - - - - - - -
很可能 1,445,000 1.09 50,900 1,460,000 1.17 55000 -4,100 -7%
存貨(已證明) 268,000 0.64 5,500 465,000 0.69 10,000 -4,500 -45%
小計 1,713,000 1.02 56,300 1,925,000 1.05 65,000 -8,700 -13%
總可採儲量 + 可能儲量 4,308,000 7.30 1,011,700 5,289,000 7.14 1,214,000 -202,300 -17%
西伍德 + 大公爵







測量(庫存) 272,000 0.76 6,700 - - - +6,700
測量 777,000 13.09 327,000 1,158,000 7.85 292,000 +35,000 +12%
指示資源 5,930,000 7.46 1,422,300 7,257,000 9.14 2,133,000 -710,700 -33%
總計測量 + 指示 6,979,000 7.83 1,756,000 8,415,000 8.96 2,425,000 -669,000 -28%
詳見2024年4月3日新聞稿 4,369,000 12.82 1,800,700 1,465,000 15.78 743,000 +1,057,700 +142%
  1. Mineral Reserves and Mineral Resources on a 100% basis
  2. M&I Mineral Resources are inclusive of Mineral Reserves
  3. Mineral Resources as of September 30, 2024 are reported using a gold price of US$1,800/oz Au. Mineral Reserves for Westwood are reported using a gold price of $1,500/oz Au, and Mineral Reserves for Grand Duc are reported using a gold price of $1,800/oz. Mineral Resources and Reserves assume a US$:C$ exchange rate of 1.25.
  4. December 31, 2023 Mineral Resources were reported assuming a gold price of $1,600/oz for Westwood and $1,700/oz for Grand Duc. Mineral Reserves were reported assuming a gold price of US$1,300/oz for Westwood and $1,600/oz for Grand Duc.
  1. 礦藏儲備和礦產資源按100%計算
  2. M&I 涉礦概念包括礦產儲量
  3. 截至2024年9月30日的涉礦概念是以每盎司黃金1800美元的價格報告的。Westwood的礦產儲量是以每盎司1500美元的黃金價格報告的,而Grand Duc的礦產儲量是以每盎司1800美元的黃金價格報告的。涉礦概念和儲量假設匯率爲1.25。
  4. 截至2023年12月31日的涉礦概念假設Westwood的黃金價格爲每盎司1600美元,Grand Duc的黃金價格爲每盎司1700美元。礦產儲量假設Westwood的黃金價格爲每盎司1300美元,Grand Duc的黃金價格爲每盎司1600美元。

The decrease in Measured and Indicated Mineral Resources estimated for Westwood from the prior estimate is primarily due to tighter confidence criteria applied to the mine planning process. To reduce variations in mine planning, Indicated Mineral Resources were classified based on the completed definition drill pattern requirements. The changes to the Indicated Mineral Resources classification requirements were primarily responsible for the increase in Inferred Mineral Resources; the other key factor contributing to increases in Inferred Mineral Resources was identification of additional mineralization through exploration drilling.

Westwood的已測和指示涉礦概念估計的減少主要是由於在礦山規劃過程中應用了更嚴格的置信標準。爲了減少礦山規劃中的變化,指示的涉礦概念根據完成的定義鑽探模式要求進行了分類。指示的涉礦概念分類要求的變化主要導致推斷的涉礦概念的增加;另一個推動推斷的涉礦概念增加的關鍵因素是通過勘探鑽探識別到的額外礦化。

Life of Mine Plan

礦山生命週期計劃

Westwood - Mining

Westwood - 採礦

The mine life based on Mineral Reserves for the Westwood Complex is forecast from 2025-2032. The Westwood mine plan assumes long-hole open stoping methods and conventional underground equipment accessed via the Westwood shaft or the Warrenmac ramp. The mine is owner-operated. An extensive seismic risk analysis was performed in 2021 following significant seismic events in October 2020. In-depth geotechnical analyses were performed by mine staff and external consultants to identify risks associated with mining sequence, infrastructure location, and support requirements. These included evaluations of stress state and rock mass classifications as well as a review of the seismic history.

基於Westwood礦產儲量的礦山壽命預測爲2025-2032年。Westwood的礦山計劃假設採用長孔開放採礦方法和常規地下設備,通過Westwood井或Warrenmac臺階進入。礦山是由業主操作的。由於2020年10月發生的重大地震事件,在2021年進行了廣泛的地震風險分析。礦山工作人員和外部顧問進行深入的岩土工程分析,以識別與採礦順序、基礎設施位置和支撐要求相關的風險。包括對應力狀態和巖體分類的評估,以及地震歷史的審查。

Following the application of the different mitigation plans, the mine has experienced a decline in seismic events as shown in Figure ‎1 below. Key items to note from that figure include:

在不同的緩解計劃實施後,礦山經歷了地震事件的下降,如下圖‎1所示。該圖的關鍵要點包括:

  • The seismic activity rate appears to have been reduced by half, which represents a significant decrease;

  • This reduction is mainly attributed to changes in mining practices including:

    • - Mining sequencing

    • - The extraction rate

    • - Mine planning based on the seismic potential of different areas (implementation of the geo-seismic strategy)

  • 地震活動率似乎減少了一半,這代表着顯著的下降;

  • 這種減少主要歸因於採礦實踐的變化,包括:

    • - 採礦順序

    • - 提取率

    • - 基於不同區域地震潛力的礦山規劃(實施地質-地震策略)

Figure ‎1: Westwood Seismic Events History

圖1:Westwood地震事件歷史

Note: Figure prepared by IAMGOLD, 2024

注:圖由iamgold準備,2024年

The majority of the stopes will be mined in a bottom-up pillarless manner for better stress management. The transition from the primary-secondary method to a pillarless method is the result of a geotechnical study conducted after the major seismic event on October 30th, 2020, which recommended using a pillarless approach with a sequence designed, generally, to move stresses away from the mining front unidirectionally. The mining strategy is to mine the East, Central and Western sections of the mine simultaneously with as many as six mining areas mined concurrently to minimize production risk should one section be impacted by seismicity for a prolonged period of time. Consideration has been applied in the LOM to mitigate colliding mining fronts, as they create diminishing pillars that are detrimental to mine stability.

大多數採空區將採用自下而上的無柱方式進行採礦,以更好地管理壓力。由主要-次要方法轉變爲無柱方法是2020年10月30日重大地震事件後進行的地質技術研究的結果,該研究建議使用無柱方法,順序設計總體上是爲了將壓力單向地移離採礦前線。採礦策略是在東、中和西礦區同時進行採礦,最多可同時開採六個採礦區域,以 minim ize 生產風險,以防某個區域在長時間內受到地震影響。在LOm中考慮了減輕碰撞採礦前線的影響,因爲這些前線會造成減小的支柱,對礦山穩定性有害。

All underground material mined (ore + waste) must be hoisted to the surface, and the overall hoisting capacity depends on the loading pockets used. The LOM plan assumes a hoisting rate of 3,000 t/d. Once on surface, the ore is transported 2.5 km with 30 t haul trucks to the Doyon process plant.

所有開採的地下物料(礦石 + 廢石)必須提升到地面,整體提升能力取決於所用的裝載口。LOm計劃假設提升速率爲3000噸/天。一旦到達地面,礦石通過30萬億輛運輸卡車運輸2.5公里到達Doyon加工廠。

The Westwood deposit remains open at depth, westward and locally to the east along the untested mineralized Westwood, North and Zone-2 corridors.

Westwood礦牀在深度、西側和當地東側的未測試礦化的Westwood、North和Zone-2走廊仍然開放。

Grand Duc - Mining

Grand Duc - 礦業

Mining is carried out using a conventional drill, blast, load, and haul surface mining method with a contractor-operated fleet. Equipment is conventional for open pit operations.

礦業採用傳統的鑽探、爆破、裝載和運輸露天開採方法,由承包商操作的車隊進行。設備是開放式採礦作業的傳統設備。

The open pit is designed to reach a total depth of 110 m and will be about 309 m long. Benches are designed on 10 m heights in overburden and 20 m heights in fresh rock. Berm widths are 20 m in overburden and 10 m in fresh rock. Ramps and roadways are typically 20 m wide, reducing to single-lane, 12 m, widths at the base of the pit.

露天礦設計達到總深度11000萬,長度約爲30900萬。臺階設計爲在覆蓋層上高度1000萬,在新鮮岩石上高度2000萬。臺階寬度爲覆蓋層2000萬,新鮮岩石1000萬。坡道和道路通常寬2000萬,減少到礦坑底部的單車道寬度1200萬。

The Grand Duc operations share a portion of the infrastructure required for the mining operations with Westwood, including the Doyon process plant, waste rock storage facility, and tailings storage.

Grand Duc的運營與Westwood共享部分採礦作業所需的基礎設施,包括Doyon加工廠、廢石存儲設施和尾礦儲存。

The remaining mine life for Grand Duc is to 2025, with processing continuing into 2027. The LOM production is included in Table 6.

Grand Duc的剩餘礦山壽命至2025年,處理將持續到2027年。LOm產量包含在表6中。

The Grand Duc deposit remains open westward and locally to the east. The Company is evaluating the potential for a second phase extension of Grand Duc.

Grand Duc礦牀在西側和當地東側仍然開放。公司正在評估Grand Duc第二階段擴展的潛力。

Processing

處理

The Doyon plant treats ore via a conventional cyanidation process. Run-of-mine (ROM) ore is processed using a conventional single stage primary crusher followed by a two-stage semi-autogenous grinding (SAG) mill and ball mill grinding circuit, gravity circuit, pre-leach, carbon in leach (CIL) and carbon in pulp (CIP) circuits, in addition to associated gold recovery and carbon handling circuits to produce gold/silver doré.

Doyon工廠通過傳統的氰化處理礦石。原礦(ROM)礦石採用傳統的單級初級破碎機處理,隨後經過兩級自磨(SAG)磨和球磨研磨迴路、重力迴路、預浸、浸炭(CIL)和漿液浸炭(CIP)迴路,以及相關的黃金回收和炭處理迴路,以生產金/銀錠。

The process plant was originally constructed in the 1970s and last refurbished in 2013 to increase throughput to 1.0 Mt/a. Upgrades were made to the grinding, cyanidation, strip, and tailings cyanide destruction circuits. A new paste backfill plant was also built to meet the Westwood Complex operational needs.

該工廠最初建於1970年代,最後一次翻新是在2013年,以提高產量至每年1.0萬噸。對研磨、氰化、洗脫和尾礦氰化物破壞迴路進行了升級。還新建了一個漿體回填工廠,以滿足Westwood綜合體的運營需求。

The plant has been operated both continuously, and in batch mode, since 2013, depending on ore availability. Currently, operations are 24 hours a day, seven days a week, 52 weeks a year. However, there will be portions of the current mine plan which will see reduced ore availability, and the plan is to have the plant operate in batch mode. Depending on the period, this may result in operating a certain number of weeks in a month of operations or select days within a week of operations.

從2013年起,該工廠根據礦石可用性採取了持續運行和批次模式。目前,運營時間爲每天24小時,每週七天,每年52周。然而,當前礦區計劃的某些部分將會減少礦石供給,計劃是在批次模式下運行。根據時間段,這可能導致在每月的運營中運行若干周或在每週的運營中選擇某些天。

There have also been instances over the plant history where the process plant toll-treated custom material from other mining operations. This remains an option since the process flowsheet is flexible and can accommodate third-party custom materials outside the LOM plan.

在工廠歷史上,也曾有過工藝廠爲其他礦業運營提供定製物料的收費處理實例。由於工藝流程靈活,能夠容納不在LOm計劃中的第三方定製物料,這仍然是一個選項。

Closure and Reclamation Planning

關閉與復墾規劃

Closure plans must be submitted to the relevant regulator before commencement of activities. Closure plans must be revised every five years, however, in certain cases, the regulator can require more frequent revisions. A financial guarantee is required to cover reclamation and closure costs.

關閉計劃必須在活動開始前提交給相關監管機構。關閉計劃必須每五年修訂一次,但在某些情況下,監管機構可以要求更頻繁的修訂。需要提供財務擔保以覆蓋復墾和關閉成本。

The most recent closure plan update was submitted for Westwood and Doyon in 2021, with separate closure plans for each of Doyon and Westwood. The combined closure costs for Westwood, Doyon/Grand Duc and Fayolle, including contingency and ongoing Doyon care and maintenance costs, are estimated to be approximately $223.7 million. The 2021 Westwood closure plan was approved by the ministry in June 2024 and IAMGOLD has provided financial guarantees of $54.2 million to date in accordance with the government's payment schedule, increasing to $57.2 million by 2026. The Doyon/Grand Duc closure plan was approved by the ministry in July 2024 and IAMGOLD provided financial guarantees of $97.0 million to date in accordance with the government's payment schedule, increasing to $122.1 million by 2026. The Fayolle closure plan was approved by the ministry in 2022 and IAMGOLD provided financial guarantees of $2.3 in accordance with the government's payment schedule, increasing to $3.0 million by Dec. 19th, 2024. The final Fayolle closure plan is required no later then December 19, 2027.

最近一次的關閉計劃更新是在2021年爲Westwood和Doyon提交的,爲Doyon和Westwood分別制定了關閉計劃。Westwood,Doyon/Grand Duc和Fayolle的 combined 關閉成本,包括應急和持續的Doyon維護成本,預計約爲$22370萬。2021年Westwood關閉計劃於2024年6月獲得部委批准,IAMGOLD根據政府的支付計劃迄今已提供$5420萬的財務擔保,預計到2026年增加至$5720萬。Doyon/Grand Duc關閉計劃於2024年7月獲得部委批准,IAMGOLD根據政府的支付計劃迄今已提供$9700萬的財務擔保,預計到2026年增加至$12210萬。Fayolle關閉計劃於2022年獲得部委批准,IAMGOLD根據政府的支付計劃提供的財務擔保爲$2.3,預計到2024年12月19日增加至$300萬。Fayolle關閉計劃最終必須在2027年12月19日之前提交。

The next planned updates for Doyon and Westwood are July and June 2029, respectively. The Company is conducting studies to determine the ability to decrease the closure costs of the Westwood Complex through ongoing rehabilitation and analysis of remediation methods.

Doyon和Westwood的下一個計劃更新分別是2029年7月和6月。公司正在進行研究,以判斷通過持續的修復和修復方法分析來降低Westwood綜合體的關閉成本的能力。

Table 6 - Westwood Complex: Mine Plan Summary

表6 - Westwood綜合體:礦山計劃摘要


Units LOM Total or Average 2025 2026 2027 2028 2029 2030 2031 2032
MINING OPERATIONS









Westwood Underground (UG)









Ore mined 000 t 2,496 351 346 370 373 374 359 275 48
Grade mined g/t Au 11.55 11.04 13.25 11.86 10.60 11.29 10.20 12.68 13.62











Grand Duc Open Pit (OP)









Ore mined 000 t 1,129 1,129






Grade mined g/t Au 1.10 1.10






Waste mined 000 t 1,059 1,059






Total mined 000 t 2,189 2,189

















PROCESSING









Ore milled - UG 000 t 2,496 351 346 370 373 374 359 275 48
Ore milled - OP 000 t 1,544 724 742 79 - - - - -
Ore milled 000 t 4,040 1,075 1,088 449 373 374 359 275 48
Head grade - UG g/t Au 11.55 11.04 13.25 11.86 10.60 11.29 10.20 12.68 13.62
Head grade - OP g/t Au 0.98 1.35 0.66 0.66 - - - - -
Head grade g/t Au 7.51 4.52 4.66 9.90 10.60 11.29 10.20 12.68 13.62
Recovery % 95% 94% 95% 95% 95% 95% 95% 95% 95%
Gold production 000 oz 925 147 154 136 121 129 112 107 20











OPERATING COST









Mining cost - UG $M $631.0 $95.8 $85.1 $92.3 $93.0 $93.3 $90.3 $69.2 $12.0
Mining Cost - OP $M $15.4 $14.3 $0.9 $0.1




Mining cost1 $M $646.4 $110.1 $86.0 $92.4 $93.0 $93.3 $90.3 $69.2 $12.0
Process cost $M $155.0 $28.0 $29.0 $21.8 $19.8 $19.9 $19.2 $14.7 $2.5
G&A cost $M $167.8 $20.5 $20.7 $21.0 $21.0 $21.0 $21.2 $21.2 $21.2
Total $M $969.2 $158.7 $135.7 $135.2 $133.8 $134.2 $130.7 $105.2 $35.7
Unit Costs









Mining cost - UG $/t mined $252.78 $272.95 $245.70 $249.48 $249.48 $249.48 $251.41 $251.41 $251.41
Mining Cost - OP $/t mined $6.55 $6.55

















Mining Cost $/t processed $160.00 $102.49 $79.07 $206.01 $249.48 $249.48 $251.41 $251.41 $251.41
Process (incl. enviro) cost $/t processed $38.37 $26.09 $26.68 $48.56 $53.12 $53.12 $53.53 $53.53 $53.53
G&A cost $/t processed $41.54 $19.10 $19.03 $46.85 $56.40 $56.18 $58.97 $76.91 $445.54











CAPITAL EXPENDITURES









Sustaining capital expenditures $M $260.7 $74.3 $51.6 $52.6 $32.9 $28.3 $20.8 $0.0 $0.0
Non-sustaining capital expenditures $M $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
Total capital expenditures $M $260.7 $74.3 $51.6 $52.6 $32.9 $28.3 $20.8 $0.0 $0.0

Units LOm總計或平均 2025 2026 2027 2028 2029 2030 2031 2032
礦業經營









西伍德地下(UG)









開採的礦石 000 噸 2,496 351 346 370 373 374 359 275 48
開採的等級 克/噸黃金 11.55 11.04 13.25 11.86 10.60 11.29 10.20 12.68 13.62











大公爵露天礦 (OP)









礦石開採量 000 噸 1,129 1,129






開採的礦石等級 克/噸黃金 1.10 1.10






開採的廢石 000噸 1,059 1,059






總開採量 000噸 65,358 65,358

















加工









磨礦量 - 礦下 000 噸 2,496 351 346 370 373 374 359 275 48
礦石磨碎 - OP 000 噸 1,544 724 742 79 - - - - -
磨礦礦石 000 噸 4,040 1,075 1,088 449 373 374 359 275 48
頭部品位 - 地下 克/噸黃金 11.55 11.04 13.25 11.86 10.60 11.29 10.20 12.68 13.62
頭級品位 - OP 克/噸黃金 0.98 1.35 0.66 0.66 - - - - -
含金量 克/噸黃金 7.51 4.52 4.66 9.90 10.60 11.29 10.20 12.68 13.62
復甦 % 95% 94% 95% 95% 95% 95% 95% 95% 95%
黃金生產 000盎司 925 147 154 136 121 129 112 107 20











運營成本









挖掘成本 - 地下 $M $631.0 $95.8 $85.1 $92.3 $93.0 $93.3 $90.3 $69.2 $12.0
開採成本 - OP $M $15.4 $14.3 $0.9 0.1美元




採礦成本1 $M $646.4 $110.1 $86.0 $92.4 $93.0 $93.3 $90.3 $69.2 $12.0
加工成本 $M $155.0 $28.0 $29.0 $21.8美元 19.8美元 $19.9 $19.2 $14.7 $2.5
管理費用 $M $167.8 $20.5 $20.7美元 $21.0 $21.0 $21.0 $21.2 $21.2 $21.2
總計 $M $969.2 $158.7 $135.7 $135.2 $133.8 $134.2 $130.7 $105.2 $35.7
單位成本









採礦成本 - 地下 每噸開採 $252.78 $272.95 $245.70 $249.48 $249.48 $249.48 $251.41 $251.41 $251.41
開採成本 - 控件 每噸開採 $6.55 $6.55

















採礦成本 $/t 處理 $160.00 $102.49 $79.07 $206.01 $249.48 $249.48 $251.41 $251.41 $251.41
工藝(包括環保)成本 $/噸處理 $38.37 $26.09 $26.68 $48.56 $53.12 $53.12 $53.53 $53.53 $53.53
管理和行政成本 $/t 處理 $41.54 $19.10 $19.03 $46.85 $56.40 $56.18 $58.97 $76.91 $445.54











資本支出









可持續資本支出 $M $260.7 $74.3 $51.6 $52.6 32.9美元 $28.3 $20.8 $0.0 $0.0
非持續性資本支出 $M $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0 $0.0
總資本支出 $M $260.7 $74.3 $51.6 $52.6 32.9美元 $28.3 $20.8 $0.0 $0.0

Note: Numbers may not add up due to rounding

注意:數字可能因四捨五入而不相加

QUALIFIED PERSON AND TECHNICAL INFORMATION

合格人員和技術信息

Mineral Resources and Mineral Reserves are reported in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (May 2014; the 2014 CIM Definition Standards) and were prepared with reference to the CIM Estimation of Mineral Resources & Mineral Reserves Best Practice Guidelines (November, 2019; the 2019 CIM Estimation Guidelines).

礦產資源和礦產儲量的報告符合加拿大礦業、冶金和石油學會(CIM)關於礦產資源和礦產儲量的定義標準(2014年5月;2014年CIM定義標準),並參考了CIM礦產資源和礦產儲量最佳實踐指南(2019年11月;2019年CIM估算指南)進行編制。

The following serve as the qualified persons (QPs) for this news release as defined in National Instrument 43-101, Standards of Disclosure for Mineral Projects, and in compliance with Form 43-101F1:

以下是本資訊稿中所定義的合格人員(QPs),符合國家文書43-101、礦業項目披露標準,以及符合表格43-101F1:

  • Mr. Bernard Haley, P.Eng., Mining Manager, IAMGOLD;

  • Mr. Abderrazak Ladidi, P.Geo., Principal Resource Geologist, IAMGOLD;

  • Mr. Martin Perron, P.Eng., Director Centre of Excellence Geology, Norda Stelo Inc.;

  • Mr. Louis Nkoy Manda Mbomba, P.Eng., Superintendent Mine Engineering, IAMGOLD;

  • Dr. Ali Jalbout; P.Eng., Principal - Geotechnical Specialist, ASA Geotech Inc.;

  • Mr. Steve Pelletier, P.Eng., Principal Director, Environment, IAMGOLD.

  • 伯納德·海利先生,工程師,礦業經理,iamgold;

  • 阿卜杜拉扎克·拉迪迪先生,地質學家,iamgold;

  • 馬丁·佩龍先生,工程師,諾達斯特洛公司地質卓越中心董事;

  • 路易斯·恩克伊·曼達·姆邦巴先生,工程師,iamgold公司礦山工程主管;

  • 阿里·賈爾布特博士,工程師,ASA Geotech Inc.董事 - 岩土專家;

  • 史蒂夫·佩爾蒂埃先生,工程師,iamgold公司環境董事。

Lisa Ragsdale, Director, Mining Geology, IAMGOLD Corporation is the QP for the purposes of NI 43-101 with respect to the mineralization being reported on and is responsible for the review and approval of all mineral resources estimates for IAMGOLD. Guy Bourque, Director, Mining, IAMGOLD Corporation is the QP for the purposes of NI 43-101 with respect to the mineralization being reported on and is responsible for the review and approval of all mineral reserves estimates for IAMGOLD. The technical information in this news release has been included with the consent and prior review of Ms. Ragsdale and Mr. Bourque, as applicable. The QPs have verified the data disclosed and data underlying the information or opinions contained in this news release.

伊麗莎·拉格斯代爾,iamgold公司採礦地質學董事,作爲NI 43-101報告中涉及的礦物化的QP,負責審查和批准iamgold的所有礦產資源估算。吉·布爾克,iamgold公司採礦董事,作爲NI 43-101報告中涉及的礦物化的QP,負責審查和批准iamgold的所有礦產儲量估算。此資訊發佈中的技術信息已獲得拉格斯代爾女士和布爾克先生的同意和事先審查,視情況而定。QP已驗證所披露的數據以及本資訊發佈中包含的信息或意見所依據的數據。

About IAMGOLD

關於iamgold

IAMGOLD is an intermediate gold producer and developer based in Canada with operating mines in North America and West Africa. The Company has commenced production at the large-scale, long life Côté Gold Mine in partnership with Sumitomo Metal Mining Co. Ltd., which is expected to be among the largest gold mines in Canada. In addition, the Company has an established portfolio of early stage and advanced exploration projects within high potential mining districts. IAMGOLD employs approximately 3,600 people and is committed to maintaining its culture of accountable mining through high standards of Environmental, Social and Governance practices, including its commitment to strive for the goal of Zero Harm, in every aspect of its business. IAMGOLD is listed on the New York Stock Exchange (NYSE: IAG) and the Toronto Stock Exchange (TSX: IMG).

IAMGOLD是一家總部位於加拿大的中間黃金生產商和開發商,在北美和西非地區擁有運營礦山。公司已與住友金屬採礦株式會社合作在大規模、長壽命的Côté黃金礦開始生產,預計該礦將成爲加拿大最大的金礦之一。此外,公司在潛力巨大的礦區擁有一系列早期階段和先進勘探項目。IAMGOLD擁有約3600名員工,並致力於通過高環境、社會和治理標準維持其負責任採礦文化,包括致力於在業務的各個方面努力實現零傷害目標。IAMGOLD在紐約證券交易所(NYSE:IAG)和多倫多證券交易所(TSX:IMG)上市。

IAMGOLD Contact Information

iamgold聯繫信息

Graeme Jennings, Vice President, Investor Relations
Tel: 416 360 4743 | Mobile: 416 388 6883
Toll-free: 1 888 464 9999
info@iamgold.com

投資者關係副總裁格雷姆·詹寧斯
電話:416 360 4743 | 手機:416 388 6883
免費電話:1 888 464 9999
info@iamgold.com

CAUTIONARY NOTE TO U.S. INVESTORS REGARDING DISCLOSURE OF MINERAL RESERVE AND MINERAL RESOURCE ESTIMATES

關於美國投資者披露礦藏儲量和礦產資源估算的警示說明

The mineral resource and reserve estimates contained in this news release have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") - CIM Definition Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended (the "CIM Standards"). These standards are similar to those found in subpart 1300 of Regulation S-K, used by the United States Securities and Exchange Commission (the "SEC"). However, the definitions in NI 43-101 and the CIM Standards differ in certain respects from those under subpart 1300 of Regulation S-K . Accordingly, mineral resource and reserve information contained in this news release may not be comparable to similar information disclosed by United States companies.

本新聞稿中包含的礦產資源和儲量估算按照NI 43-101和加拿大礦業、冶金和石油協會("CIM")的礦產資源和礦藏儲量定義標準編制,這些標準經過CIM理事會採納並修訂("CIM標準")。這些標準與美國證券交易委員會("SEC")所用的S-k規則1300部分中的標準類似。然而,NI 43-101和CIM標準中的定義在某些方面與S-k規則第1300部分下的定義有所不同。因此,本新聞稿中包含的礦產資源和儲量信息可能與美國公司披露的類似信息不可比擬。

As a result of the adoption of subpart 1300 of Regulation S-K (the "SEC Modernization Rules"), which more closely align its disclosure requirements and policies for mining properties with current industry and global regulatory practices and standards, including NI 43-101 and the CIM Standards, and which became effective on February 25, 2019, the SEC now recognizes estimates of "measured mineral resources", "indicated mineral resources" and "inferred mineral resources." In addition, the SEC has amended definitions of "proven mineral reserves" and "probable mineral reserves" in its amended rules, with definitions that are substantially similar to those used in NI 43-101 and the CIM Standards. Issuers must begin to comply with the SEC Modernization Rules in their first fiscal year beginning on or after January 1, 2022, though Canadian issuers that report in the United States using the Multijurisdictional Disclosure System ("MJDS") may still use NI 43-101 rather than the SEC Modernization Rules when using the SEC's MJDS registration statement and annual report forms.

由於S-k規則第1300部分("SEC現代化規則")的採用,該規則將其披露要求和政策與當前行業和全球監管實踐及標準,包括NI 43-101和CIM標準,更加緊密地對齊,該規則於2019年2月25日生效,SEC現在承認「已探明礦產資源」、「指示性礦產資源」和「推測性礦產資源」的估算。此外,SEC在其修訂規則中對「已探明礦藏儲量」和「可能礦藏儲量」的定義進行了修訂,其定義與NI 43-101和CIM標準中使用的定義基本相似。發行人必須在2022年1月1日或之後開始的第一個財政年度開始遵守SEC現代化規則,儘管在使用SEC的MJDS註冊聲明和年度報告表格時,用於在美國報告的加拿大發行人仍可使用NI 43-101,而不是SEC現代化規則。

United States investors are cautioned that while the SEC now recognizes "measured mineral resources", "indicated mineral resources" and "inferred mineral resources" under the SEC Modernization Rules, investors should not assume that any part or all of the mineral deposits in these categories will ever be converted into a higher category of mineral resources or into mineral reserves. These terms have a great amount of uncertainty as to their economic and legal feasibility. Under Canadian regulations, estimates of inferred mineral resources may not form the basis of feasibility or pre-feasibility studies, except in limited circumstances.

美國投資者應注意,儘管證券交易委員會(SEC)現在在現代化規則下承認「已測量的礦產資源」、「已指示的礦產資源」和「推測的礦產資源」,但投資者不應假設這些類別中的任何部分或全部礦產儲量將會轉化爲更高類別的礦產資源或礦產儲備。這些術語在其經濟和法律可行性方面具有很大的不確定性。根據加拿大法規,推測的礦產資源估計可能不會形成可行性或預可行性研究的基礎,除非在有限情況下。

Investors are cautioned not to assume that any "measured mineral resources", "indicated mineral resources", or "inferred mineral resources" that the Company reports in this news release are or will be economically or legally mineable. Further, "inferred mineral resources" have a great amount of uncertainty as to their existence and as to their economic and legal feasibility. It cannot be assumed that any part or all of an inferred mineral resource will ever be upgraded to a higher category.

投資者應注意,不要假設公司在本資訊發佈中報告的任何「已測量的礦產資源」、「已指示的礦產資源」或「推測的礦產資源」是或將會是經濟或法律上可開採的。此外,「推測的礦產資源」在其存在及經濟和法律可行性方面具有很大的不確定性。無法假設推測的礦產資源的任何部分或全部將會升級到更高類別。

The mineral reserve and mineral resource data set out in this news release are estimates, and no assurance can be given that the anticipated tonnages and grades will be achieved or that the indicated level of recovery will be realized.

本資訊發佈中列出的礦產儲備和礦產資源數據爲估計值,無法保證預期的噸位和品位將會實現或所指示的回收率將會實現。

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

關於前瞻性信息的警告聲明

All information included or incorporated by reference in this news release, including any information as to the Company's vision, strategy, future financial or operating performance and other statements that express management's expectations or estimates of future performance or impact, including statements in respect of the prospects and/or development of the Company's projects, other than statements of historical fact, constitutes forward-looking information or forward-looking statements within the meaning of applicable securities laws (collectively referred to herein as "forward-looking statements") and such forward-looking statements are based on expectations, estimates and projections as of the date of this news release. Forward-looking statements are generally identifiable by the use of words such as "may", "will", "should", "would", "could", "continue", "expect", "budget", "aim", "can", "focus", "forecast", "anticipate", "estimate", "believe", "intend", "plan", "schedule", "guidance", "outlook", "potential", "seek", "targets", "cover", "strategy", "during", "ongoing", "subject to", "future", "objectives", "opportunities", "committed", "prospective", "preliminary", "likely", "progress", "strive", "sustain", "effort", "extend", "on track", "remain", "pursue", "predict", or "project" or the negative of these words or other variations on these words or comparable terminology.

本新聞稿中包含的所有信息或通過引用納入的內容,包括公司願景、戰略、未來財務或營運業績以及表達管理層預期或對未來績效或影響的估計的其他描述,包括有關公司項目前景和/或發展的聲明,除歷史事實陳述外,均構成前瞻性信息或前瞻性聲明,根據適用證券法的含義(以下統稱「前瞻性聲明」)。這些前瞻性聲明基於本新聞稿日期的預期、估計和投影。前瞻性聲明通常可通過使用諸如「可能」、「將」、「應該」、「將會」、「可以」、「持續」、「期望」、「預算」、「旨在」、「能夠」、「專注」、「預測」、「預期」、「估計」、「相信」、「打算」、「計劃」、「安排」、「指導」、「展望」、「潛力」、「尋求」、「目標」、「涵蓋」、「策略」、「在」、「進行中」、「受」、「未來」、「目標」、「機會」、「承諾」、「有望的」、「初步」、「可能」、「進展」、「努力」、「維持」、「堅持」、「預測」、「預計」等詞語來識別,或這些詞的否定形式,以及這些詞的其他變體或類似的術語。

For example, forward-looking statements include, but are not limited to, statements with respect to: the estimation of mineral reserves and mineral resources and the realization of such estimates; operational and financial performance including the Company's guidance for and actual results of production, ESG (including environmental) performance, costs and capital and other expenditures such as exploration and including depreciation expense and effective tax rate; the updated life-of-mine plan, ramp-up assumptions and other project metrics including operating costs in respect to the Côté Gold Mine; expected production of the Côté Gold Mine, expected benefits from the operational improvements and de-risking strategies implemented or to be implemented by the Company; mine development activities; the Company's capital allocation and liquidity; the announced intention to repurchase the Transferred Interests in the Côté Gold Mine, the composition of the Company's portfolio of assets including its operating mines, development and exploration projects; the completion of the sale of the Bambouk Assets; permitting timelines and the expected receipt of permits; inflation, including global inflation and inflationary pressures; global supply chain constraints; environmental verification, biodiversity and social development projects; plans, targets, proposals and strategies with respect to sustainability, including third party data on which the Company relies, and their implementation; commitments with respect to sustainability and the impact thereof, including the Company's "Zero Harm" vision; commitments with respect to greenhouse gas emissions and decarbonization initiatives (eg. interim target of achieving 30% absolute reduction in Scope 1 and 2 emissions by 2030); the development of the Company's Water Management Standard; commitments with respect to biodiversity; commitments related to social performance, including commitments in furtherance of Indigenous relations; the ability to secure alternative sources of consumables of comparable quality and on reasonable terms; workforce and contractor availability, labour costs and other labour impacts; the impacts of weather; the future price of gold and other commodities; foreign exchange rates and currency fluctuations; financial instruments; hedging strategies; impairment assessments and assets carrying values estimates; safety and security concerns in the jurisdictions in which the Company operates and the impact thereof on the Company's operational and financial performance and financial condition; and government regulation of mining operations (including the Competition Act and the regulations associated with the fight against climate change).

例如,前瞻性聲明包括但不限於有關以下事項的聲明:礦產儲量和礦產資源的估計以及對此類估計的實現;運營和財務表現,包括公司對生產、ESG(包括環境)表現、成本和資本以及其他支出(如勘探支出、折舊費用和有效稅率)的指導及實際結果;更新後的礦生命週期計劃、Côté黃金礦的開採假設和其他項目指標,包括與Côté黃金礦有關的運營成本;Côté黃金礦的預期產量,從公司實施或擬實施的運營改進和降低風險策略中預期的益處;礦山開發活動;公司的資本配置和流動性;宣佈意圖回購Côté黃金礦的轉讓權益,包括公司資產組合的組成,包括其運營礦山、開發和勘探項目;完成對Bambouk資產的出售;許可時間表和預期獲證情況;通貨膨脹,包括全球通貨膨脹和通貨膨脹壓力;全球供應鏈限制;環境驗證、生物多樣性和社會發展項目;關於可持續性的計劃、目標、提議和策略,包括公司依賴的第三方數據及其實施;關於可持續性的承諾及其影響,包括公司的「無傷害」願景;關於溫室氣體排放和脫碳倡議(例如,2030年前實現減少30% Scope 1和2排放的中期目標)的承諾;公司水管理標準的制定;與生物多樣性有關的承諾;與社會績效相關的承諾,包括促進與土著民族關係的承諾;確保替代可比質量的消耗品且價格合理的能力;勞動力和承包商的可用性、勞動力成本和其他勞動力影響;天氣影響;黃金和其他大宗商品的未來價格;外匯率和貨幣波動;金融工具;套期保值策略;減值評估和資產賬面價值估計;公司運營所在司法管轄區的安全和安全擔憂及其對公司運營和財務表現以及財務狀況的影響;以及對採礦業運營的政府監管(包括競爭法和與應對氣候變化有關的法規)。

The Company cautions the reader that forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by management, are inherently subject to significant business, financial, operational and other risks, uncertainties, contingencies and other factors, including those described below, which could cause actual results, performance or achievements of the Company to be materially different from results, performance or achievements expressed or implied by such forward-looking statements and, as such, undue reliance must not be placed on them. Forward-looking statements are also based on numerous material factors and assumptions, including as described in this news release, including with respect to: the Company's present and future business strategies; operations performance within expected ranges; anticipated future production and cash flows; local and global economic conditions and the environment in which the Company will operate in the future; the price of precious metals, other minerals and key commodities; projected mineral grades; international exchanges rates; anticipated capital and operating costs; the availability and timing of required governmental and other approvals for the construction of the Company's projects.

公司提醒讀者,前瞻性聲明必然基於一系列估計和假設,儘管管理層認爲這些是合理的,但本質上受到重大商業、財務、運營和其他風險、不確定性、不確定因素以及其他因素的影響,包括下文描述的那些,這些因素可能導致公司的實際業績或成果與前瞻性聲明所表達或暗示的成果、業績或成就存在實質性差異,因此不應過度依賴這些聲明。前瞻性聲明還基於許多重要因素和假設,包括本新聞發佈中所述的,包括與公司現在和未來的業務策略有關的; 在預期範圍內的運營業績; 預期未來的生產和現金流; 本公司將來在環境等地區的本地和全球經濟狀況環境; 貴金屬、其他礦物和主要大宗商品的價格; 預測的礦石品位; 國際匯率; 預期的資本和運營成本; 施工項目所需政府和其他批准的可用性和時間等。

Risks, uncertainties, contingencies and other factors that could cause actual results, performance or achievements of the Company to be materially different from results, performance or achievements expressed or implied by such forward-looking statements include, without limitation: the ability of the Company to complete the repurchase of the Transferred Interest in the Côté Gold Mine; the ability of the Company to complete the sales of the remaining Bambouk Assets; the Company's business strategies and its ability to execute thereon; the ability of the Company to complete pending transactions; the development and execution of implementing strategies to meet the Company's sustainability vision and targets; security risks, including civil unrest, war or terrorism and disruptions to the Company's supply chain and transit routes as a result of such security risks, particularly in Burkina Faso and the Sahel region surrounding the Company's Essakane mine; the availability of labour and qualified contractors; the availability of key inputs for the Company's operations and disruptions in global supply chains; the volatility of the Company's securities; litigation; contests over title to properties, particularly title to undeveloped properties; mine closure and rehabilitation risks; management of certain of the Company's assets by other companies or joint venture partners; the lack of availability of insurance covering all of the risks associated with a mining company's operations; unexpected geological conditions; competition and consolidation in the mining sector; the profitability of the Company being highly dependent on the condition and results of the mining industry as a whole, and the gold mining industry in particular; changes in the global prices for gold, and commodities used in the operation of the Company's business (included, but not limited to diesel, fuel oil and electricity); legal, litigation, legislative, political or economic risks and new developments in the jurisdictions in which the Company carries on business; changes in taxes, including mining tax regimes; the failure to obtain in a timely manner from authorities key permits, authorizations or approvals necessary for transactions, exploration, development or operation, operating or technical difficulties in connection with mining or development activities, including geotechnical difficulties and major equipment failure; the inability of the Company to participate in any gold price increase above the cap in any collar transaction entered into in conjunction with certain gold sale prepayment arrangements; the availability of capital; the level of liquidity and capital resources; access to capital markets and financing; the Company's level of indebtedness; the Company's ability to satisfy covenants under its credit facilities; changes in interest rates; adverse changes in the Company's credit rating; the Company's choices in capital allocation; effectiveness of the Company's ongoing cost containment efforts; the Company's ability to execute on de-risking activities and measures to improve operations; availability of specific assets to meet contractual obligations; risks related to third-party contractors, including reduced control over aspects of the Company's operations and/or the failure and/or the effectiveness of contractors to perform; risks arising from holding derivative instruments; changes in U.S. dollar and other currency exchange rates or gold lease rates; capital and currency controls in foreign jurisdictions; assessment of carrying values for the Company's assets, including the ongoing potential for material impairment and/or write-downs of such assets; the speculative nature of exploration and development, including the risks of diminishing quantities or grades of reserves; the fact that reserves and resources, expected metallurgical recoveries, capital and operating costs are estimates which may require revision; the presence of unfavourable content in ore deposits, including clay and coarse gold; inaccuracies in life of mine plans; failure to meet operational targets; , including but not limited to the ability of the Company to achieve ninety percent (90%) throughput at the Côté Gold Mine by year-end and the ability of the Company to achieve nameplate capacity at the Côté Gold Mine in 2025; equipment malfunctions; information systems security threats and cybersecurity; laws and regulations governing the protection of the environment (including greenhouse gas emission reduction and other decarbonization requirements and the uncertainty surrounding the interpretation of omnibus Bill C-59 and the related amendments to the Competition Act (Canada)); employee relations and labour disputes; the maintenance of tailings storage facilities and the potential for a major spill or failure of the tailings facilities due to uncontrollable events, lack of reliable infrastructure, including access to roads, bridges, power sources and water supplies; physical and regulatory risks related to climate change; unpredictable weather patterns and challenging weather conditions at mine sites; disruptions from weather related events resulting in limited or no productivity such as forest fires, flooding, heavy snowfall, poor air quality, and extreme heat or cold; attraction and retention of key employees and other qualified personnel; availability and increasing costs associated with mining inputs and labour, negotiations with respect to new, reasonable collective labour agreements and/or collective bargaining agreements may not be agreed to; the ability of contractors to timely complete projects on acceptable terms; the relationship with the communities surrounding the Company's operations and projects; indigenous rights or claims; illegal mining; the potential direct or indirect operational impacts resulting from external factors, including infectious diseases, pandemics, or other public health emergencies; and the inherent risks involved in the exploration, development and mining business generally. Please see the Company's AIF or Form 40-F available on or www.sec.gov/edgar for a comprehensive discussion of the risks faced by the Company and which may cause actual results, performance or achievements of the Company to be materially different from results, performance or achievements expressed or implied by forward-looking statements.

可能使公司的實際結果、績效或成就與前瞻性聲明中表達或暗示的結果、績效或成就存在重大差異的風險、不確定性、事態及其他因素包括但不限於:公司完成轉讓到科特黃金礦的權益回購的能力;公司完成剩餘Bambouk資產的銷售的能力;公司的業務策略及其執行能力;公司完成待定交易的能力;執行實現戰略以滿足公司的可持續願景和目標;安全風險,包括內亂、戰爭或恐怖主義以及由此導致的打亂公司供應鏈和運輸路線的風險,特別是在布基納法索和莎赫爾地區,圍繞着公司Essakane礦的地區;勞動力和合格承包商的供應;公司運營所需的關鍵輸入物資的供應和全球供應鏈中斷;公司證券的波動性;訴訟;產權爭議,特別是未開發財產的產權; 礦井關閉和恢復風險;其他公司或合資夥伴管理公司某些資產;保險中缺乏覆蓋礦業公司運營風險的所有風險的保險的可用性;意外地質條件;礦業板塊中的競爭和整合;公司的盈利高度依賴整個礦業行業以及黃金礦業的情況和結果;黃金和公司業務運營所用的大宗商品全球價格的變化(包括但不限於柴油、燃料油和電力);法律、訴訟、立法、政治或經濟風險以及公司經營業務的管轄地的新發展;稅收變化,包括礦業稅制的變化;未能及時從相關部門獲得關鍵許可、授權或批准,該許可、授權或批准對於交易、勘探、開發或運營、與礦山或開發活動相關的操作或技術困難,包括地質技術困難和主要設備故障;公司無法參與與某些黃金預售安排相結合的任何護領鎖定交易中的價格上漲上限以上的黃金價格;資本的可用性;流動性水平和資本資源;資本市場和融資獲取途徑;公司的負債水平;公司履行信貸安排下的契約的能力;利率變動;公司信用評級不利變化;公司資本配置選擇;公司正在進行的成本控制努力的有效性;公司展開降低風險活動和提高運營措施的能力;特定資產的可用性以滿足合同義務的風險;與第三方承包商有關的風險,包括公司運營某些方面減少控制和/或承包商未能以適當方式執行的風險和/或有效性;由於控制無效的風險;美元和其他貨幣匯率或黃金租金率的變化;外國司法管轄區的資本和貨幣控制;對公司資產的賬面價值評估;不斷可能出現重大資產減值和/或減記的潛在性;勘探和開發的投機性質,包括儲量或品位減少的風險;儲備和資源、預期冶金回收率、資本和營運成本只是估計值,這可能需要修訂;礦石蘊含負面成分,包括粘土和粗金;生命週期計劃的不準確性;不能實現運營目標; 包括但不限於公司能否在年底實現科黃金礦90%的吞吐量以及公司能否在2025年實現科黃金礦的骨幹產能的能力;設備故障;信息系統安全威脅和網絡安全;法律和規定管理環境保護(包括溫室氣體減排和其他脫碳要求以及關於特許法案C-59和相關對競爭法(加拿大)修改的解釋的不確定性);僱員關係和勞資糾紛;尾礦儲存設施的維護和由於無法控制事件而可能導致尾礦設施的重大溢出或失效風險,缺乏可靠的基礎設施,包括道路、橋樑、電源和供水;與氣候變化相關的物理和監管風險;不可預測的天氣模式和礦山現場惡劣天氣條件;由於天氣相關事件造成的干擾導致生產能力有限或沒有生產,如森林火災、洪水、大雪、空氣質量差、極端炎熱或嚴寒;吸引和留住關鍵員工和其他合格人員的能力;與礦業投入和勞動力相關的成本上升和不斷增加成本的可用性和談判;關於新的、合理的集體勞資協議和/或集體談判協議可能無法達成協議;承包商能否及時按可接受條款完成項目;與圍繞公司的運營和項目的社區的關係;土著權利或主張;非法採礦;由外部因素,包括傳染病、大流行病或其他公共衛生緊急情況導致的潛在直接或間接運營衝擊的可能性;以及勘探、開發和礦產業務普遍涉及的固有風險。請參閱公司的AIF或40-F表,可在或www.sec.gov/edgar上獲取,了解公司面臨的風險的全面討論,這些風險可能導致公司的實際結果、績效或成就與前瞻性聲明中表達或暗示的結果、績效或成就存在重大差異。

Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise except as required by applicable law.

儘管公司已經試圖確定可能導致實際結果與前瞻性聲明中包含的結果大相徑庭的重要因素,但可能存在其他因素導致結果未如預期、估計或預期。公司聲明不承擔更新或修訂任何前瞻性聲明的意向或義務,除非根據適用法律的要求。

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論