TeraWulf Announces November 2024 Production and Operations Update
TeraWulf Announces November 2024 Production and Operations Update
Completed critical electrical upgrades to support Lake Mariner HPC hosting and mining buildings
完成了關鍵電氣升級以支持湖馬里納HPC託管和挖礦建築
Remain on schedule to deliver 72.5 MW of HPC hosting capacity by the end of Q2 2025
按計劃在2025年第二季度末交付72.5 MW的HPC託管能力
Successfully installed approximately 7,400 state-of-the-art S21 Pro miners
成功安裝了約7400台最先進的S21 Pro礦機
Achieved 8.4 EH/s of operational self-mining capacity, a 68% year-over-year increase
實現了8.4 EH/s的運營自挖能力,同比增長68%
EASTON, Md., Dec. 03, 2024 (GLOBE NEWSWIRE) -- TeraWulf Inc. (Nasdaq: WULF) ("TeraWulf" or the "Company"), a leading owner and operator of vertically integrated, next-generation digital infrastructure powered by predominantly zero-carbon energy, today provided its unaudited monthly production and operations update for November 2024.
2024年12月3日,馬里蘭州伊斯頓,世界環球新聞社報道--TeraWulf Inc.(納斯達克股票代碼:WULF)("TeraWulf"或"公司"),一家主要依靠零碳能源驅動的垂直一體化、下一代數字基礎設施的領先業主和運營商,今天提供了其2024年11月份未經審計的生產和運營更新。
November 2024 Production and Operations Highlights
2024年11月生產和運營亮點
-
Bitcoin Production: Self-mined 115 bitcoin, with an average daily production rate of approximately 3.8 bitcoin.
-
Operating Capacity: Maintained 8.4 EH/s of operational self-mining capacity, a 68.0% year-over-year increase.
-
Power Costs: Achieved an average power cost of $41,190 per bitcoin mined, equivalent to approximately $0.051/kWh, excluding proceeds from demand response and ancillary services.
-
Miner Upgrades: Advanced the miner refresh program at Lake Mariner, replacing legacy S19 Pro/J-Pro and M30s+ models with approximately 7,400 S21 Pro miners.
-
Electrical Upgrades: Completed a planned outage to connect high-voltage redundant power feeds, temporarily affecting approximately 5.3 EH/s of miners.
- 比特幣生產:自挖115個比特幣,平均每日生產率約爲3.8個比特幣。
- 運營容量:保持8.4 EH/s的自挖運作能力,同比增長68.0%。
- 電力成本:每個比特幣礦產的平均電力成本爲41,190美元,相當於約0.051美元/kWh,不包括需求響應和輔助服務的收益。
- 礦工升級:推進Lake Mariner的礦工更新計劃,使用約7,400個S21 Pro礦工替代舊款S19 Pro/J-Pro和M30s+型號。
- 電氣升級:完成了計劃中的停電,以連接高壓冗餘電源,暫時影響約5.3 EH/s的礦工。
Key Metrics1 |
November 2024 |
October 2024 |
||||
Bitcoin Self-Mined | 115 | 150 | ||||
Value per Bitcoin Self-Mined2 | $ | 83,947 | $ | 65,427 | ||
Power Cost per Bitcoin Self-Mined | $ | 41,190 | $ | 36,789 | ||
Avg. Operating Hash Rate (EH/s)3 | 5.9 | 6.8 | ||||
Nameplate Miner Efficiency (J/TH)4 | 19.2 | 22.0 |
關鍵指標1 | 2024年11月 |
2024年10月 |
||||
比特幣自挖 | 115 | 150 | ||||
每枚自我挖掘的比特幣價值2 | $ | 83,947 | $ | 65,427 | ||
每枚自我挖掘的比特幣的功率成本 | $ | 41,190 | $ | 36,789 | ||
平均運營算力(EH/s)3 | 5.9 | 6.8 | ||||
額定礦機效率(J/TH)4 | 19.2 | 22.0 |
_______________
1 All figures except Bitcoin Self-Mined are estimates and remain subject to standard month-end adjustments.
2 Computed as the weighted-average opening price of bitcoin on each respective day the Bitcoin Self-Mined is earned.
3 While nameplate mining inventory as of November 30, 2024 for Lake Mariner is estimated at 9.7 EH/s, actual monthly hash rate performance depends on a variety of factors, including (but not limited to) performance tuning to increase efficiency and maximize margin, scheduled outages (scopes to improve reliability or performance), unscheduled outages, curtailment due to participation in various cash generating demand response programs, derate of ASICS due to adverse weather and ASIC maintenance and repair. Performance in November was impacted by planned outage for electrical upgrades and miner fleet upgrade work. Performance in October was impacted by miner fleet upgrade work.
4 Nameplate miner efficiency excludes auxiliary load.
_______________
除比特幣自挖外的所有數字均爲估算值,並仍然需遵循標準的月末調整。
2、根據獲得的比特幣自我挖掘日期計算加權平均開盤價。
截至2024年11月30日,Lake Mariner的命名礦井庫存估計爲9.7 EH/s,但實際的每月哈希率表現取決於多種因素,包括(但不限於)爲了提高效率和最大化利潤而進行的性能調整、計劃停機(用於提高可靠性或性能的範圍)、非計劃停機、因參與各種現金產生的需求響應程序而造成的削減、由於不良天氣和ASIC的維護和修理而導致的性能下降。11月的表現受到電力升級和礦工設備升級工作的計劃停機影響。10月的表現則受到了礦工設備升級工作的影響。
4、額定礦工的效率不包括輔助負載。
Management Commentary
管理層評論
Sean Farrell, Chief Operating Officer of TeraWulf remarked, "November marked a pivotal month for Lake Mariner as we completed significant upgrades to our electrical infrastructure. These enhancements will ensure reliable and redundant power delivery to CB-1, CB-2, and future HPC hosting loads, positioning us to meet the increasing demand for Tier 3 HPC infrastructure."
TeraWulf首席運營官Sean Farrell表示:「11月對於湖泊馬里納來說是一個關鍵的月份,我們完成了電力基礎設施的重要升級。這些增強措施將確保對Cb-1、Cb-2以及未來HPC承載負載提供可靠和冗餘的電力,幫助我們滿足對Tier 3 HPC基礎設施日益增長的需求。」
Farrell added, "Despite a brief planned outage, we mined 115 bitcoin with an average daily production rate of nearly four bitcoin. Our miner refresh program has substantially improved efficiency, achieving a weighted average of approximately 19 J/TH. Additionally, our onsite repair teams are on track to restore 1.3 EH/s of mining equipment under warranty by year-end. Construction of MB-5 is proceeding on schedule, with conduit installation complete and foundation pours and structural steel assembly underway."
Farrell補充道:「儘管經歷了短暫的計劃停機,但我們挖掘了115個比特幣,平均每日生產率接近四個比特幣。我們的礦工更新計劃顯著提高了效率,達到了約19 J/TH的加權平均水平。此外,我們的現場維修團隊正按計劃在年底前恢復1.3 EH/s的保修挖礦設備。Mb-5的施工按計劃進行,管道安裝已完成,基礎澆築和結構鋼鐵組裝正在進行中。」
Production and Operations Update
生產和運營更新
TeraWulf's commitment to operational excellence and sustainability continues to drive its growth across the Company's bitcoin mining and HPC hosting businesses.
TeraWulf對運營卓越和可持續發展的承諾繼續推動其在公司比特幣挖礦和HPC託管業務中的增長。
As of November 30, 2024, TeraWulf's operational bitcoin mining capacity was 195 MW at the Lake Mariner facility. Upon completing miner repairs, fleet upgrades and onboarding new miners, TeraWulf's self-mining hash rate is expected to reach approximately 9.7 EH/s. November's average hash rate was 5.9 EH/s, factoring in planned outage for electrical upgrades, demand response events and optimization strategies to maximize profitability.
截至2024年11月30日,TeraWulf在Lake Mariner設施的運營比特幣挖礦能力爲195 MW。在完成礦機維修、機隊升級和新礦工入駐後,TeraWulf的自礦哈希率預計將達到約9.7 EH/s。11月份的平均哈希率爲5.9 EH/s,考慮到電氣升級的計劃停機、需求響應事件和優化策略以最大化盈利能力。
On the WULF Compute front, progress continues on large-scale HPC hosting infrastructure at Lake Mariner. Dry cooler installation is complete for the 20 MW CB-1 facility, which is on track for Q1 2025 completion. We remain on schedule to deliver 72.5 MW of HPC hosting capacity by the end of Q2 2025.
在WULF計算方面,Lake Mariner的大規模HPC託管基礎設施的進展持續進行。20 MW的Cb-1設施的乾冷卻器安裝已完成,預計將在2025年第一季度完成。我們仍按計劃在2025年第二季度末交付72.5 MW的HPC託管能力。
About TeraWulf
關於TeraWulf
TeraWulf develops, owns, and operates environmentally sustainable, next-generation data center infrastructure in the United States, specifically designed for Bitcoin mining and high-performance computing. Led by a team of seasoned energy entrepreneurs, the Company owns and operates the Lake Mariner facility situated on the expansive site of a now retired coal plant in Western New York. Currently, TeraWulf generates revenue primarily through Bitcoin mining, leveraging predominantly zero-carbon energy sources, including hydroelectric and nuclear power. Committed to environmental, social, and governance (ESG) principles that align with its business objectives, TeraWulf aims to deliver industry-leading economics in mining and data center operations at an industrial scale.
TeraWulf在美國開發、擁有並運營環境可持續的新一代數據中心基礎設施,專爲比特幣挖掘和高性能計算而設計。由經驗豐富的能源企業家領導,公司擁有並運營位於紐約西部一座現已退役煤電廠寬敞用地上的Lake Mariner設施。目前,TeraWulf主要通過比特幣挖掘實現收入,主要利用水力發電和核電等幾乎零碳能源。致力於與業務目標一致的環境、社會和治理(ESG)原則,TeraWulf旨在以工業規模交付挖礦和數據中心運營的業內領先經濟效益。
Forward-Looking Statements
前瞻性聲明
This press release contains forward-looking statements within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as "plan," "believe," "goal," "target," "aim," "expect," "anticipate," "intend," "outlook," "estimate," "forecast," "project," "continue," "could," "may," "might," "possible," "potential," "predict," "should," "would" and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf's management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) conditions in the cryptocurrency mining industry, including fluctuation in the market pricing of bitcoin and other cryptocurrencies, and the economics of cryptocurrency mining, including as to variables or factors affecting the cost, efficiency and profitability of cryptocurrency mining; (2) competition among the various providers of cryptocurrency mining services; (3) changes in applicable laws, regulations and/or permits affecting TeraWulf's operations or the industries in which it operates, including regulation regarding power generation, cryptocurrency usage and/or cryptocurrency mining, and/or regulation regarding safety, health, environmental and other matters, which could require significant expenditures; (4) the ability to implement certain business objectives and to timely and cost-effectively execute integrated projects; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to growth strategies or operations; (6) loss of public confidence in bitcoin or other cryptocurrencies and the potential for cryptocurrency market manipulation; (7) adverse geopolitical or economic conditions, including a high inflationary environment; (8) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (9) the availability, delivery schedule and cost of equipment necessary to maintain and grow the business and operations of TeraWulf, including mining equipment and infrastructure equipment meeting the technical or other specifications required to achieve its growth strategy; (10) employment workforce factors, including the loss of key employees; (11) litigation relating to TeraWulf and/or its business; and (12) other risks and uncertainties detailed from time to time in the Company's filings with the Securities and Exchange Commission ("SEC"). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company's filings with the SEC, which are available at www.sec.gov.
本新聞稿包含根據1995年修正版《私人證券訴訟改革法》中的「安全港」條款做出的前瞻性聲明。這些前瞻性聲明涉及預期的未來事件和預期,而不是歷史事實。除歷史事實外,所有聲明都可以被視爲前瞻性聲明。此外,儘管沒有這些詞或表達,但通常可以用諸如「計劃」、「相信」、「目標」、「目標」、「目標」、「期望」、「預計」、「有利前景」、「估計」、 「預測」、「項目」、「繼續」、「可能」、「可能」、「潛在」、「預測」、「應該」、「將」和其他類似的詞彙和表達來識別前瞻性聲明,儘管缺乏這些詞或表達並不意味着一份聲明不是前瞻性的。前瞻性聲明基於TeraWulf管理層的當前期望和信念,並天生受到一系列因素、風險、不確定性和假設及其潛在影響的影響。不能保證未來的發展將是預期的發展。由於風險、不確定性和假設的事實、風險、不確定性和假設可能導致實際結果與前瞻性聲明中表述的結果有根本不同,這些前瞻性聲明可能會根據多種因素(但不限於此)產生的實際月度哈希率表現,包括(但不限於)性能調整以提高效率和最大化利潤的計劃外停機範圍工程,計劃之外的停機,參與各種產生現金的需求響應項目和當地政策等影響成本、效率和利潤的因素或變量。各種加密貨幣開採服務提供商之間的競爭,適用法律、法規和/或許可證的變化涉及TeraWulf的業務或其所處行業的法規,包括有關發電、加密貨幣使用和/或加密貨幣開採的法規,以及有關安全、健康、環境和其他事項的法規,這可能需要支付巨額支出;實施某些業務目標並實時、具有成本效益地執行綜合項目的能力;未能及時且符合增長戰略或運營要求的可接受條款融資;公衆對比特幣或其他加密貨幣的信心的喪失,以及加密貨幣市場操縱的可能性;不利的地緣政治或經濟狀況,包括高通脹環境;網絡犯罪、洗錢、惡意軟件感染和網絡釣魚等風險,以及由於設備故障或損壞、物理災害、數據安全漏洞、計算機故障或破壞導致的損失和干擾以及與此類事件相關的成本;支持公司業務和運營所需的設備的可用性、交付計劃和成本,包括符合實現其增長戰略所需的技術或其他規格要求的開採設備和基礎設施設備;員工的僱用工作力因素,包括關鍵員工的流失;與TeraWulf和/或其業務有關的訴訟;以及其他風險和不確定性,這些風險和不確定性會隨時因不同時間或未來企業或經濟狀況的變化而發生變化。潛在投資者、股東和其他讀者被警告不要將太多信任寄託在這些前瞻性聲明上,這些前瞻性聲明僅在其做出時發揮作用,除非依法或依法規定,否則TeraWulf不承擔公開更新前瞻性聲明的任何義務。參與者將被指引到關於前瞻性聲明的風險和不確定性的全面討論,以及公司在美國證券交易委員會(「SEC」)的文件中包含的風險因素的討論,在www.sec.gov。
Investors:
Investors@terawulf.com
投資者:
Investors@terawulf.com
Media:
media@terawulf.com
媒體:
media@terawulf.com
譯文內容由第三人軟體翻譯。