The facility is now 80% complete.
該設施現在已經完成80%。
Keppel has completed the installation of a gas turbine at the Keppel Sakra Cogen Plant, Singapore's first hydrogen-compatible cogeneration power plant.
吉寶已經在吉寶薩克拉分佈式聯合發電廠完成了一臺燃料燃氣輪機的安裝,這是新加坡第一座適用於氫能的聯合發電廠。
In a statement, the company said the turbine will improve the efficiency of the 600-megawatt (MW) combined cycle gas turbine (CCGT) power plant. The facility will also be able to produce steam for use in industrial processes for energy and chemicals customers on Jurong Island.
公司在一份聲明中表示,該燃機將提高這座600兆瓦(MW)的聯合循環燃氣輪機(CCGT)發電廠的效率。該設施還能夠爲裕廊島的能源和化學客戶生產工業過程中使用的蒸汽。
The CCGT plant is currently 80% complete and is on track to commence operations in the first half of 2026. When completed, the Keppel Sakra Cogen Plant will generate significantly less carbon than that of Singapore's average operating efficiency for the equivalent power generated using natural gas, abating over 6 million tonnes of emissions over its useful life.
CCGT發電廠目前已完成80%,計劃於2026年上半年開始運營。吉寶薩克拉分佈式聯合發電廠建成後,將大大減少新加坡通過使用天然氣發電所產生的碳排放,其整個使用壽命內將減少超過600萬噸的排放量。
"Once operational, the plant will expand Keppel's generation capacity by nearly 50% to 1,900 MW, enabling Keppel to play a larger role in meeting Singapore's growing energy demand," said Cindy Lim, CEO of Keppel's Infrastructure Division.
「一旦投入運營,該發電廠將使吉寶的發電能力增加近50%至1,900兆瓦,使吉寶能夠在滿足新加坡不斷增長的能源需求方面扮演更重要的角色,」吉寶基礎設施部門首席執行官林慧芬表示。
Keppel is also looking into other low carbon solutions and is one of two consortia shortlisted to commence pre-Front End Engineering and Design work to develop proposals to provide end-to-end low- or zero-carbon ammonia solutions for power generation and bunkering on Jurong Island.
吉寶還在研究其他低碳解決方案,並且被列爲兩個財團之一的候選人,開始進行前端工程設計工作,制定提供端到端低碳或零碳氨解決方案的建議,用於裕廊島上的發電和船用燃料補給。