Silver Tiger Announces PFS With NPV of US$222M for the Stockwork Zone of the El Tigre Silver-Gold Project, Sonora, Mexico
Silver Tiger Announces PFS With NPV of US$222M for the Stockwork Zone of the El Tigre Silver-Gold Project, Sonora, Mexico
HALIFAX, NS / ACCESSWIRE / October 22, 2024 / Silver Tiger Metals Inc. (TSXV:SLVR)(OTCQX:SLVTF) ("Silver Tiger" or the "Corporation") is pleased to announce a Preliminary Feasibility Study ("PFS") for its 100% owned, silver-gold El Tigre Project (the "Project" or "El Tigre") located in Sonora, Mexico. The PFS is focused on the conventional open pit mining economics of the Stockwork Mineralization Zone defined in the updated Mineral Resource Estimate ("MRE") (Figure 1). The updated MRE also contains an Out-of-Pit Mineral Resource that Silver Tiger plans to study in a Preliminary Economic Assessment in H1-2025.
HALIFAX,NS / ACCESSWIRE / 2024年10月22日 / 白銀虎金屬股份有限公司(TSXV:SLVR)(OTCQX:SLVTF)("Silver Tiger"或"公司")很高興宣佈其100%擁有的白銀-黃金El Tigre項目("項目"或"El Tigre")位於墨西哥索諾拉。 PFS聚焦於最新礦產資源估算("MRE")中定義的常規露天採礦經濟學的斯托克溝化礦化帶。更新後的MRE還包括一個外坑礦產資源,白銀虎計劃在2025年上半年對其進行初步經濟評估。
Highlights of the PFS are as follows (all figures in US dollars unless otherwise stated):
PFS的亮點如下(除非另有說明,所有數字均以美元計):
After-Tax net present value ("NPV") (using a discount rate of 5%) of US$222 million with an After-Tax IRR of 40.0% and Payback Period of 2.0 years (Base Case);
10-year mine life recovering a total of 43 million payable silver equivalent ounces ("AgEq") or 510 thousand payable gold equivalent ounces ("AuEq"), consisting of 9 million silver ounces and 408 thousand gold ounces;
Total Project undiscounted after-tax cash flow of US$318 million;
Initial capital costs of $86.8 million, which includes $9.3 million of contingency costs, over an expected 18-month build, expansion capital of $20.1 million in year 3 and sustaining capital costs of $6.2 million over the life of mine ("LOM");
Average LOM operating cash costs of $973/oz AuEq, and all in sustaining costs ("AISC") of $1,214/oz AuEq or Average LOM operating cash costs of $12/oz AgEq, and all in sustaining costs ("AISC") of $14/oz AgEq;
Average annual production of approximately 4.8 million AgEq oz or 56.7 thousand AuEq oz; and
Three (3) years of production in the Proven category in the Phase 1 Starter Pit.
使用5%的折現率的稅後淨現值("NPV")爲22200萬美元,稅後內部收益率爲40.0%,投資回收期爲2.0年(基準案例);
10年的礦山壽命,可回收4300萬盎司等值的可贖回白銀("AgEq")或51萬盎司等值的可贖回黃金("AuEq"),其中包括900萬盎司白銀和40.8萬盎司黃金;
項目總的稅後折現未考慮的現金流爲31800萬美元;
初始資本成本爲8680萬美元,其中包括930萬美元的應急成本,預計18個月的建設週期,第3年的擴建資本爲2010萬美元,維持資本成本爲620萬美元,可維持礦井壽命;
平均LOM運營現金成本爲每盎司973美元AuEq,全面維持成本("AISC")爲每盎司1214美元AuEq,或平均LOM運營現金成本爲每盎司12美元AgEq,全面維持成本("AISC")爲每盎司14美元AgEq;
預計年均產量約爲480萬盎司AgEq或5.67萬盎司AuEq;
在一期起始礦坑中,已經有三年的產量屬於已被證實類別。
Glenn Jessome, President & CEO stated "We are very pleased with the work completed by our consultants and our technical team on the PFS for the open pit at El Tigre. The open pit delivers robust economics with an NPV of US$222 million, an initial capital expenditure of US$87 million, and a payback of 2 years with 3 years of production in the Proven category in the 'Starter Pit using metal prices greatly discounted to the spot price." Mr. Jessome continued "This is a pivotal point for our Company as we now have a clear path forward to making a construction decision for the open pit. The open pit has good grade (48 g/t AgEq), low strip ratio (1.7:1), and wide benches (~150 m) with mineralization at surface. With such positive parameters and with our VP of Operations Francisco Albelais, a career expert in the construction of large heap leach mines in Mexico, we are confident we will be able to advance the Project very quickly." Mr. Jessome concluded "The open pit is only one component of El Tigre as we have also today delivered over 113 Mozs AgEq in the underground Mineral Resource Estimate and disclosed an Exploration Target establishing 10 to 12 million tonnes at 225 to 265 g/t AgEq for 73 to 100 Moz AgEq. This disclosed 'near-mine' Mineral Resource and potential, when coupled with the fact that only 30% of this prolific Property has been explored, shows the value of the El Tigre Project. The Company will also continue to work on this substantial underground Mineral Resource by starting underground drilling immediately, and plan to release an underground PEA in H1-2025."
格倫·傑瑟姆,總裁兼首席執行官表示"我們對我們的顧問團隊和技術團隊在El Tigre露天礦坑的可行性研究(PFS)所完成的工作感到非常滿意。該露天礦坑以大幅折價於現貨價金屬價格下的NPV達到22200萬美元,初始資本支出爲8700萬美元,投資回報期爲2年,其中有3年的產量屬於已被證實類別。傑瑟姆先生繼續說道:"對於我們公司來說,這是一個關鍵時刻,因爲我們現在已經明確了爲露天礦坑做出建設決策的正確道路。該露天礦坑具有良好的品位(48 g/t AgEq),低剝離比(1.7:1),寬坡面(約150米),礦化物位於地表。有了這麼積極的參數以及我們的運營副總裁弗朗西斯科·阿爾貝萊斯,一位在墨西哥大型堆浸礦山建設方面的專家,我們相信我們將能夠迅速推進該項目。"傑瑟姆先生總結道:"露天礦坑只是El Tigre項目的一個組成部分,因爲我們今天還在地下礦產資源評估中交付了逾113 Mozs AgEq,並公佈了一個探明礦物資源的探明目標,確定10至1200萬噸,AgEq爲225至265 g/t,AgEq爲73至100 Moz。這個公佈的『近礦』礦產資源和潛力,再加上這個富饒地塊僅有30%被探索,展現了El Tigre項目的價值。公司還將立即啓動地下鑽探工作,着手繼續開展這個龐大的地下礦產資源,並計劃在2025年上半年發佈地下礦Preliminary Economic Assessment(PEA)。"
Highlights of the updated Mineral Resource
更新後的礦產資源要點
Increased confidence in MRE, with increase of 132% in Total Measured & Indicated Silver Equivalent ("AgEq") Ounces from September 2023 MRE, with 59% increase in Measured & Indicated AgEq grade;
Total Measured & Indicated Mineral Resource of 200 Moz AgEq grading 92 g/t AgEq contained in 68.0 million tonnes ("Mt");
Inferred Mineral Resource of 84 Moz AgEq grading 180 g/t AgEq contained in 14.5 Mt; and
Inclusion of Out-of-Pit Mineral Resource of 5.3 Mt Measured & Indicated Mineral Resource at grade of 255 g/t AgEq and 10.1 Mt Inferred Mineral Resource grading 216 g/t AgEq.
對Mineral Resource Estimate(MRE)的信心增強,與2023年9月的MRE相比,Total Measured & Indicated Silver Equivalent("AgEq")盎司增加132%,Measured & Indicated AgEq品位增加了59%;
總計200 Moz AgEq的Total Measured & Indicated Mineral Resource,品位爲92 g/t AgEq,包含在6800萬噸("Mt")中。
推斷的礦產資源爲84 Moz AgEq,品位爲180 g/t AgEq,含量爲14.5 Mt;和
外場礦產資源包括5.3 Mt測量和指示礦產資源,品位爲255 g/t AgEq,以及10.1 Mt推斷礦產資源,品位爲216 g/t AgEq。
Preliminary Feasibility Summary
The PFS was prepared by independent consultants P&E Mining Consultants Inc. ("P&E"), with metallurgical test work completed by McClelland Laboratories, Inc. - Sparks, Nevada, process plant design and costing by D.E.N.M. Engineering Ltd., and environmental and permitting led by CIMA Mexico. Following are tables and figures showing key assumptions, results, and sensitivities.
初步可行性總結
PFS由獨立顧問公司P&E Mining Consultants Inc.(「P&E」)編制,冶金測試由McClelland Laboratories, Inc. - Sparks, Nevada完成,工藝設計和成本由D.E.N.m. Engineering Ltd.負責,環保和許可由CIMA Mexico主導。以下是顯示關鍵假設、結果和敏感性的表格和圖表。
Table 1: El Tigre PFS Key Economic Assumptions and Results (1-2)
表1:El Tigre PFS關鍵經濟假設和結果(1-2)
Assumption / Result |
Unit |
Value |
Assumption / Result |
Unit |
Value |
|
---|---|---|---|---|---|---|
Total OP Plant Feed Mined |
kt |
40,292 |
Net Revenue |
US$M |
1,093 |
|
Operating Strip Ratio |
Ratio |
1.7:1 |
Initial Capital Costs |
US$M |
87 |
|
Silver Grade 1 |
g/t |
14.9 |
Expansion Capital Costs |
US$M |
15 |
|
Gold Grade 1 |
g/t |
0.40 |
Sustaining Capital Costs |
US$M |
11 |
|
Silver Recovery (Oxide/Sul.) 2 |
% |
45 / 40 |
Mining Costs |
$/t Material |
2.24 |
|
Gold Recovery (Oxide/Sul.) 2 |
% |
83 / 56 |
Processing Costs (Phase 1 and Phase 2) |
$/t Feed |
5.79/4.74 |
|
Silver Price |
US$/oz |
26.00 |
G&A Costs |
$/t Feed |
1.27 |
|
Gold Price |
US$/oz |
2,150 |
Operating Cash Cost |
US$/oz AgEq |
11.6 |
|
Payable Silver Metal |
Moz |
8.57 |
All-in Sustaining Cost |
US$/oz AgEq |
14.4 |
|
Payable Gold Metal |
koz |
408 |
After-Tax NPV (5% discount) |
US$M |
222 |
|
Payable AgEq |
Moz |
42.9 |
Pre-Tax NPV (5% discount) |
US$M |
342 |
|
Mine Life |
Yrs |
10 |
After-Tax IRR |
% |
40.0 |
|
Average mining rate |
t/day |
30,000 |
Pre-Tax IRR |
% |
51.2 |
|
After-Tax Payback Period |
Yrs |
2.0 |
假設/結果 |
單位 |
數值 |
Assumption / Result |
單位 |
數值 |
|
---|---|---|---|---|---|---|
Total OP Plant Feed Mined |
千噸 |
40,292 |
淨營業收入 |
美元 |
1,093 |
|
操作梯度比 |
比率 |
1.7開多:1 |
$92百萬($18百萬維持資本開支,持續礦生命週期) |
美元 |
87 |
|
白銀品位1 |
克/噸 |
14.9 |
擴張資本成本 |
美元 |
15 |
|
黃金品位 1 |
克/噸 |
0.40 |
維持資本成本 |
美元 |
11 |
|
白銀回收(氧化物/硫化物)2 |
% |
45 / 40 |
採礦成本 |
每噸材料 |
2.24 |
|
黃金回收(氧化/硫化)2 |
% |
83 / 56 |
加工成本(階段1和階段2) |
每噸飼料 |
5.79/4.74 |
|
白銀價格 |
美元/盎司 |
26.00 |
管理與銷售成本 |
每噸飼料 |
1.27 |
|
黃金價格 |
美元/盎司 |
2,150 |
控件現金成本 |
白銀當量每盎司美元 |
責任範圍 |
|
可付白銀金屬 |
百萬盎司 |
8.57 |
全包生產成本 |
白銀當量每盎司美元 |
14.4 |
|
應付黃金金屬 |
千盎司(koz) |
408 |
稅後淨現值(5%折現) |
美元 |
222 |
|
應付白銀當量 |
百萬盎司 |
42.9 |
稅前NPV(5%折現率) |
美元 |
342 |
|
礦山壽命 |
年 |
10 |
稅後內部收益率(IRR) |
% |
與Allist協議有關,在2021年12月,雙方還簽署了一份聯合臨床合作協議(「臨床合作」),規定了雙方合作和共同承擔全球臨床研究成本的框架。在2024年3月31日和2023年的三個月期間內,公司分別支出了1,200萬美元的成本補償金,這已在臨床協作協議下記爲研究和發展費用貸方。對於2024年3月31日和2023年的每個三個月期間,公司還有資格從Allist獲得1200萬美元的費用補償金,這已被記錄爲減少研究和開發費用。公司按照ASC 808《合作安排》進行了臨床合作評估。 |
|
每天的平均採礦速率 |
每天噸 |
30,000 |
稅前內部收益率(IRR) |
% |
51.2 |
|
稅後收回期 |
年 |
2.0 |
Grades shown are LOM average process plant feed grades include only OP sources. Mining losses and external dilution of 3.7% were incorporated in the mining schedule.
Column testing indicated both variable gold and silver recovery for the oxide material vs the previously reported non-discounted PEA (83% and 64%) at a 3/8-in crush size. In the process design and financial model for the PFS process design and financial model recoveries have been discounted by 3% for leaching in the field versus optimum conditions in the laboratory and shown accordingly. The presence of transition and sulfide zones has affected both the gold and silver recoveries and are shown as separate recoveries. These are reasonable and appropriate for use in this PFS design and economic analysis.
所示品位爲LOm平均工藝廠進料品位,僅包括OP來源。在採礦計劃中考慮了3.7%的採礦損失和外部稀釋。
柱體測試顯示氧化材料的可變黃金和白銀回收率與先前報告的未打折前PEA(83%和64%)在3/8英寸碎石尺寸下。在PFS工藝設計和財務模型中,回收率已因現場浸出與實驗室最佳條件相比而打折3%並相應顯示。過渡帶和硫化帶的存在影響了黃金和白銀的回收率,並顯示爲單獨的回收率。在此PFS設計和經濟分析中使用這些回收率是合理且適當的。
Figure 2: El Tigre Cash Flow Profile by Year
圖2:El Tigre按年現金流量概況
Figure 2 above highlights the post-tax cash flows of US$318 million associated with the El Tigre Project. The economics of the Project have been evaluated based on the base case scenario $26/oz silver price and gold price of $2,150/oz. As illustrated in the following sensitivity tables, the Project remains robust even at lower commodity prices or with higher costs (Tables 2 and 3).
上圖2突顯了El Tigre項目的31800萬美元的稅後現金流。項目的經濟性是基於基準情景26美元/盎司的銀價和2150美元/盎司的金價進行評估的。如下的敏感性表格所示,即使商品價格較低或成本較高(表2和表3),項目仍然具有強大可持續性。
Table 2 - El Tigre PFS Gold and Silver Price Sensitivities
表2 - El Tigre PFS 黃金和白銀價格敏感度
Sensitivity |
Base Case |
||||||
---|---|---|---|---|---|---|---|
Silver Price (US$/oz) |
18 |
22 |
26 |
30 |
34 |
38 |
42 |
Gold Price (US$/oz) |
1,500 |
1,750 |
2,150 |
2,500 |
2,750 |
3,000 |
3,250 |
After-Tax NPV (5%) (US$M) |
55.9 |
123.9 |
221.5 |
308.7 |
375.6 |
442.5 |
509.4 |
After-Tax IRR (%) |
15.8 |
26.7 |
40.0 |
50.2 |
57.2 |
63.9 |
70.3 |
After-Tax Payback (years) |
4.5 |
3.4 |
2.0 |
1.7 |
1.6 |
1.4 |
1.3 |
靈敏度 |
基準案例 |
||||||
---|---|---|---|---|---|---|---|
白銀價格(美元/盎司) |
18 |
22 |
26 |
30 |
34 |
38 |
42 |
黃金價格(美元/盎司) |
1,500 |
1,750 |
2,150 |
2,500 |
2,750 |
3,000 |
3250 |
稅後淨現值(5%)(美元百萬) |
55.9 |
123.9萬美元現金及現金等價物被屬於2022年12月31日的合併資產負債表,其中$ |
221.5 |
308.7 |
375.6 |
442.5 |
509.4 |
After-Tax IRR (%) |
15.8 |
26.7 |
與Allist協議有關,在2021年12月,雙方還簽署了一份聯合臨床合作協議(「臨床合作」),規定了雙方合作和共同承擔全球臨床研究成本的框架。在2024年3月31日和2023年的三個月期間內,公司分別支出了1,200萬美元的成本補償金,這已在臨床協作協議下記爲研究和發展費用貸方。對於2024年3月31日和2023年的每個三個月期間,公司還有資格從Allist獲得1200萬美元的費用補償金,這已被記錄爲減少研究和開發費用。公司按照ASC 808《合作安排》進行了臨床合作評估。 |
50.2 |
57.2 |
63.9 |
70.3 |
稅後回本期(年) |
4.5 |
3.4 |
2.0 |
1.7 |
1.6 |
1.4 |
1.3 |
Table 3 - El Tigre PFS Operating Cost and Capital Cost Sensitivities
表3 - 老虎礦可行性研究運營成本和資本成本敏感性
Sensitivity |
-20% |
-10% |
Base Case |
10% |
20% |
---|---|---|---|---|---|
Operating Costs - NPV (5%) (US$M) |
270.4 |
246.0 |
221.5 |
194.2 |
169.6 |
Operating Costs - IRR (%) |
46.2 |
43.2 |
40.0 |
36.1 |
32.7 |
Capital Costs - NPV (5%) (US$M) |
236.7 |
229.1 |
221.5 |
211.1 |
203.4 |
Capital Costs - IRR (%) |
48.5 |
43.9 |
40.0 |
36.1 |
33.2 |
靈敏度 |
-20% |
-10% |
基準案例 |
10% |
20% |
---|---|---|---|---|---|
運營成本 - NPV (5%) (美元百萬) |
270.4 |
246.0 |
221.5 |
194.2 |
169.6 |
營運成本 - 內部回報率(%) |
2021年10月30日,截至該日爲止。 |
43.2 |
與Allist協議有關,在2021年12月,雙方還簽署了一份聯合臨床合作協議(「臨床合作」),規定了雙方合作和共同承擔全球臨床研究成本的框架。在2024年3月31日和2023年的三個月期間內,公司分別支出了1,200萬美元的成本補償金,這已在臨床協作協議下記爲研究和發展費用貸方。對於2024年3月31日和2023年的每個三個月期間,公司還有資格從Allist獲得1200萬美元的費用補償金,這已被記錄爲減少研究和開發費用。公司按照ASC 808《合作安排》進行了臨床合作評估。 |
36.1 |
32.7 |
資本成本 - 淨現值(5%)(百萬美元) |
236.7 |
229.1 |
221.5 |
211.1 |
公司於2015年3月發行了總額爲$的 |
資本成本 - 內部收益率 (%) |
48.5 |
43.9 |
與Allist協議有關,在2021年12月,雙方還簽署了一份聯合臨床合作協議(「臨床合作」),規定了雙方合作和共同承擔全球臨床研究成本的框架。在2024年3月31日和2023年的三個月期間內,公司分別支出了1,200萬美元的成本補償金,這已在臨床協作協議下記爲研究和發展費用貸方。對於2024年3月31日和2023年的每個三個月期間,公司還有資格從Allist獲得1200萬美元的費用補償金,這已被記錄爲減少研究和開發費用。公司按照ASC 808《合作安排》進行了臨床合作評估。 |
36.1 |
人民幣3.32億元($ |
Capital and Operating Costs
The El Tigre Project has been envisioned as an open pit mining operation starting at a processing rate of 7,500 tonnes per day for years 1-3 and then ramping up to 15,000 tonnes per day by year 4 after 1 year construction for ramp up in year 3.
資本和運營成本
El Tigre項目被設想爲露天採礦操作,從第1至第3年起始加工速率爲每天7,500噸,然後在第4年增加到每天15,000噸,在第3年施工完畢後逐步提升。
The process plant is comprised of conventional three (3) stage crushing to an optimum -3/8 inch (10 mm) crush size. The crushed material will be conveyed and loaded on the lined pad areas. A series of pumping and piping will allow irrigation of the stacked heap material and subsequent production of pregnant solution to flow to the respective impoundment pond. The pregnant solution will be pumped to the recovery facility consisting of the Merrill - Crowe process (zinc precipitation) and refinery to produce the gold and silver dore for marketing. The process barren solution will be recycled (with NaCN addition) and pumped back to the heap for further leaching. The process plant location will be adjacent to the pad and pond infrastructure area.
工藝廠由傳統的三級破碎工藝組成,使礦石粒度最優爲-3/8英寸(10毫米)。破碎後的料將被輸送並裝載到鋪墊區域。一系列的泵和管道將允許澆灌堆積的礦石料,並隨後生產含金溶液流入各自的堆積池。含金溶液將被抽送至含金回收設施,包括Merrill-Crowe工藝(鋅沉澱)和精煉設施,用於生產黃金和白銀金條以供市場銷售。工藝中的貧化溶液將被回收(加入NaCN)並抽送回堆石進行更多的浸出。工藝園區將位於鋪墊和池塘基礎設施區旁邊。
Water supply to the process plant is provided by pumping from nearby Bavispe River to the process area water distribution system and high voltage grid power will be installed by the local utility to supply process and infrastructure electrical requirements. Expansion capital includes the cost to increase the process plant capacity from 7,500 tonnes per day to 15,000 tonnes per day as noted in Year 4 of operation.
工藝廠的供水由從附近的巴維斯佩河抽水至工藝區供水系統,並且由當地公用事業公司安裝高壓電網以滿足工藝和基礎設施電力需求。擴建資本包括增加工藝廠產能的費用,從每天7,500噸增加到每天15,000噸,如在運營的第4年所述。
Table 4 - LOM Capital Cost Estimate
表4 - 方案資本成本估算
Type |
Initial |
Expansion |
Sustaining |
Total |
(US$k) |
(US$k) |
(US$k) |
(US$k) |
|
Process Plant direct costs |
42,851 |
13,584 |
1,600 |
58,034 |
Mining direct costs |
2,660 |
4,362 |
3,956 |
10,978 |
Pre-stripping |
3,362 |
3,362 |
||
Infrastructure |
20,489 |
20,489 |
||
Process indirect costs (with EPCM) |
8,121 |
8,121 |
||
Total |
77,483 |
17,946 |
5,556 |
100,985 |
Contingency (12%) |
9,298 |
2,199 |
622 |
12,118 |
Total with Contingency |
86,780 |
20,145 |
6,178 |
113,103 |
類型 |
初始 |
擴張 |
持續性 |
總費用 |
(千美元) |
(千美元) |
(千美元) |
(千美元) |
|
加工廠直接成本 |
42,851 |
13,584 |
1,600 |
58,034 |
採礦直接成本 |
2,660 |
4,362 |
3,956 |
10,978 |
Pre-stripping |
3,362 |
3,362 |
||
製造行業 |
20,489 |
20,489 |
||
處理間接成本(與EPCM合作) |
8,121 |
8,121 |
||
總費用 |
77,483 |
17,946 |
5,556 |
100,985 |
應急費用(12%) |
9,298 |
2,199 |
622 |
12,118 |
總額含應急費用 |
86,780 |
20,145 |
6,178 |
113,103 |
Mining
Open pit mining will be contracted and carried out by drill and blast followed by conventional loading and truck haulage to the waste rock storage facilities and the process plant.
採礦業
露天礦採礦將由鑽孔和爆破進行承包,並隨後進行常規裝載和卡車運輸到廢石堆存設施和工藝廠。
Metallurgy
A detailed metallurgical test program was carried out by McClelland Laboratories, Inc., Sparks, Nevada on six (6) El Tigre starter pit samples. The program included crushing, coarse bottle rolls, and column testing at both 80% passing 3/8 inch and 1/2 inch (10 and 12 mm) crush size for five (5) of the six samples. One low grade sample was only crushed to 80% passing 1-1/2 inch (38 mm) as an indication of low grade leachability. The leach samples comprised of drill core sample representing the starter pit and during the testing process it became apparent that the presence of transition and sulfide zones are in the starter pit thus affecting the base design recoveries. This variable test program (column and coarse bottle roll) estimated oxide average gold and silver respective metallurgical recoveries of 86% Au and 48% Ag at the 3/8 inch (10 mm) crush. The transition and sulfide zones had estimated recoveries of 59% Au and 43% Ag. Further percolation testing also confirmed no requirement for agglomeration of the crushed material is required prior to loading on the leach pad.
2023年9月30日及MD&A報告日期時的未履行DSU
McClelland Laboratories, Inc.在內華達州斯帕克斯進行了對6個El Tigre起始坑樣本的詳細冶金測試項目。 測試項目包括粗瓶滾和柱式試驗,分別在80%經過3/8英寸和1/2英寸(10和12毫米)碎石尺寸下進行,其中5個樣本的尺寸。 一個低品位樣本僅經過80%通過1-1/2英寸(38毫米)碾碎,作爲低品位浸出性的指示。 浸出樣本包括代表起始坑的鑽芯樣本,在測試過程中,出現了明顯具有過渡帶和硫化帶存在於起始坑中,從而影響基礎設計回收率。 變量測試項目(柱式和粗瓶滾)估計了在3/8英寸(10毫米)破碎下,氧化平均金和白銀各冶金回收率分別爲86% Au和48% Ag。 過渡和硫化帶的估計回收率爲59% Au和43% Ag。 進一步滲演測試也確認,在裝載浸出墊前,不需要對碎料進行團聚化。
Mineral Resource Estimate
The basis for the PFS is the Mineral Resource Estimate completed by P&E for the El Tigre Project located in Sonora State, Mexico, which has an effective date of October 22, 2024, with an NI 43-101 Technical Report to be filed within 45 days of this news release. A summary of the Mineral Resource Estimate is provided in Table 5.
礦物資源估算
PFS的依據是P&E爲位於墨西哥索諾拉州的El Tigre項目完成的涉礦概念估算,有效日期爲2024年10月22日,NI 43-101技術報告將在此新聞發佈後的45天內提交。 涉礦概念估算摘要詳見表5。
Table 5 - Updated Mineral Resource Estimate October 2024
表5 - 更新的涉礦概念估算2024年10月
Mineral Resources, which are not Mineral Reserves, do not have demonstrated economic viability. The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
The Inferred Mineral Resource in this estimate has a lower level of confidence than that applied to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of the Inferred Mineral Resource could be upgraded to an Indicated Mineral Resource with continued exploration.
The Mineral Resources were estimated in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council.
Historically mined areas were depleted from the Mineral Resource model.
Prices used are US$2,000/oz Au, US$25/oz Ag, US$4.00/lb Cu, US$0.95 lb Pb and US$1.25/lb Zn.
The pit-constrained AuEq respective oxide and sulfide cut-off grades of 0.10 and 0.15 g/t were derived from 40% Ag and 83% Au oxide process recovery, 40% Ag and 56% Au sulfide process recovery, US$5.25/tonne process and G&A cost. The constraining pit optimization parameters were $2.00/t mining cost and 45-degree pit slopes. Regarding recoveries, the PFS recovery for Ag in oxide material was increased to 45% after a more detailed study was complete after the MRE was finalized.
The out-of-pit AuEq cut-off grade of 1.50 g/t was derived 93% Ag and 89% Au process recovery, US$28/tonne process and G&A cost, and a $60/tonne mining cost. The out-of-pit Mineral Resource grade blocks were quantified above the 1.50 g/t AuEq cut-off, below the constraining pit shell and within the constraining mineralized wireframes. Out-of-Pit Mineral Resources are restricted to the El Tigre Main Veins, which exhibit historical continuity and reasonable potential for extraction by cut and fill and long hole mining methods.
The Low-Grade Stockpile AuEq cut-off grade of 0.54 g/t was derived from 85% Ag and 85% Au recovery US$28/tonne process and G&A cost, and a $2/tonne mining cost.
The Tailings AuEq cut-off grade of 0.55 g/t was derived from 82% Ag and 83% Au process recovery, US$28.72/tonne process and G&A cost.
AgEq and AuEq were calculated at an Ag/Au ratio of 166:1 (oxide) and 122:1 (sulfide) for pit-constrained Mineral Resources.
AgEq and AuEq were calculated at an Ag/Au ratio of 77:1 for out-of-pit Mineral Resources.
AgEq and AuEq were calculated at an Ag/Au ratio of 80:1 for Low-Grade Stockpile Mineral Resources.
AgEq and AuEq were calculated at an Ag/Au ratio of 79:1 for Tailings Mineral Resources
Totals may not sum due to rounding.
涉礦概念,不是礦石儲備,尚未證實具備經濟可行性。涉礦概念的估算可能受環境、許可、法律、所有權、稅收、社會政治、市場或其他相關問題的影響。
此估算中的推論性涉礦概念比應用於指示性涉礦概念的置信度低,不得轉換爲礦石儲備。可以合理預期大部分推論性涉礦概念可以通過繼續勘探提升爲指示性涉礦概念。
涉礦概念的估算是根據加拿大礦業、冶金和石油協會(CIM)的準則,CIM有關礦產資源和儲備的標準、定義和指南所制定的,由CIM儲量定義委員會準備,並由CIM理事會採納。
歷史上已開採的區域已從涉礦概念模型中剝奪。
所使用的價格分別是美元每盎司黃金$2,000,白銀$25,銅每磅$4.00,鉛每磅$0.95和鋅每磅$1.25。
在40%的白銀和83%的金氧化物工藝回收率,40%的白銀和56%的金硫化物工藝回收率,美元每噸$5.25的工藝費用和G&A成本下,Pit-constrained AuEq分別金氧化物和硫化物切割等級分別爲0.10和0.15 g/t。約束性開採優化參數包括每噸$2.00的採礦成本和45度的礦坑坡度。關於回收率,氧化材料中Ag的PFS回收率在MRE完成後進行了更詳細的研究後提高到45%。
街區外AuEq切割等級爲1.50 g/t,回收率爲93%的Ag和89%的Au,美元每噸$28的工藝費用和G&A成本,以及每噸$60的採礦成本。街區外涉礦資源等級塊量化超過1.50 g/t AuEq切割,低於約束性礦坑外殼,且在約束性礦化框內。區外涉礦資源受限於展現出歷史連續性和通過切割和長孔採礦方法進行開採的El Tigre主脈。
白銀和黃金的低品位存儲庫AuEq切割品位爲0.54 g/t,是由85%白銀和85%黃金回收率以及每噸28美元的過程和G&A成本以及每噸2美元的採礦成本衍生出的。
尾礦AuEq切割品位爲0.55 g/t,來源於82%白銀和83%黃金的過程回收率,每噸28.72美元的過程和G&A成本。
AgEq和AuEq根據166:1(氧化物)和122:1(硫化物)的Ag/Au比率計算出受坑限制的礦產資源。
AgEq和AuEq根據77:1的Ag/Au比率計算出場外礦產資源。
AgEq和AuEq根據80:1的Ag/Au比率計算出低品位存儲庫礦產資源。
AgEq和AuEq根據79:1的Ag/Au比率計算出尾礦礦產資源。
總數可能因四捨五入而不準確。
Mineral Resource Estimate Methodology - El Tigre Project
The El Tigre Project includes the El Tigre Veins, El Tigre Tailings and the El Tigre Low-Grade Stockpile.
礦產資源估算方法-El Tigre項目
El Tigre項目包括El Tigre礦脈、El Tigre尾礦和El Tigre低品位尾礦庫。
The databases used for this Mineral Resource update contain a total of 20,149 collar records that contribute directly to the Mineral Resource Estimate and includes collar, survey, assay, lithology and bulk density data. Assay data includes Au g/t, Ag g/t, Cu %, Pb % and Zn % grades. The drilling extends approximately five km along strike.
用於這一礦產資源更新的數據庫包含共計20,149個領口記錄,直接貢獻於礦產資源評估,其中包括領口、測量、化驗、巖性和堆積密度數據。化驗數據包括金(Au)克/噸、銀(Ag)克/噸、銅(Cu)%、鉛(Pb)%和鋅(Zn)%品位。鑽探沿着大約五公里的走向延伸。
P&E Mining Consultants Inc. ("P&E") collaborated with Silver Tiger personnel to develop the mineralization models, grade estimates, and reporting criteria for the Mineral Resources at El Tigre. Mineralized domains were initially developed by Silver Tiger and were reviewed and modified by P&E. A total of twenty-seven individual mineralized domains have been identified through drilling and surface sampling. Interpreted mineralization wireframes were developed by Silver Tiger geologists for the El Tigre Veins based on logged drill hole lithology, assay grades and historical records. Silver Tiger identified continuous zones of mineralization from assay grades equal to or greater than 0.30 g/t AuEq with observed continuity along strike and down-dip, using a calculated Ag:Au equivalent factor of 75:1. The selected intervals include lower grade material where necessary to maintain wireframe continuity between drill holes.
P&E礦業顧問有限公司("P&E")與Silver Tiger人員合作,爲El Tigre的礦產資源開發礦化模型、評級估算和報告標準。礦化領域最初由Silver Tiger開發,並由P&E進行審查和修改。通過鑽探和地表取樣共確認了27個礦化領域。銀虎地質學家根據記錄的鑽孔巖性、化驗品位和歷史記錄,爲El Tigre礦脈開發了解釋性的礦化線框模型。Silver Tiger基於計算的Ag:Au當量比75:1,識別了從化驗品位等於或高於0.30g/t AuEq的礦化連續帶,觀察到了沿走向和向下傾斜的連續性,選定區間在必要時包括更低品位物質以維持鑽孔之間的線框連續性。
P&E developed mineralized domains for the El Tigre Low-Grade Stockpile and the El Tigre Tailings based on lithological logging and LiDAR surface topography.
P&E根據巖性記錄和LiDAR地表地形爲El Tigre低品位尾礦庫和El Tigre尾礦開發了礦化領域。
Assay samples were composited to either 1.00 m or 1.50 m for the vein domains. No compositing was used for the Low-Grade Stockpiles and Tailings models. Composites were capped prior to grade estimation based on the analysis of individual composite log-probability distributions.
對礦脈領域的化驗樣品進行合成,合成到100萬或150萬。對低品位尾礦庫和尾矟能量模型未進行合成。在進行個體複合概率分佈分析之前,對合成進行了封頂。
A total of 5,542 bulk density values were taken by Silver Tiger from drill hole core. Mineralized bulk density values were assigned for each of the El Tigre Main Veins based on the median vein measurement. For the El Tigre North Veins, a bulk density of 2.65 t/m 3 was assigned for the veins and a value of 2.42 t/m 3 was assigned for the Protectora Halo. For the Low-Grade Stockpile a value of 1.60 t/m 3 was assigned, and for the Tailings a value of 1.39 t/m 3 was used based on 37 nuclear density measurements.
Silver Tiger根據鑽孔核心採集了共計5542個堆積密度數值。基於中值礦脈測量值,爲每個El Tigre主脈指定了礦化的堆積密度值。對於El Tigre北脈,爲脈石指定了2.65 t/m 3的堆積密度,併爲Protectora Halo指定了2.42 t/m 3的數值。對於低品位尾礦庫,指定了1.60 t/m 3的數值,對於尾礦,基於37個核密度測量,使用了1.39 t/m 3的數值。
Vein block grades for gold and silver were estimated by Inverse Distance Cubed ("ID3") interpolation of capped composites using a minimum of four and a maximum of twelve composites. Vein block grades for copper, lead and zinc were estimated by Inverse Distance Squared ("ID2") interpolation of capped composites using a minimum of four and a maximum of twelve composites.
金和白銀的礦脈塊品位通過截尾組合的反距離三次方(「ID3」)插值估算,使用最少四個最多十二個組合。銅、鉛和鋅的礦脈塊品位通過截尾組合的反距離二次方(「ID2」)插值估算,使用最少四個最多十二個組合。
Nearest-Neighbour grade interpolation was used for the Low-Grade Stockpiles, and for the Tailings, block grades were estimated by ID2 estimation of capped assays using a minimum of four and a maximum of twelve samples.
對於低品位堆存礦石,採用最近鄰插值法,對於尾礦,塊品位通過截尾檢驗的ID2估算插值,使用最少四個最多十二個樣本。
For the El Tigre Main Veins, blocks within 30 m of three or more drill holes/channels were classified as Measured Mineral Resources, and blocks within 60 m of three or more drill holes/channels were classified as Indicated Mineral Resources. All additional estimated blocks were classified as Inferred Mineral Resources.
對於El Tigre主脈,距離三個或更多鑽孔/測量通道3000萬內的塊被歸類爲測量礦產資源,距離三個或更多鑽孔/測量通道6000萬內的塊被歸類爲指示礦產資源。所有其他估算的塊被歸類爲推斷礦產資源。
For the North Veins, blocks interpolated by at least two drill holes within 50 m were classified as Indicated Mineral Resources. Blocks interpolated by at least one drill hole within a maximum distance of 200 m were classified as Inferred Mineral Resources.
對於North Veins,至少有兩個鑽孔內插值5000萬內的塊被歸類爲指示礦產資源。至少有一口鑽孔內估算距離不超過20000萬的塊被歸類爲推斷礦產資源。
For the Low-Grade Stockpiles, blocks within 15 m of two or more drill holes were classified as Indicated Mineral Resources. All additional estimated blocks were classified as Inferred Mineral Resources.
對於低品位堆存礦石,距離兩個以上鑽孔1500萬內的塊被歸類爲指示礦產資源。所有其他估算的塊被歸類爲推斷礦產資源。
For the Tailings, blocks within 30 m of three or more auger or core drill holes were classified as Measured Mineral Resources. Blocks within 60 m of two or more auger/drill holes/pits or trenches were classified as Indicated Mineral Resources. All additional estimated blocks were classified as Inferred Mineral Resources.
對於尾礦,距離三個或更多中和周或岩心鑽孔3000萬內的塊被歸類爲測量礦產資源。距離兩個或更多中和周/鑽孔/坑或槽6000萬內的塊被歸類爲指示礦產資源。所有其他估算的塊被歸類爲推斷礦產資源。
P&E considers that the block model Mineral Resource Estimates and Mineral Resource classification represent a reasonable estimation of the global mineral resources for the El Tigre Project with regard to compliance with generally accepted industry standards and guidelines, the methodology used for estimation, the classification criteria used and the actual implementation of the methodology in terms of Mineral Resource estimation and reporting. The Mineral Resources have been estimated in conformity with the requirements of the CIM "Estimation of Mineral Resource and Mineral Reserves Best Practices" guidelines as required by the Canadian Securities Administrators' National Instrument 43-101. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.
P&E認爲,塊模型礦產資源估算和礦產資源分類對於遵守普遍公認的行業標準和指導方針,估算方法,分類標準和實際估算方法等方面,合理估計了El Tigre項目的全球礦產資源。礦產資源估算符合加拿大證券管理局根據CIm「礦產資源和礦產儲量估算最佳實踐」指南的要求。礦產資源不是礦藏,尚未證明經濟可行性。
Table 6: AuEq Cut-off Sensitivities - ET Pit-Constrained Mineral Resource
表6:AuEq截斷靈敏度 - Et Pit限制的礦產資源
Table 7: AuEq Cut-off Sensitivities - ET Out-of-Pit Mineral Resource
表7:AuEq截斷靈敏度 - Et採場外的礦產資源
Exploration Potential
Exploration potential at the El Tigre Project is substantial with prospective areas for exploration both down dip and along strike with the disclosed Exploration Target establishing 10 to 12 million tonnes at 225 to 265 g/t AgEq for 73 to 100 Moz AgEq.
勘探潛力
El Tigre項目的勘探潛力巨大,有望的勘探區域既沿着傾斜面延伸,又沿着走向延伸,揭露的勘探目標確立爲10至1200萬噸,銀當量225至265克/噸,爲73至100百萬盎司銀當量。
Figure 3-Exploration Potential released October 2024
圖3-2024年10月發佈的勘探潛力
Surface Rights Agreement
The Company owns royalty-free, 100% of the 6,238 hectares land-package encompassing the footprint of proposed mining operation with no Ejido presence. In addition, the Company controls 28,414 hectares of Concessions to conduct exploration along a 25 km strike length of the Sierra Madres.
地面權利協議
公司擁有無產權稅、佔據了佔地6238公頃的土地包,涵蓋了擬議採礦控件的範圍,沒有Ejido(集體農莊)的存在。此外,公司控制了28414公頃的特許權,以沿着西拉馬德雷斯群山25公里走向進行勘探。
Underground Preliminary Economic Assessment
The Company will also continue to work on this substantial, permitted underground Mineral Resource Estimate and advance this towards a Preliminary Economic Assessment by H1-2025. The Measured and Indicated Out-of-Pit Mineral Resource at El Tigre is 44 Moz AgEq grading 255 g/t AgEq contained in 5.3 Mt and the Inferred Mineral Resource is 70 Moz AgEq grading 216 g/t AgEq contained in 10.1 Mt.
地下初步經濟評估
該公司還將繼續致力於這個重要的、經許可的地下礦產資源評估,並將其推進至2025年上半年的初步經濟評估。 El Tigre礦區的測量和指示類外露礦產資源爲44 Moz AgEq,品位爲255克/噸AgEq,含量爲5.3百萬噸,推斷礦產資源爲70 Moz AgEq,品位爲216克/噸AgEq,含量爲10.1百萬噸。
Qualified Persons
Mineral Resource Estimate: Dave Duncan P. Geo. VP Exploration of Silver Tiger, Charles Spath P.Geo., VP of Technical Services of Silver Tiger, and Fred Brown, P.Geo RM-SME Senior Associate Geologist of P&E Mining Consultants, and Eugene Puritch, P.Eng., FEC, CET, President of P&E Mining Consultants are the Qualified Persons as defined under National Instrument 43-101. All Qualified Persons have reviewed and approved the scientific and technical information in this press release.
合格人員
礦產資源評估:Silver Tiger公司的VP Exploration Dave Duncan P. Geo.,Silver Tiger公司的技術服務VP Charles Spath P.Geo.,P&E礦業顧問公司的Rm-SME高級助理地質學家Fred Brown, P.Geo以及P&E礦業顧問公司的總裁Eugene Puritch, P.Eng., FEC, CEt,均符合《43-101號全國工具定義的有資格人員》的定義。所有有資格人員已經審查並批准了本新聞稿中的科學技術信息。
Preliminary Feasibility Study: Andrew Bradfield P. Eng of P&E Mining Consultants, Eugene Puritch, P.Eng., FEC, CET, President of P&E Mining Consultants and David J. Salari, P. Eng. of D.E.N.M. Engineering Ltd are the Qualified Persons as defined under National Instrument 43-101. All Qualified Persons have reviewed and approved the scientific and technical information in this press release.
初步可行性研究:P&E礦業顧問公司的Andrew Bradfield P. Eng,P&E礦業顧問公司的總裁Eugene Puritch, P.Eng., FEC, CEt以及D.E.N.m. Engineering Ltd的David J. Salari, P. Eng.,均符合《43-101號全國工具定義的有資格人員》的定義。所有有資格人員已經審查並批准了本新聞稿中的科學技術信息。
A Technical Report is being prepared on the Preliminary Feasibility Study in accordance with National Instrument 43-101 ("NI-43-101"), and will be available on the Company's website and SEDAR within 45 days of the date of this news release. The effective date of this Preliminary Feasibility Study is October 22, 2024.
根據《43-101號全國工具規定》,初步可行性研究的技術報告正在準備中,將在此新聞發佈日期後45天內在公司網站和SEDAR平台上提供。該初步可行性研究的生效日期爲2024年10月22日。
VRIFY Slide Deck and 3D Presentation - Silver Tiger's El Tigre Project
VRIFY is a platform being used by companies to communicate with investors using 360° virtual tours of remote mining assets, 3D models and interactive presentations. VRIFY can be accessed by website and with the VRIFY iOS and Android apps.
在VRIFY上訪問Silver Tiger Metals Inc.公司簡介:
VRIFY是一種平台,公司使用360°虛擬觀看遠程採礦資產,3D模型和交互式演示與投資者溝通。可以通過網站和VRIFY iOS和Android應用程序訪問VRIFY。
Access the Silver Tiger Metals Inc. Company Profile on VRIFY at:
在VRIFY上查看Silver Tiger Metals Inc.公司簡介:
The VRIFY Slide Deck and 3D Presentation for Silver Tiger Metals Inc. can be viewed at: and on the Corporation's website at: .
Silver Tiger Metals Inc.的VRIFY幻燈片和3D演示可以在該網站上查看:以及公司網站上:。
About Silver Tiger and the El Tigre Historic Mine District
Silver Tiger Metals Inc. is a Canadian company whose management has more than 25 years' experience discovering, financing and building large epithermal silver projects in Mexico. Silver Tiger's 100% owned 28,414 hectare Historic El Tigre Mining District is located in Sonora, Mexico. Principled environmental, social and governance practices are core priorities at Silver Tiger.
關於Silver Tiger和El Tigre歷史礦區
Silver Tiger Metals Inc.是一家加拿大公司,其管理層在墨西哥發現、融資和建造大型熱液銀礦項目方面擁有超過25年的經驗。Silver Tiger百分之百擁有的28,414公頃歷史悠久的El Tigre礦區位於墨西哥索諾拉州。環境、社會和治理方法是Silver Tiger的核心優先事項。
Silver Tiger Metals Inc.是一家加拿大公司,其管理團隊擁有超過25年的經驗,在墨西哥發現、融資和建設大型低溫熱泉白銀項目。Silver Tiger擁有100%持有的28414公頃的歷史El Tigre礦區位於墨西哥Sonora。Silver Tiger將環保、社會責任和治理實踐作爲核心優先事項。
The El Tigre historic mine district is located in Sonora, Mexico and lies at the northern end of the Sierra Madre silver and gold belt which hosts many epithermal silver and gold deposits, including Dolores, Santa Elena and Las Chispas at the northern end. In 1896, gold was first discovered on the property in the Gold Hill area and mining started with the Brown Shaft in 1903. The focus soon changed to mining high-grade silver veins in the area with production coming from 3 parallel veins the El Tigre Vein, the Seitz Kelley Vein and the Sooy Vein. Underground mining on the middle El Tigre Vein extended 1,450 metres along strike and was mined on 14 levels to a depth of approximately 450 metres. The Seitz Kelley Vein was mined along strike for 1 kilometre to a depth of approximately 200 metres. The Sooy Vein was only mined along strike for 250 metres to a depth of approximately 150 metres. Mining abruptly stopped on all 3 of these veins when the price of silver collapsed to less than 20¢ per ounce with the onset of the Great Depression. By the time the mine closed in 1930, it is reported to have produced a total of 353,000 ounces of gold and 67.4 million ounces of silver from 1.87 million tons (Craig, 2012). The average grade mined during this period was over 2 kilograms silver equivalent per ton.
El Tigre歷史礦區位於墨西哥Sonora,位於西拉馬德勒銀金帶的北端,這裏擁有許多低溫熱泉白銀和金礦牀,包括Dolores、Santa Elena和Las Chispas等。1896年,Gold Hill地區首次發現金礦,1903年開始在Brown Shaft進行採礦。很快重點轉移到開採該地區的高品位銀礦脈,產量來自3條並行脈帶:El Tigre脈帶、Seitz Kelley脈帶和Sooy脈帶。沿着中El Tigre脈帶進行地下開採,沿着走向延伸1450米,開採至約450米深的14層級。Seitz Kelley脈帶沿走向開採1公里深,深約200米。Sooy脈帶只沿走向開採250米深,深約150米。隨着白銀價格下跌至不到20¢每盎司,隨着大蕭條的來臨,這3條脈帶的採礦工作突然中止。到1930年礦井關閉時,據稱共生產了353,000盎司黃金和6740萬盎司白銀,採出187萬噸(Craig, 2012)。在這段時期,平均開採品位超過每噸2千克等銀。
For further information, please contact:
Glenn Jessome
President and CEO
902 492 0298
jessome@silvertigermetals.com
如需更多信息,請聯繫:
Glenn Jessome
總裁和首席執行官
902 492 0298
jessome@silvertigermetals.com
CAUTIONARY STATEMENT:
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.
警示聲明:
TSX創業公司交易所及其監管服務提供商(指TSX創業公司交易所政策中所定義的術語)均不對本新聞稿的充分性或準確性承擔責任。
This News Release includes certain "forward-looking statements". All statements other than statements of historical fact included in this release, including, without limitation, statements regarding potential mineralization, Mineral Resources and Reserves, the ability to convert Inferred Mineral Resources to Indicated Mineral Resources, the ability to complete future drilling programs and infill sampling, the ability to extend Mineral Resource blocks, the similarity of mineralization at El Tigre to Delores, Santa Elena and Chispas, exploration results, and future plans and objectives of Silver Tiger, are forward-looking statements that involve various risks and uncertainties. Forward-looking statements are frequently characterized by words such as "may", "is expected to", "anticipates", "estimates", "intends", "plans", "projection", "could", "vision", "goals", "objective" and "outlook" and other similar words. Although Silver Tiger believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, there can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from Silver Tiger's expectations include risks and uncertainties related to exploration, development, operations, commodity prices and global financial volatility, risk and uncertainties of operating in a foreign jurisdiction as well as additional risks described from time to time in the filings made by Silver Tiger with securities regulators.
本新聞發佈包括某些「前瞻性聲明」。除了本公告中包含的歷史事實聲明外,其他所有聲明,包括但不限於關於潛在礦化、礦產資源和儲量、將推論礦產資源轉化爲指示礦產資源的能力、完成未來鑽探項目和補充取樣的能力、延伸礦產資源區塊的能力、El Tigre礦化與Delores、Santa Elena和Chispas相似性、勘探結果、Silver Tiger未來計劃和目標等均爲涉及各種風險和不確定性的前瞻性聲明。前瞻性聲明經常以「可能」、「預計」、「預計」、「估計」、「打算」、「計劃」、「預測」、「可能」、「遠見」、「目標」、「目標」和「展望」等類似詞語來描述。儘管Silver Tiger相信此類前瞻性聲明中所表達的期望基於合理的假設,但無法保證此類聲明將被證明是準確的,實際結果和未來事件可能會與這些聲明中預期的結果有實質不同。可能導致實際結果與Silver Tiger預期有實質不同的重要因素包括與勘探、開發、運營、大宗商品價格和全球金融波動相關的風險和不確定性,以及在外國司法管轄區開展業務的風險和不確定性,還有Silver Tiger向證券監管機構提出的文件中不時描述的其他風險。
SOURCE: Silver Tiger Metals Inc.
資料來源:Silver Tiger Metals Inc.
譯文內容由第三人軟體翻譯。