share_log

Sego Exploration Target Review of South Gold Zone "At and Near Surface" Potential Tonnage & Grade

Sego Exploration Target Review of South Gold Zone "At and Near Surface" Potential Tonnage & Grade

Sego探礦目標評估黃金南部區域"地表及附近"潛在噸位&品位
newsfile ·  09/24 22:17

Vancouver, British Columbia--(Newsfile Corp. - September 24, 2024) - Sego Resources Inc. (TSXV: SGZ) ("Sego" or "the Company") is pleased to announce that it has received from SRK Consulting (Canada) Inc. ("SRK"), an Exploration Target Review on the South Gold Zone at its Miner Mountain Project including recommended additional infill drilling.

溫哥華,不列顛哥倫比亞省--(新聞發佈 - 2024年9月24日) - Sego Resources Inc. (tsxv: SGZ)("Sego"或"該公司")高興地宣佈,已收到SRk諮詢(加拿大)公司(「SRK」)關於其Miner Mountain項目南黃金區的勘探靶向審查,包括推薦的額外填充鑽探。


Figure 1: 3-D View of the Litho-structural and Mineralization Models of the South Gold Zone
Source: SRK, 2024


圖1:南黃金區岩石結構和礦化模型的三維視圖
來源:SRk,2024年

DISCLOSURE WARNINGS IN RESPECT TO AN EXPL0RATION TARGET REVIEW

關於勘探目標審核的披露警告

- An exploration target is not a NI 43-101 compliant resource or reserve.
- The South Gold Zone is confirmed only as a target for further exploration.
- Potential quantity and grades are conceptual in nature only.
- There has not been sufficient exploration to define any mineral resource.
- There is no certainty that further exploration will result in the target being delineated as a Mineral Resource.
- The assessment of the target for further exploration was completed by SRK Consulting ("SRK"), a consultant independent of the Company. The estimation of the potential quantity and grade of the exploration target was based on a drillhole database of 22 diamond core holes and 1,545 gold assay data. With the available drilling information, SRK developed conceptual gold mineralization volumes, constrained by interpreted lithological and structural models. The original core samples were composited, and the composited gold assays were capped after evaluating the statistical distributions on probability plots. The gold values were interpolated into a three-dimensional block model using Inverse Distance to a power of three. To estimate a tonnage, an average specific gravity of 2.7 was considered.

- 勘探目標不是符合NI 43-101標準的資源或儲備。
- 南黃金區僅確認爲進一步勘探的目標。
- 潛在數量和品位僅具有概念性質。
- 尚未進行足夠的勘探以定義任何礦產資源。
- 無法確定進一步勘探是否會將目標界定爲涉礦概念。
- 對進一步勘探的目標進行評估是由獨立於公司的顧問SRk諮詢公司(「SRK」)完成的。對勘探目標潛在數量和品位的估計基於22個金剛石岩心鑽孔和1,545個黃金化驗數據的鑽孔數據庫。根據可用的鑽探信息,SRk開發了概念性的金礦化體積,受解釋的巖性和構造模型的約束。原始岩心樣品被合併,合併後的金化驗經過概率圖上的統計分佈評估後進行上限處理。金值被插值到一個使用三次方反距離法的三維塊模型中。爲了估算噸位,考慮了平均比重爲2.7。

HIGHLIGHTS

亮點

- An estimated total of 5,000,000 to 8,000,000 tonnes of mineralization of between 0.5 to 0.7 grams per tonne of gold in the South Gold Zone.

- 在南部金域,估計的礦化總量爲5,000,000至8,000,000噸,金品位在0.5至0.7克/噸之間。

- The South Gold Zone may contain 100,000 to 150,000 ounces of gold.

- 南部金域可能含有100,000至150,000盎司的黃金。

- The SRK Study also proposed drill hole locations to firstly provide infill drilling, secondly test structural features and thirdly potentially increase the size of the exploration target.

- SRk研究還提議鑽孔位置,首先提供填充鑽探,其次測試構造特徵,第三可能增加勘探目標的規模。

This study is an integrated litho-structural model of the South Gold Zone, which covers the conceptual target and a second conceptual target to the immediate north, with the aim of facilitating future targeting and drill hole planning.

這項研究是南部金域的綜合巖構造模型,涵蓋了概念目標和緊鄰北部的第二概念目標,旨在促進未來定位和鑽孔規劃。


Figure 2: 3D and Sectional (Inset) Views of the South Gold Zone Block Model
Source: SRK, 2024


圖2:南部金域塊模型的三維和截面(插圖)視圖
來源:SRk,2024年

NEXT STEPS

即將開展的工作。

- Complete the SRK recommended drilling.

- 完成SRk推薦的鑽探。

- Further drilling to test a copper-gold porphyry spatially related target immediately north of the South Gold Zone.

- 進一步鑽探,以測試銅-黃金斑岩空間相關目標,該目標位於南部黃金區域的北部。

Qualified Person

合格人士

The technical information in this news release, including the information that relates to geology, drilling and gold mineralization was prepared under the supervision of, or was reviewed by Souvik Banerjee, P.Geo, an independent Qualified Person as this term is defined in National Instrument 43-101.

這則新聞稿中的技術信息,包括與地質、鑽探和金礦化有關的信息,是在Souvik Banerjee,P.Geo的監督下編制的,或經過了他的審查,他是根據《43-101號國家規定書》中定義的獨立合格人員。

OTHER MATTERS

其他問題

The Board of Directors has granted directors, officers and consultants of the Company, 6,775,000 stock options exercisable at $0.08 until July 25, 2029. The options are subject to TSX Venture Exchange approval. The options will vest 25% on grant and 25% every 6 months thereafter.

董事會已授予公司的董事、高管和顧問6,775,000股票期權,行權價爲0.08美元,有效期至2029年7月25日。這些期權需獲得TSX Venture Exchange的批准。期權授予後,25%立即行使,之後每6個月行使25%。

ABOUT THE MINER MOUNTAIN PROJECT

關於Miner Mountain項目

Sego owns 100% of the Miner Mountain Project, an alkalic copper-gold porphyry exploration project located near Princeton, British Columbia. The property is 2,056 hectares in size and is 15 kilometres north of the Copper Mountain Mine operated by Hudbay Minerals Inc. Sego has a Memorandum of Understanding with the Upper Similkameen Indian Band on whose Traditional Territory the Miner Mountain Project is situated. Sego has received an Award of Excellence for its reclamation work at Miner Mountain.

Sego擁有Miner Mountain項目的100%,這是位於不列顛哥倫比亞省普林斯頓附近的一項含鹼性銅金斑岩勘探項目。該物業佔地2,056公頃,位於Hudbay Minerals Inc.經營的Copper Mountain銅礦北部15公里處。Sego與上西米爾卡明印第安部落達成諒解備忘錄,Miner Mountain項目位於其傳統領土上。Sego因在Miner Mountain項目的復墾工作獲得卓越獎。

For further information please contact:
J. Paul Stevenson, CEO (604) 682-2933

要了解更多信息,請聯繫:
J. Paul Stevenson,首席執行官(604)682-2933

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. No regulatory authority has approved or disapproved the information contained in this news release.

TSX創業公司交易所及其監管服務提供商(如其在TSX創業公司規則中所定義)對本公告的充分性或準確性不承擔責任。任何監管機構都未批准或不批准本資訊稿中包含的信息。

This release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statement of historical facts that address future production, reserve potential, exploration drilling, exploitation activities and events or developments that the Company expects are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, statements are not guarantees of future performance and actual results or developments may differ materially from the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation and exploration successes, continued availability of capital and financing, general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements.

本公告包含可能被視爲「前瞻性聲明」的某些聲明。本公告中的所有聲明,除了涉及未來生產、儲量潛力、勘探鑽探、開發活動、以及公司預期的事件或事態的歷史事實陳述外,均屬前瞻性聲明。儘管公司認爲這些前瞻性聲明表述的期望是基於合理假設的,但這些聲明不是對未來業績的保證,實際結果或發展可能與前瞻性聲明有實質性差異。導致實際結果與前瞻性聲明存在實質性差異的因素包括市場價格、開採和勘探成功、資本和融資的持續可用性、一般經濟、市場或商業狀況。投資者應當注意,任何此類聲明都不構成對未來業績的保證,實際結果或發展可能與前瞻性聲明中所預期的有實質性差異。

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論