Saguenay, Quebec--(Newsfile Corp. - May 14, 2024) - First Phosphate Corp. (CSE: PHOS) (OTC: FRSPF) (FSE: KD0) ("First Phosphate" or the "Company") is pleased to report results from another 29 drill holes at its Bégin-Lamarche project located in Saguenay-Lac-St-Jean, Quebec, Canada. The Company's 25,929 m drill program was completed ahead of schedule on April 29, 2024. To date, 4,557 assays have been received representing 16,468 m of drilling. A remaining 1,775 assays are expected to be delivered by the end of May.

魁北克薩格奈--(Newsfile Corp.,2024年5月14日)——第一磷酸鹽公司(CSE:PHOS)(場外交易代碼:FRSPF)(FSE:KD0)(”第一磷酸鹽“或者”公司“)很高興地報告其位於加拿大魁北克省薩格奈-聖讓湖的Begin-Lamarche項目又有29個鑽孔的結果。該公司的25,929米鑽探計劃已於2024年4月29日提前完成。迄今爲止,已經收到了4,557份化驗報告,相當於16,468米的鑽探。剩餘的1,775份化驗結果預計將在5月底之前交付。

Highlights:

亮點:

  • Phosphate Mountain Zone:
  • 磷酸鹽山區:
    • Drill hole BL-24-67 intersected 11.85% P2O5 (phosphate) over 84.0 m starting at a surface depth of 3.0 m. Drilling in the Phosphate Mountain Zone revealed a thick 90 m layer of phosphate bearing nelsonite rock outcropping at surface with numerous other high grade intersects grading at over 10% P2O5.

    • Drill hole BL-24-82 returned a sub-intersection of 20.51% P2O5 over 9.75 m within a 77.7 phosphate intersect grading at 11.07% P2O5. This sub-section also contains a 2.1 m massive apatite vein that returned 30.73% P2O5.

  • Southern Zone:
    • 鑽孔 BL-24-67 與 11.85% P 相交2O5 (磷酸鹽)超過 84.0 米,表面深度爲 3.0 米。在磷酸鹽山區的鑽探顯示,地表露出了一層 90 米厚的含磷酸鹽尼爾森岩石,還有許多其他高品位交叉點的品位超過 10% P2O5

    • 鑽孔 BL-24-82 返回了 20.51% P 的子交叉點2O5 在 77.7 的磷酸鹽交叉點內超過 9.75 m,坡度爲 11.07%2O5。該子部分還包含一個 2.1 m 的巨大磷灰石礦脈,其返回 30.73% P2O5

  • 南部區域:
    • Drill hole BL-24-60 intersected 5.21% P2O5 over 194.0 m from a surface depth of 4.0 m and drill hole BL-24-83 intersected 5.81% P2O5 over 216.1 m starting at surface.

    • Drilling revealed many phosphate layers over 10% P2O5 at he base of the main phosphate layer.

    • Drill hole BL-24-84 intersected 8.41% P2O5 over 77.1 m starting at 6.0 m. Results demonstrate that high grade phosphate layers also occur in the Southern Zone.

    • 鑽孔 BL-24-60 與 5.21% P 相交2O5 從 4.0 m 的表面深度超過 194.0 m,鑽孔 BL-24-83 與 5.81% P 的相交2O5 從水面起點超過 216.1 米。

    • 鑽探發現許多磷酸鹽層超過 10% P2O5 在主要磷酸鹽層的底部。

    • 鑽孔 BL-24-84 與 8.41% P 相交2O5 從 6.0 m 開始超過 77.1 m。結果表明,南部地區也存在高品位的磷酸鹽層。

"We are pleased with the continued high grade phosphate results encountered across the 3 km strike zone at our Bégin-Lamarche project," said First Phosphate CEO, John Passalacqua. "The drill program is now completed and we begin preparations for a 43-101 resource estimate followed immediately by a Preliminary Economic Assessment ("PEA")."

第一磷酸鹽首席執行官約翰·帕薩拉誇說:“我們對我們的Begin-Lamarche項目在3公里長的打擊區內持續獲得高品位的磷酸鹽結果感到滿意。”“鑽探計劃現已完成,我們開始爲43-101的資源估算做準備,隨後立即進行初步經濟評估(“PEA”)。”

Phosphate Mountain Zone

磷酸鹽山區

A total of 23 drill holes have been completed to date in the Phosphate Mountain Zone while results from 14 drill holes have been received to date. Data received from these 14 drill holes shows grades of over 10% P2O5 over widths ranging from 7 m to 92 m. The Phosphate Mountain Zone has been drilled for a total length of 250 m to date. This zone is beginning to merge (from the southeast) with the Northern Zone where a 500 m thick phosphate mineralized envelope exists, one which has delineated up to 5 individual layers ranging from 60 m to 100 m in thickness starting at surface and continuing down to a depth of 300 m. The overall strike length of the Phosphate Mountain Zone and the Northern Zone is approximately 600 m.

迄今爲止,磷酸鹽山區共完成了23個鑽孔,而迄今爲止,已經收到了14個鑽孔的結果。從這 14 個鑽孔收到的數據顯示 P 的品位超過 10%2O5 寬度從 7 米到 92 米不等。迄今爲止,磷酸鹽山區的鑽探總長度爲 250 米。該區域已開始(從東南方向開始)與北部地區合併,那裏存在厚度爲500米的磷酸鹽礦化包層,該包膜從地表開始,一直延伸到300米,深度爲300米。磷酸鹽山區和北區的總走向長度約爲600米。

Drill hole BL-24-67 intersected 11.85% P2O5 (phosphate) over 84.0 m starting at a surface depth of 3.0 m. Drilling in the Phosphate Mountain Zone revealed a thick 90 m layer of phosphate bearing nelsonite rock outcropping at surface with numerous other high grade intercepts grading at over 10% P2O5. Drill hole BL-24-82 returned a sub-intersection of 20.51% P2O5 over 9.75 m within a 77.7 phosphate intersection grading at 11.07% P2O5. This sub-section contains a 2.1 m massive apatite vein that returned 30.73% P2O5. (See Table 1).

鑽孔 BL-24-67 與 11.85% P 相交2O5 (磷酸鹽)起始深度爲3.0米,表面深度超過84.0米。在磷酸鹽山區的鑽探顯示,地表露出了一層厚厚的含磷酸鹽的尼爾森石岩層,還有許多其他高品位截距的P2O5品位超過10%。鑽孔 BL-24-82 返回了 20.51% P 的子交叉點2O5 在 77.7 的磷酸鹽交叉點內超過 9.75 米,坡度爲 11.07%2O5。該分段包含 2.1 m 的巨大磷灰石礦脈,返回 30.73% P2O5。(參見表 1)。

Table 1 - Drill Results for the Phosphate Mountain Zone

表 1-磷酸鹽山區的鑽探結果

Hole From (m) To (m) Length1 (m) P2O5 (%) TiO2 (%) Fe2O3T (%)
BL-24-59 6.55 59.4 52.85 12.44 5.65 33.60
BL-24-59 71.0 88.0 17.0 10.68 4.58 23.33
BL-24-59 123.0 145.0 22.0 11.61 2.52 20.20
including 132.0 145.0 13.0 16.45 2.56 21.18
BL-24-59 150.35 166.4 16.05 7.98 1.13 11.13
BL-24-62 3.8 48.0 44.2 11.37 4.65 22.77
BL-24-62 69.0 144.65 75.65 9.97 3.66 20.71
including 69.0 128.3 59.3 11.04 4.30 23.55
BL-24-62 156.0 160.0 4.0 14.40 4.90 26.34
BL-24-64 3.0 42.0 39.0 9.06 4.11 25.45
including 3.0 26.0 23.0 12.04 5.40 34.63
BL-24-64 75.0 126.5 51.5 7.20 2.64 16.44
including 102.0 120.9 18.9 10.67 4.13 20.59
BL-24-67 3.00 87.0 84.0 11.85 5.09 32.49
BL-24-67 117.0 152.0 35.0 9.86 3.22 18.88
including 117.0 143.0 26.0 11.85 3.95 22.03
BL-24-69 2.4 10.43 8.03 13.81 5.07 31.14
BL-24-69 28.0 65.1 37.1 9.55 3.17 21.76
including 28.0 39.75 11.75 16.70 6.20 32.09
BL-24-74 11.5 21.4 9.9 9.81 3.65 22.68
48.0 57.0 9.0 6.25 2.96 16.14
82.0 102.3 20.3 10.30 4.28 19.01
66.8 102.3 35.6 8.78 3.49 16.44
BL-24-76 49.0 64.25 15.3 11.27 4.40 24.29
BL-24-78 50.55 62.1 11.55 11.88 4.90 29.82
including 47.55 102.7 55.15 8.72 3.18 19.87
including 82.4 102.7 20.3 10.04 3.53 19.32
BL-24-82 6.0 83.7 77.7 11.07 3.28 18.63
including 6.0 36.0 30.0 13.21 4.82 24.31
including 54.0 63.75 9.75 20.51 3.87 16.59
BL-24-82 102.0 119.1 17.1 9.96 2.78 14.97
從 (m) 到 (m) 長度1 (m) P2O5 (%) TiO2 (%) 2O3T (%)
BL-24-59 6.55 59.4 52.85 12.44 5.65 33.60
BL-24-59 71.0 88.0 17.0 10.68 4.58 23.33
BL-24-59 123.0 145.0 22.0 11.61 2.52 20.20
包括 132.0 145.0 13.0 16.45 2.56 21.18
BL-24-59 150.35 166.4 16.05 7.98 1.13 11.13
BL-24-62 3.8 48.0 44.2 11.37 4.65 22.77
BL-24-62 69.0 144.65 75.65 9.97 3.66 20.71
包括 69.0 128.3 59.3 11.04 4.30 23.55
BL-24-62 156.0 160.0 4.0 14.40 4.90 26.34
BL-24-64 3.0 42.0 39.0 9.06 4.11 25.45
包括 3.0 26.0 23.0 12.04 5.40 34.63
BL-24-64 75.0 126.5 51.5 7.20 2.64 16.44
包括 102.0 120.9 18.9 10.67 4.13 20.59
BL-24-67 3.00 87.0 84.0 11.85 5.09 32.49
BL-24-67 117.0 152.0 35.0 9.86 3.22 18.88
包括 117.0 143.0 26.0 11.85 3.95 22.03
BL-24-69 2.4 10.43 8.03 13.81 5.07 31.14
BL-24-69 28.0 65.1 37.1 9.55 3.17 21.76
包括 28.0 39.75 11.75 16.70 6.20 32.09
BL-24-74 11.5 21.4 9.9 9.81 3.65 22.68
48.0 57.0 9.0 6.25 2.96 16.14
82.0 102.3 20.3 10.30 4.28 19.01
66.8 102.3 35.6 8.78 3.49 16.44
BL-24-76 49.0 64.25 15.3 11.27 4.40 24.29
BL-24-78 50.55 62.1 11.55 11.88 4.90 29.82
包括 47.55 102.7 55.15 8.72 3.18 19.87
包括 82.4 102.7 20.3 10.04 3.53 19.32
BL-24-82 6.0 83.7 77.7 11.07 3.28 18.63
包括 6.0 36.0 30.0 13.21 4.82 24.31
包括 54.0 63.75 9.75 20.51 3.87 16.59
BL-24-82 102.0 119.1 17.1 9.96 2.78 14.97

1 Lengths are measured along the core. True widths are estimated to be between 70 and 90% of the core interval.

1 長度是沿着核心測量的。實際寬度估計在覈心間隔的70%至90%之間。

Southern Zone

南部區域

The Southern Zone has been drilled at 100 m spaced sections over a strike length of 1,600 m. Results to date from the Southern Zone show continuous widths of over 100 m of phosphate mineralization. Drill hole BL-24-60 intersected 5.21% P2O5 over 194.0 m from a surface depth of 4.0 m and drill hole BL-24-83 intersected 5.81% P2O5 over 216.1 m from surface. Drilling also revealed many phosphate layers over 10% P2O5 at he base of the main phosphate layer. Drill hole BL-24-84 intersected 8.41% P2O5 over 77.1 m. Results demonstrate that high grade phosphate layers also occur in the Southern Zone.

南區已在間隔100米的部分鑽探,鑽探長度爲1,600 m。迄今爲止,南部區域的結果顯示,磷酸鹽礦化的連續寬度超過100 m。鑽孔 BL-24-60 與 5.21% P 相交2O5 從 4.0 m 的表面深度超過 194.0 m,鑽孔 BL-24-83 與 5.81% P 的相交2O5 距離地面超過 216.1 米。鑽探還發現了許多超過 10% P 的磷酸鹽層2O5 在主要磷酸鹽層的底部。鑽孔 BL-24-84 與 8.41% P 相交2O5 超過 77.1 m。結果表明,南部地區也存在高品位的磷酸鹽層。

Table 2 - Drill Results for the Southern Zone

表 2-南部地區的鑽探結果

Hole From (m) To (m) Length1 (m) P2O5 (%) TiO2 (%) Fe2O3T (%)
BL-24-58 81.0 144.0 63.00 4.02 3.46 18.82
including 81.0 102.0 21.00 7.09 4.50 25.47
176.55 185.7 9.15 9.55 4.72 26.28
195.0 212.4 17.40 6.51 3.88 18.85
including 206.3 212.4 6.10 11.96 5.01 26.27
BL-24-60 3.7 197.7 194.00 5.21 3.81 22.50
BL-24-61 No significant results
BL-24-63 37.7 297.0 259.3 5.21 3.80 21.65
including 37.7 60.0 22.3 8.02 5.07 30.02
including 240.0 285.0 45.0 7.57 4.54 26.60
BL-24-65 12.5 19.5 7.0 4.27 3.09 17.72
49.2 63.3 14.1 9.44 5.19 30.12
144.7 162.5 17.8 10.37 5.40 31.00
223.4 235.4 12.0 11.61 5.61 28.72
BL-24-66 6.0 97.0 91.0 5.35 4.43 26.85
BL-24-68 13.0 46.65 33.65 5.64 4.02 22.83
81.8 92.0 10.20 3.92 3.90 17.92
BL-24-70 73.6 148.0 74.40 4.27 3.49 20.55
BL-24-71 73.3 174.9 101.6 4.76 3.52 19.60
193.5 238.2 44.7 6.52 4.98 26.00
261.0 272.0 11.0 6.27 4.42 24.32
292.7 304.0 11.3 7.75 3.85 30.68
BL-24-72 196.0 305.0 109.0 4.72 3.70 21.26
including 278.35 305.0 26.65 7.46 5.29 27.45
BL-24-73 154.0 180.5 26.5 5.43 4.07 23.85
195.2 366.0 170.8 5.23 4.13 22.38
including 309.0 366.0 57.0 7.07 5.15 27.34
BL-24-75 118.2 135.0 16.8 6.01 4.34 26.65
BL-24-75 208.5 219.4 10.9 6.32 4.15 29.74
BL-24-77 174.0 360.0 186.0 4.53 3.23 19.64
including 2.4 288.0 114.0 5.39 3.63 21.54
BL-24-79 No significant results
BL-24-80 2.4 74.55 72.15 6.59 2.37 16.23
including 2.4 12.55 10.15 9.35 4.25 27.10
including 25.25 52.5 27.25 10.27 3.24 19.77
BL-24-81 190.15 265.3 75.15 5.05 3.61 20.30
285.0 291.0 6.00 8.44 4.93 27.02
BL-24-83 5.0 216.6 211.6 5.81 3.52 24.00
including 46.5 61.45 14.95 11.37 4.99 35.52
including 117.0 157.3 40.3 8.49 4.66 32.83
BL-24-83 287.2 313 25.8 6.53 5.38 28.50
BL-24-84 177.85 193.55 15.7 7.46 3.69 22.45
205.9 283.0 77.1 8.41 4.14 22.75
BL-24-86 9.3 44.55 35.25 6.24 4.46 23.61
102.6 116.85 14.25 5.50 3.66 19.90
168.0 189.2 21.2 6.33 3.21 18.89
BL-24-87 173.6 198.0 24.4 7.12 5.57 28.79
從 (m) 到 (m) 長度1 (m) P2O5 (%) TiO2 (%) 2O3T (%)
BL-24-58 81.0 144.0 63.00 4.02 3.46 18.82
包括 81.0 102.0 21.00 7.09 4.50 25.47
176.55 185.7 9.15 9.55 4.72 26.28
195.0 212.4 17.40 6.51 3.88 18.85
包括 206.3 212.4 6.10 11.96 5.01 26.27
BL-24-60 3.7 197.7 194.00 5.21 3.81 22.50
BL-24-61 沒有顯著的結果
BL-24-63 37.7 297.0 259.3 5.21 3.80 21.65
包括 37.7 60.0 22.3 8.02 5.07 30.02
包括 240.0 285.0 45.0 7.57 4.54 26.60
BL-24-65 12.5 19.5 7.0 4.27 3.09 17.72
49.2 63.3 14.1 9.44 5.19 30.12
144.7 162.5 17.8 10.37 5.40 31.00
2234 235.4 12.0 11.61 5.61 28.72
BL-24-66 6.0 97.0 91.0 5.35 4.43 26.85
BL-24-68 13.0 46.65 33.65 5.64 4.02 22.83
81.8 92.0 10.20 3.92 3.90 17.92
BL-24-70 73.6 148.0 74.40 4.27 3.49 20.55
BL-24-71 73.3 174.9 101.6 4.76 3.52 19.60
193.5 238.2 44.7 6.52 4.98 26.00
261.0 272.0 11.0 6.27 4.42 24.32
292.7 304.0 11.3 7.75 3.85 30.68
BL-24-72 196.0 305.0 109.0 4.72 3.70 21.26
包括 278.35 305.0 26.65 7.46 5.29 27.45
BL-24-73 154.0 180.5 26.5 5.43 4.07 23.85
195.2 366.0 170.8 5.23 4.13 22.38
包括 309.0 366.0 57.0 7.07 5.15 27.34
BL-24-75 118.2 135.0 16.8 6.01 4.34 26.65
BL-24-75 208.5 219.4 10.9 6.32 4.15 29.74
BL-24-77 174.0 360.0 186.0 4.53 3.23 19.64
包括 2.4 288.0 114.0 5.39 3.63 21.54
BL-24-79 沒有顯著的結果
BL-24-80 2.4 74.55 72.15 6.59 2.37 16.23
包括 2.4 12.55 10.15 9.35 4.25 27.10
包括 25.25 52.5 27.25 10.27 3.24 19.77
BL-24-81 190.15 265.3 75.15 5.05 3.61 20.30
285.0 291.0 6.00 8.44 4.93 27.02
BL-24-83 5.0 216.6 211.6 5.81 3.52 24.00
包括 46.5 61.45 14.95 11.37 4.99 35.52
包括 117.0 157.3 40.3 8.49 4.66 32.83
BL-24-83 287.2 313 25.8 6.53 5.38 28.50
BL-24-84 177.85 193.55 15.7 7.46 3.69 22.45
205.9 283.0 77.1 8.41 4.14 22.75
BL-24-86 9.3 44.55 35.25 6.24 4.46 23.61
102.6 116.85 14.25 5.50 3.66 19.90
168.0 189.2 21.2 6.33 3.21 18.89
BL-24-87 173.6 198.0 24.4 7.12 5.57 28.79

1 Lengths are measured along the core. True width is estimated to be between 60% and 90% of the core interval.

1 長度是沿着核心測量的。實際寬度估計在覈心間隔的60%至90%之間。

The technical parameters of the drill holes being released in this press release are shown in Table 3 below and their location is shown in Figure 1 below. A summary of the mineralized intersections from the 2024 drilling program is presented in Table 4.

本新聞稿中發佈的鑽孔的技術參數如下表3所示,其位置如下圖1所示。表 4 概述了 2024 年鑽探計劃的礦化交叉點。

Table 3 - Parameters for the Current Drill Holes Being Released

表 3-當前發佈的鑽孔參數

Hole_ID Easting Northing Azimuth Dip Depth Zone
BL-24-58 326371 5403264 125 -45 228 Southern
BL-24-59 326899 5403859 150 -60 216 Mountain
BL-24-60 325894 5402244 305 -50 200.5 Southern
BL-24-61 326173 5403280 125 -45 312 Southern
BL-24-62 326922 5403891 150 -45 201 Mountain
BL-24-63 325866 5402145 305 -70 300 Southern
BL-24-64 326933 5403801 150 -45 180 Mountain
BL-24-65 325712 5402131 125 -45 285 Southern
BL-24-66 326281 5403201 125 -45 150 Southern
BL-24-67 326931 5403802 330 -45 161 Mountain
BL-24-68 326400 5403111 125 -45 126 Southern
BL-24-69 326894 5403856 0 -90 201 Mountain
BL-24-70 326345 5403160 125 -45 201 Southern
BL-24-71 325660 5402170 125 -45 354 Southern
BL-24-72 326228 5403145 125 -45 315 Southern
BL-24-73 325606 5402214 125 -45 375 Southern
BL-24-74 326960 5403846 150 -45 201 Mountain
BL-24-75 326126 5403222 130 -45 300 Southern
BL-24-76 326993 5403785 150 -45 175.5 Mountain
BL-24-77 325604 5402214 125 -60 366 Southern
BL-24-78 326993 5403785 330 -45 250 Mountain
BL-24-79 326126 5403222 130 -60 250 Southern
BL-24-80 326921 5403897 0 -90 213 Southern
BL-24-81 325560 5402121 125 -45 306 Southern
BL-24-82 326921 5403897 150 -67 201 Mountain
BL-24-83 326168 5403167 125 -45 327 Southern
BL-24-84 325615 5402080 125 -45 301.3 Southern
BL-24-86 325675 5402034 125 -45 293.5 Southern
BL-24-87 325655 5401926 305 -45 210 Southern
BL-24-88 326226 5403248 125 -45 366 Mountain
hole_ID 向東 北方 方位角 深度 區域
BL-24-58 326371 5403264 125 -45 228 南方
BL-24-59 326899 5403859 150 -60 216
BL-24-60 325894 5402244 305 -50 200.5 南方
BL-24-61 326173 5403280 125 -45 312 南方
BL-24-62 326922 5403891 150 -45 201
BL-24-63 325866 5402145 305 -70 300 南方
BL-24-64 326933 5403801 150 -45 180
BL-24-65 325712 5402131 125 -45 285 南方
BL-24-66 326281 5403201 125 -45 150 南方
BL-24-67 326931 5403802 330 -45 161
BL-24-68 326400 5403111 125 -45 126 南方
BL-24-69 326894 5403856 0 -90 201
BL-24-70 326345 5403160 125 -45 201 南方
BL-24-71 325660 5402170 125 -45 354 南方
BL-24-72 326228 5403145 125 -45 315 南方
BL-24-73 325606 5402214 125 -45 375 南方
BL-24-74 326960 5403846 150 -45 201
BL-24-75 326126 5403222 130 -45 300 南方
BL-24-76 326993 5403785 150 -45 175.5
BL-24-77 325604 5402214 125 -60 366 南方
BL-24-78 326993 5403785 330 -45 250
BL-24-79 326126 5403222 130 -60 250 南方
BL-24-80 326921 5403897 0 -90 213 南方
BL-24-81 325560 5402121 125 -45 306 南方
BL-24-82 326921 5403897 150 -67 201
BL-24-83 326168 5403167 125 -45 327 南方
BL-24-84 325615 5402080 125 -45 301.3 南方
BL-24-86 325675 5402034 125 -45 293.5 南方
BL-24-87 325655 5401926 305 -45 210 南方
BL-24-88 326226 5403248 125 -45 366

Table 4 - Other Previously Released Results for the 2024 Drill Campaign

表 4-先前公佈的 2024 年演習活動的其他結果

Hole_ID From (m) To (m) Length (m) P2O5 (%) TiO2 (%) Fe2O3T (%)
BL-24-22 195.00 259.50 64.50 5.80 2.94 21.04
BL-24-23 21.00 175.10 154.10 7.02 4.40 27.34
BL-24-24 61.30 190.90 129.60 5.22 3.63 22.32
BL-24-25 74.20 117.00 42.80 9.89 3.54 28.65
BL-24-26 6.90 96.00 89.10 9.44 3.92 27.59
BL-24-27 138.00 189.00 51.00 4.41 3.05 20.62
BL-24-28 73.25 152.20 78.95 5.48 4.07 24.68
BL-24-29 99.00 276.00 177.00 4.46 3.63 22.85
BL-24-30 33.00 78.65 45.65 4.28 2.97 19.83
BL-24-31 119.85 213.80 93.95 7.16 3.49 18.76
BL-24-32 159.00 228.00 69.00 5.51 3.82 24.60
BL-24-33 3.80 110.00 106.20 5.00 3.70 21.19
BL-24-34 93.00 192.00 99.00 6.34 2.74 20.09
BL-24-35 212.50 253.70 41.20 6.25 3.44 19.55
BL-24-36 234.0 342.0 108.0 6.83 4.33 28.34
BL-24-37 84.0 126.0 42.0 6.03 4.47 28.57
BL-24-39 102.0 150.0 48.0 5.51 2.20 16.64
BL-24-43 111.0 369.0 258.0 5.41 4.33 22.19
BL-24-44 192.4 283.0 90.6 7.48 3.38 23.64
BL-24-47 153.0 304.0 151.0 3.89 3.36 19.51
BL-24-48 32.0 39.65 7.65 15.01 2.59 19.17
BL-24-49 72.5 105.5 33.0 8.65 3.77 24.05
BL-24-50 4.2 93.0 88.8 5.90 4.14 23.62
BL-24-51 70.0 111.0 41.0 7.72 1.88 16.09
BL-24-52 204.0 247.7 43.7 7.04 3.62 24.50
BL-24-53 70.1 132.4 62.3 9.50 4.12 28.45
BL-24-53 154.1 246.0 91.9 6.92 3.50 20.08
BL-24-54 61.1 101.1 40.0 9.18 4.80 28.16
BL-24-55 4.0 194.8 190.8 4.60 3.64 19.83
BL-24-56 6.5 99 92.5 11.82 5.29 30.96
BL-24-56 123 162 39.0 8.43 3.18 17.56
BL-24-57 183.9 194.0 10.1 6.58 3.86 22.58
hole_ID 從 (m) 到 (m) 長度 (m) P2O5 (%) 二氧化鈦 (%) Fe2O3T (%)
BL-24-22 195.00 259.50 64.50 5.80 2.94 21.04
BL-24-23 21.00 175.10 154.10 7.02 4.40 27.34
BL-24-24 61.30 190.90 129.60 5.22 3.63 22.32
BL-24-25 74.20 117.00 42.80 9.89 3.54 28.65
BL-24-26 6.90 96.00 89.10 9.44 3.92 27.59
BL-24-27 138.00 189.00 51.00 4.41 3.05 20.62
BL-24-28 73.25 152.20 78.95 5.48 4.07 24.68
BL-24-29 99.00 276.00 177.00 4.46 3.63 22.85
BL-24-30 33.00 78.65 45.65 4.28 2.97 19.83
BL-24-31 119.85 213.80 93.95 7.16 3.49 18.76
BL-24-32 159.00 228.00 69.00 5.51 3.82 24.60
BL-24-33 3.80 110.00 106.20 5.00 3.70 21.19
BL-24-34 93.00 192.00 99.00 6.34 2.74 20.09
BL-24-35 212.50 253.70 41.20 6.25 3.44 19.55
BL-24-36 234.0 342.0 108.0 6.83 4.33 28.34
BL-24-37 84.0 126.0 42.0 6.03 4.47 28.57
BL-24-39 102.0 150.0 48.0 5.51 2.20 16.64
BL-24-43 111.0 369.0 258.0 5.41 4.33 22.19
BL-24-44 192.4 283.0 90.6 7.48 3.38 23.64
BL-24-47 153.0 304.0 151.0 3.89 3.36 19.51
BL-24-48 32.0 39.65 7.65 15.01 2.59 19.17
BL-24-49 72.5 105.5 33.0 8.65 3.77 24.05
BL-24-50 4.2 93.0 88.8 5.90 4.14 23.62
BL-24-51 70.0 111.0 41.0 7.72 1.88 16.09
BL-24-52 204.0 247.7 43.7 7.04 3.62 24.50
BL-24-53 70.1 132.4 62.3 9.50 4.12 28.45
BL-24-53 154.1 246.0 91.9 6.92 3.50 20.08
BL-24-54 61.1 101.1 40.0 9.18 4.80 28.16
BL-24-55 4.0 194.8 190.8 4.60 3.64 19.83
BL-24-56 6.5 99 92.5 11.82 5.29 30.96
BL-24-56 123 162 39.0 8.43 3.18 17.56
BL-24-57 183.9 194.0 10.1 6.58 3.86 22.58

Detailed results from the 2024 drill program are available at:

2024 年鑽探計劃的詳細結果可在以下網址獲得:

April 2, 2024:
March 19, 2024:
April 23, 2024:

2024 年 4 月 2 日:
2024 年 3 月 19 日:
2024 年 4 月 23 日:

Results for the earlier 4,661 m drill program conducted in 2023 can be found in the June 5, 2023 press release available at: .

早些時候在2023年進行的4,661米鑽探計劃的結果可以在2023年6月5日的新聞稿中找到,該新聞稿可在以下網址獲得:。

Quality Assurance / Quality Control

質量保證/質量控制

The sampling of, and assay data from, the drill core is monitored through the Company's implementation of a quality assurance - quality control (QA-QC) program designed to the CIM Mineral Exploration Best Practices Guidelines.

通過公司實施根據CIM礦產勘探最佳實踐指南設計的質量保證-質量控制(QA-QC)計劃,對鑽芯的採樣和化驗數據進行監測。

A formal chain-of-custody procedure was adopted for security of samples until their delivery at the laboratory. Drill core (NQ size) is logged and samples are selected by Laurentia Exploration Inc. geologists and sawn in half with a diamond saw at the project site. Half of the core is retained at the site for reference purposes. Sample intervals may vary from 0.5 to 3 metres in length depending on the geological observations. A blank and a standard are inserted at the beginning of each sample batch, usually one complete hole, and a blank and a standard are then inserted alternatively each 10 samples. Half-core samples are packaged and sent by ground transportation in sealed rice bags to an independent laboratory, Activation Laboratories Ltd. of Ancaster, Ontario (ISO/IEC 17025:2005 with CAN-P-1579). The core samples are crushed up to 80% passing 2mm (10 mesh), riffle split 250 g and pulverized (mild steel) to 95% passing -200 mesh. Each sample is analyzed for whole rock analysis (code 4B) for 10 major oxides and 7 trace elements by lithium metaborate/tetraborate fusion of 3g of material and analyze by ICP-OES. The laboratory has its own QA/QC protocols.

爲確保樣本在實驗室交付之前的安全,採用了正式的監管鏈程序。Laurentia Exploration Inc. 的地質學家會記錄鑽芯(NQ 尺寸)並選擇樣品,並在項目現場用金剛石鋸切成兩半。一半的核心保留在現場以供參考。根據地質觀測結果,採樣間隔的長度可能從0.5到3米不等。在每個樣品批次的開頭插入一個空白和一個標準品,通常是一個完整的孔,然後每10個樣品交替插入一個空白和一個標準。半核樣本被包裝並用密封的米袋通過地面運輸發送到安大略省安卡斯特的活化實驗室有限公司(使用 CAN-P-1579 的 ISO/IEC 17025:2005)。通過2毫米(10個網格),岩心樣品被壓碎至多80%,裂縫分裂250克,粉碎(低碳鋼)至95%,通過-200目篩選。通過3g材料的偏硼酸鋰/四硼酸鹽融合,對每個樣品進行全巖分析(代碼爲4B),分析10種主要氧化物和7種微量元素,並由ICP-OES進行分析。該實驗室有自己的質量保證/質量控制協議。

Qualified Person

合格人員

The scientific and technical disclosure for First Phosphate included in this news release has been reviewed and approved by Gilles Laverdière, P.Geo. Mr. Laverdière is Chief Geologist of First Phosphate and a Qualified Person under National Instrument 43-101 - Standards of Disclosure of Mineral Projects ("NI 43-101").

本新聞稿中包含的第一磷酸鹽的科學和技術披露已由P.Geo的Gilles Laverdieère審查和批准。Laverdieère 先生是 First Phosphate 的首席地質學家,也是 National Instrument 43-101 的合格人員- 礦業項目披露標準 (“NI 43-101”)。

About First Phosphate Corp.

關於第一磷酸鹽公司

First Phosphate is a mineral development company fully dedicated to extracting and purifying phosphate for the production of cathode active material for the Lithium Iron Phosphate ("LFP") battery industry. First Phosphate is committed to producing at high purity level, at full ESG standard and with low anticipated carbon footprint. First Phosphate plans to vertically integrate from mine source directly into the supply chains of major North American LFP battery producers that require battery grade LFP cathode active material emanating from a consistent and secure supply source. First Phosphate holds over 1,500 sq. km of royalty-free district-scale land claims in the Saguenay-Lac-St-Jean Region of Quebec, Canada that it is actively developing. First Phosphate properties consist of rare anorthosite igneous phosphate rock that generally yields high purity phosphate material devoid of high concentrations of harmful elements.

First Phosphate是一家礦物開發公司,致力於爲磷酸鐵鋰(“LFP”)電池行業生產正極活性物質的磷酸鹽,完全致力於提取和純化磷酸鹽。First Phosphate致力於生產高純度水平、完全符合ESG標準且預期碳足跡較低的產品。First Phosphate計劃將礦產直接垂直整合到北美主要LFP電池生產商的供應鏈中,這些生產商需要來自穩定和安全的供應來源的電池級LFP正極活性材料。First Phosphate在加拿大魁北克省薩格奈-聖讓湖地區擁有超過1,500平方公里的免版稅地區規模土地所有權,目前正在積極開發這些土地。首先,磷酸鹽特性由稀有的正長巖火成磷酸鹽岩組成,這些岩石通常會產生不含高濃度有害元素的高純度磷酸鹽材料。

-30-

-30-

For additional information, please contact:

欲了解更多信息,請聯繫:

Bennett Kurtz, CFO
bennett@firstphosphate.com
Tel: +1 (416) 200-0657

首席財務官 Bennett Kurtz
bennett@firstphosphate.com
電話:+1 (416) 200-0657

Investor Relations: investor@firstphosphate.com
Media Relations: media@firstphosphate.com
Website:

投資者關係:investor@firstphosphate.com
媒體關係:media@firstphosphate.com
網站:

Follow First Phosphate:

關注第一磷酸鹽:

Twitter:
LinkedIn:

推特:
領英:

Forward-Looking Information and Cautionary Statements

前瞻性信息和警示聲明

This news release contains certain statements and information that may be considered "forward-looking statements" and "forward-looking information" within the meaning of applicable securities laws. In some cases, but not necessarily in all cases, forward-looking statements and forward-looking information can be identified by the use of forward-looking terminology such as "plans", "targets", "expects" or "does not expect", "is expected", "an opportunity exists", "is positioned", "estimates", "intends", "assumes", "anticipates" or "does not anticipate" or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might", "will" or "will be taken", "occur" or "be achieved" and other similar expressions. In addition, statements in this news release that are not historical facts are forward-looking statements, including, among other things, the Company's planned exploration and production activities, the properties and composition of any extracted phosphate, the Company's plans for vertical integration into North American supply chains, statements relating to the Company's planned exploration activities, including its drill target strategy and next steps for the Bégin-Lamarche Property; and the Company's interpretations and expectations about the results on the Bégin-Lamarche Property.

本新聞稿包含某些陳述和信息,根據適用的證券法,這些陳述和信息可能被視爲 “前瞻性陳述” 和 “前瞻性信息”。在某些情況下,但不一定在所有情況下,前瞻性陳述和前瞻性信息可以通過使用前瞻性術語來識別,例如 “計劃”、“目標”、“預期” 或 “不期望”、“預期”、“機會存在”、“有定位”、“估計”、“打算”、“假設” 或 “不預期” 或 “相信”,或此類詞語和短語的變體或聲明 “可能”、“可能”、“將”、“可能”、“將” 或 “將採取”、“發生” 或 “實現” 等行動、事件或結果類似的表情。此外,本新聞稿中非歷史事實的陳述均爲前瞻性陳述,除其他外,包括公司計劃的勘探和生產活動、任何提取的磷酸鹽的特性和成分、公司縱向整合北美供應鏈的計劃、與公司計劃勘探活動(包括其鑽探目標戰略和Begin-Lamarche地產的下一步行動)有關的陳述;以及公司對結果的解釋和預期那個 Be`gin-Lamarche地產。

These statements and other forward-looking information are based on assumptions and estimates that the Company believes are appropriate and reasonable in the circumstances, including, without limitation, expectations of the Company's long term business outcomes given its short operating history; expectations regarding revenue, expenses and operations; the Company having sufficient working capital and ability to secure additional funding necessary for the exploration of the Company's property interests; expectations regarding the potential mineralization, geological merit and economic feasibility of the Company's projects; expectations regarding drill programs and the potential impacts successful drill programs could have on the life of the mine and the Company; mineral exploration and exploration program cost estimates; expectations regarding any environmental issues that may affect planned or future exploration programs and the potential impact of complying with existing and proposed environmental laws and regulations; receipt and timing of exploration and exploitation permits and other third-party approvals; government regulation of mineral exploration and development operations; expectations regarding any social or local community issues that may affect planned or future exploration and development programs; expectations surrounding global economic trends and technological advancements; and key personnel continuing their employment with the Company.

這些陳述和其他前瞻性信息基於公司認爲在當時情況下適當和合理的假設和估計,包括但不限於對公司長期業務成果的預期;對收入、支出和運營的預期;公司有足夠的營運資金和能力獲得勘探公司財產權益所需的額外資金;對潛在礦化的預期,公司項目的地質價值和經濟可行性;對鑽探計劃的預期以及成功的鑽探計劃可能對礦山和公司壽命產生的潛在影響;礦產勘探和勘探計劃成本估算;對可能影響計劃或未來勘探計劃的任何環境問題以及遵守現行和擬議環境法律法規的潛在影響的預期;勘探和開採許可證以及其他第三方批准的接收和時間;政府對礦產勘探和開發業務的監管;對可能影響計劃或未來勘探和開發計劃的任何社會或地方社區問題的預期;對全球經濟趨勢和技術進步的預期;以及繼續在公司工作的關鍵人員。

There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include: limited operating history; high risk of business failure; no profits or significant revenues; limited resources; negative cash flow from operations and dependence on third-party financing; the uncertainty of additional funding; no dividends; risks related to possible fluctuations in revenues and results; insurance and uninsured risks; litigation; reliance on management and key personnel; conflicts of interest; access to supplies and materials; dangers of mineral exploration and related liability and damages; risks relating to health and safety; government regulation and legal uncertainties; the company's exploration and development properties may not be successful and are highly speculative in nature; dependence on outside parties; title to some of the Company's mineral properties may be challenged or defective; Aboriginal title and land claims; obtaining and renewing licenses and permits; environmental and other regulatory risks may adversely affect the company; risks relating to climate change; risks related to infrastructure; land reclamation requirements may be burdensome; current global financial conditions; fluctuation in commodity prices; dilution; future sales by existing shareholders could cause the Company's share price to fall; fluctuation and volatility in stock exchange prices; and risks related to market demands. There can be no assurance that any opportunity will be successful, commercially viable, completed on time or on budget, or will generate any meaningful revenues, savings or earnings, as the case may be, for the Company. In addition, the Company will incur costs in pursuing any particular opportunity, which may be significant.

無法保證此類陳述會被證明是準確的,實際結果和未來事件可能與此類陳述中的預期存在重大差異。可能導致實際業績與公司預期存在重大差異的重要因素包括:運營歷史有限;業務失敗風險高;沒有利潤或可觀的收入;資源有限;運營產生的負現金流和對第三方融資的依賴;額外資金的不確定性;沒有分紅;與收入和業績可能波動相關的風險;保險和未投保風險;訴訟;對管理層和關鍵人員的依賴;利益衝突;供應和材料的獲取;危險礦產勘探及相關責任和損失;與健康和安全有關的風險;政府監管和法律的不確定性;公司的勘探和開發地產可能不成功,本質上具有高度投機性;對外部的依賴;公司某些礦產的所有權可能受到質疑或存在缺陷;原住民所有權和土地索賠;獲得和續訂執照和許可證;環境和其他監管風險可能對公司產生不利影響;與氣候變化有關的風險;與氣候變化相關的風險基礎設施;土地開墾要求可能很繁重;當前的全球金融狀況;大宗商品價格的波動;稀釋;現有股東未來的銷售可能導致公司股價下跌;證券交易所價格的波動和波動;以及與市場需求相關的風險。無法保證任何機會都會成功、商業上可行、按時或按預算完成,也無法保證會爲公司帶來任何有意義的收入、儲蓄或收益。此外,公司在追求任何特定機會時都會產生成本,這些成本可能很大。

These factors and assumptions are not intended to represent a complete list of the factors and assumptions that could affect the Company and, though they should be considered carefully, should be considered in conjunction with the risk factors described in the Company's other documents filed with the Canadian securities authorities, including without limitation the "Risk Factors" section of the Company's Annual Information Form dated November 29, 2023 which is available on SEDAR at . Although the Company has attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking information or information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. The Company does not undertake to update any forward-looking information, except in accordance with applicable securities laws.

這些因素和假設並非旨在代表可能影響公司的因素和假設的完整清單,儘管應仔細考慮,但應與公司向加拿大證券當局提交的其他文件中描述的風險因素一起考慮,包括但不限於2023年11月29日公司年度信息表中的 “風險因素” 部分,該部分可在SEDAR上查閱。儘管公司試圖確定可能導致實際行動、事件或結果與前瞻性信息或信息中披露的內容存在重大差異的因素,但可能還有其他因素導致行動、事件或結果不符合預期、估計或預期。除非根據適用的證券法,否則公司不承諾更新任何前瞻性信息。

譯文內容由第三人軟體翻譯。