newsfile ·  02/22 20:36

Toronto, Ontario--(Newsfile Corp. - February 22, 2024) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide an operations update for the Santana gold project outlining updated plans for expanding mining and processing operations over the next year.

安大略省多倫多--(Newsfile Corp.-2024 年 2 月 22 日)- Minera Alamos Inc.(多倫多證券交易所股票代碼:MAI)(“公司” 或 “Minera Alamos”) 很高興提供桑塔納黃金項目的最新運營情況,概述了明年擴大采礦和加工業務的最新計劃。

"Last year was challenging for both our operations and our shareholders. However, we are optimistic that 2024 will see significant positive advancements at the Santana gold mine," stated Darren Koningen, CEO. "A newly modelled approach to the development of Santana utilizing the existing leach pad capacity will allow mining and stacking operations to increase significantly from 2023 levels. We are currently finalizing plans for the year and concluding our discussions with our mining contractor to implement the new production plans. In parallel we will continue our active conversations regarding approval of our permit amendments covering the future development for the Santana mine."

“去年對我們的業務和股東來說都充滿挑戰。但是,我們樂觀地認爲,桑塔納金礦將在2024年取得重大積極進展。” 首席執行官達倫·科寧根說。“利用現有滲濾池產能開發桑塔納的新建模方法將使採礦和堆垛業務比2023年的水平大幅增加。我們目前正在敲定今年的計劃,並結束與採礦承包商的討論,以實施新的生產計劃。同時,我們將繼續就批准涵蓋桑塔納礦未來開發的許可證修正案進行積極對話。”

2024 Outlook

2024 年展望

In late 2023, the Minera operations team evaluated a series of operation scenarios aimed at balancing future planned leach pad expansion (awaiting permit amendments) against a shorter-term plan to expand mining and stacking activities using the current permitted pad space. Modelling results supported a plan of operations that can be conducted prior to any pad expansion required for longer term production plans. During 2023, the Company initiated some advanced development activities at the Nicho Main zone as preparation for the new plan of operations. This included:

2023年底,Minera運營團隊評估了一系列運營情景,旨在平衡未來計劃中的滲濾池擴建(等待許可證修訂)與使用當前允許的停機坪空間擴大采礦和堆疊活動的短期計劃。建模結果支持了一項運營計劃,該計劃可以在長期生產計劃所需的油田擴建之前進行。2023年,該公司在Nicho主區啓動了一些高級開發活動,爲新的運營計劃做準備。這包括:

  • Pioneering/pre-stripping of waste material within the proposed 2024 mining areas.
  • Blasting and crushing studies using material from the Nicho Main zone to determine any significant differences in the rock mechanical properties versus those for the Nicho Norte starter pit operations that were the focus of 2021-2023 mining.
  • 在擬議的2024年礦區內率先對廢物進行/預剝離。
  • 使用來自尼科主區的材料進行爆破和破碎研究,以確定岩石力學特性與作爲2021-2023年採礦重點的Nicho Norte起始礦坑作業的岩石力學特性是否存在任何顯著差異。

Approximately 20,000 oz of gold at an average grade of 0.63 g/t and an approximate strip ratio of 1.6:1 has now been defined for mining and loading over a 12-month schedule utilizing the current leach pad installed capacity. Included in the current plan are an additional 4,500 oz of higher grade (~1 g/t) mineralized material. Due to its elevated gold content, this mineralization will be stockpiled initially for future processing pending additional studies to determine an optimal approach for crushing and processing to maximize recoveries.

現在已經定義了大約20,000盎司黃金,平均品位爲0.63 g/t,帶材比率約爲1. 6:1,用於利用當前的滲濾池裝機容量在12個月的時間表內進行開採和裝載。目前的計劃中還包括額外的4500盎司更高品位(約1克/噸)的礦化材料。由於其含金量較高,這種礦化物最初將儲存起來,以備將來處理,等待進一步研究,以確定最佳的破碎和加工方法,以最大限度地提高回收率。

The Company is working to conclude discussions with its mining contractor to prepare their equipment and personnel for the revised operational plan and expansion of mining and stacking activities. Included in the plan are minor modifications to the crushing equipment to help with processing and gold recoveries. Subject to a successful conclusion of the current discussions, the Company anticipates the upgrades to the Santana operations will be phased in over the next month or so which will allow production levels to significantly increase from 2023 levels.

該公司正在努力結束與採礦承包商的討論,爲修訂後的運營計劃和擴大采礦和堆放活動做好設備和人員準備。計劃中包括對破碎設備進行細微改造,以幫助加工和回收黃金。視當前討論的成功結束而定,該公司預計桑塔納業務的升級將在下個月左右分階段實施,這將使產量從2023年的水平大幅提高。

Further details regarding the Company's 2023 full year financial results will be provided prior to the end of April 2024 along with ongoing updates regarding the new plan for the Santana mining operations.

有關公司2023年全年財務業績的更多詳細信息將在2024年4月底之前提供,以及有關桑塔納采礦業務新計劃的持續更新。

Cautionary Statement

警示聲明

The Company made its production decision at the Santana gold mine without having completed a feasibility study demonstrating economic and technical viability. As such, there may be increased uncertainty of achieving planned production levels, estimated recovery of gold, the costs associated with such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.

該公司在桑塔納金礦做出了生產決定,但沒有完成證明經濟和技術可行性的可行性研究。因此,實現計劃產量水平、預計的黃金回收率、與回收相關的成本,包括與開發商業上可開採的礦牀相關的風險增加,都可能增加不確定性。從歷史上看,此類項目發生經濟和技術失敗的風險要高得多。

Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the technical content of this press release under National Instrument 43-101.

Minera Alamos首席執行官工程師達倫·科寧根先生是負責根據國家儀器43-101發佈的本新聞稿技術內容的合格人士。

For Further Information Please Contact:

欲了解更多信息,請聯繫:

Minera Alamos Inc.

Minera Alamos Inc.

Doug Ramshaw, President
Tel: 604-600-4423
Email: dramshaw@mineraalamos.com

道格·拉姆肖,總統
電話:604-600-4423
電子郵件:dramshaw@mineraalamos.com

Victoria Vargas de Szarzynski, VP Investor Relations
Tel: 289-242-3599
Email: vvargas@mineraalamos.com

Victoria Vargas de Sarzynski,投資者關係副總裁
電話:289-242-3599
電子郵件:vvargas@mineraalamos.com

Website:

網站:

About Minera Alamos Inc.

關於 Minera Alamos Inc.

Minera Alamos is a gold production and development Company undergoing the operational start-up of its first gold mine that produced its first gold in October 2021. The Company has a portfolio of high-quality Mexican assets, including the 100%-owned Santana open-pit, heap-leach mine in Sonora that is currently going through its operational ramp up. The 100%-owned Cerro de Oro oxide gold project in northern Zacatecas has considerable past drilling and metallurgical work completed and the proposed mining project is currently being guided through the permitting process by the Company's permitting consultants. The La Fortuna open pit gold project in Durango (100%-owned) has a positive, robust preliminary economic assessment (PEA) completed, and the main Federal permits are in place. Minera Alamos is built around its operating team that together brought three open pit heap leach gold mines into successful production in Mexico over the last 13 years.

Minera Alamos是一家黃金生產和開發公司,其第一座金礦正在投入運營,該金礦於2021年10月生產了第一批黃金。該公司擁有一批高質量的墨西哥資產,包括位於索諾拉州的桑塔納露天堆濾礦,該礦目前正在擴大運營。位於薩卡特卡斯州北部的100%擁有的Cerro de Oro氧化金項目過去已經完成了大量的鑽探和冶金工作,該公司的許可顧問目前正在指導擬議的採礦項目完成許可程序。位於杜蘭戈的La Fortuna露天金礦項目(100%持有)已完成積極而穩健的初步經濟評估(PEA),主要的聯邦許可證已經到位。Minera Alamos是圍繞其運營團隊建立的,在過去的13年中,該團隊共同使墨西哥的三個露天堆浸金礦成功投入生產。

The Company's strategy is to develop very low capex assets while expanding the projects' resources and continuing to pursue complementary strategic acquisitions.

該公司的戰略是開發非常低的資本支出資產,同時擴大項目資源並繼續進行補充性戰略收購。

Caution Regarding Forward-Looking Statements

關於前瞻性陳述的注意事項

This news release may contain forward-looking information and Minera Alamos cautions readers that forward-looking information is based on certain assumptions and risk factors that could cause actual results to differ materially from the expectations of Minera Alamos included in this news release. This news release includes certain "forward-looking statements", which often, but not always, can be identified by the use of words such as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". These statements are based on information currently available to Minera Alamos and Minera Alamos provides no assurance that actual results will meet management's expectations. Forward-looking statements include timing, cost estimates and statements with respect to Minera Alamos' future plans, objectives and goals with respect to the Cerro de Oro gold mine including the receipt of permits and construction timeline, and the satisfaction by the Company of the closing conditions to draw the Remaining Amount. Since forward-looking statements are based on assumptions and address future events and conditions that, by their very nature involve inherent risks and uncertainties. Actual results relating to, among other things, results of exploration, the economics of processing methods, project development, reclamation and capital costs of Minera Alamos' mineral properties, the ability to complete a preliminary economic assessment which supports the technical and economic viability of mineral production could differ materially from those currently anticipated in such statements for many reasons. Minera Alamos' financial condition and prospects could differ materially from those currently anticipated in such statements for many reasons such as: an inability to finance and/or complete an updated resource and reserve estimate and a preliminary economic assessment which supports the technical and economic viability of mineral production; changes in general economic conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation, legislative, environmental and other judicial, regulatory, political and competitive developments; technological and operational difficulties encountered in connection with Minera Alamos' activities; and other matters discussed in this news release and in filings made with securities regulators. This list is not exhaustive of the factors that may affect any of Minera Alamos' forward-looking statements. These and other factors should be considered carefully, and readers should not place undue reliance on Minera Alamos' forward-looking statements. Minera Alamos does not undertake to update any forward-looking statement that may be made from time to time by Minera Alamos or on its behalf, except in accordance with applicable securities laws.

本新聞稿可能包含前瞻性信息,Minera Alamos提醒讀者,前瞻性信息基於某些假設和風險因素,這些假設和風險因素可能導致實際業績與本新聞稿中包含的Minera Alamos的預期存在重大差異。本新聞稿包括某些 “前瞻性陳述”,這些陳述通常可以通過使用 “相信”、“預期”、“預期”、“估計”、“可能”、“可能”、“會”、“將” 或 “計劃” 等詞語來識別。這些聲明基於Minera Alamos目前獲得的信息,而Minera Alamos並不能保證實際業績將達到管理層的預期。前瞻性陳述包括時間、成本估算和有關Minera Alamos對塞羅德奧羅金礦的未來計劃、目標和目標的陳述,包括許可證的獲得和施工時間表,以及公司對提取剩餘金額的截止條件的滿意程度。由於前瞻性陳述基於假設,涉及未來的事件和條件,這些事件和條件本質上涉及固有的風險和不確定性。與勘探結果、加工方法的經濟學、項目開發、開墾和Minera Alamos礦產的資本成本、完成支持礦產生產技術和經濟可行性的初步經濟評估的能力等有關的實際結果可能與此類聲明中目前的預期存在重大差異,原因有很多。Minera Alamos的財務狀況和前景可能與此類聲明中目前的預期存在重大差異,原因有很多,例如:無法融資和/或完成最新的資源和儲量估算以及支持礦產生產技術和經濟可行性的初步經濟評估;金融市場總體經濟狀況和條件的變化;礦產需求和價格的變化;訴訟、立法、環境和其他司法、監管、政治和競爭力發展;與Minera Alamos活動有關的技術和運營困難;以及本新聞稿和向證券監管機構提交的文件中討論的其他事項。此列表並未詳盡列出可能影響Minera Alamos任何前瞻性陳述的因素。應仔細考慮這些因素和其他因素,讀者不應過分依賴Minera Alamos的前瞻性陳述。除非符合適用的證券法,否則Minera Alamos不承諾更新Minera Alamos或其代表可能不時發表的任何前瞻性陳述。

The Company does not have a feasibility study of mineral reserves, demonstrating economic and technical viability for the Santana project, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.

該公司沒有關於礦產儲量的可行性研究,無法證明桑塔納項目的經濟和技術可行性,因此,實現任何特定礦產回收水平或此類回收成本的不確定性可能會增加,包括與開發商業上可開採的礦牀相關的風險增加。從歷史上看,此類項目發生經濟和技術失敗的風險要高得多。

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

多倫多證券交易所及其監管服務提供商(該術語在多倫多證券交易所風險投資交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論