VANCOUVER, BC / ACCESSWIRE / September 26, 2023 / Ximen Mining Corp. (TSX.v:XIM)(FRA:1XMA)(OTCQB:XXMMF) (the "Company" or "Ximen") is pleased to provide an update on activities at its Kenville Gold Mine project in southeastern BC.

溫哥華,BC/ACCESSWIRE/2023年9月26日/西門礦業公司。多倫多證券交易所股票代碼:XIM)(法蘭克福證券交易所股票代碼:1XMA)(OTCQB:XXMMF)(以下簡稱“公司”或“西門”)很高興地向您介紹其位於卑詩省東南部肯維爾金礦專案的最新活動情況。

Kenville Mine: Photos of site showing office buildings, parking and workshop.
肯維爾煤礦:展示辦公樓、停車場和車間的現場照片。

"We are pleased by the significant progress we have achieved to date in finalizing the conditions under our current permits. Once these conditions are satisfactorily met, we will commence development at the Kenville Gold Mine site. In the meantime, as we embrace the virtue of patience, we remain steadfast in advancing the other 100% owned gold assets in our portfolio. "Our strategic efforts position us optimally for the anticipated resurgence in the gold sector, which, with a little luck, will help shed light as we navigate the current market challenges," stated Anderson, CEO of Ximen Mining Corp

西門礦業公司首席執行官安德森表示:“我們很高興在目前的許可條件下,我們在最終敲定條件方面取得了重大進展。一旦這些條件得到滿足,我們將開始在肯維爾金礦基地進行開發。同時,在我們秉持耐心的美德的同時,我們仍然堅定不移地推進我們投資組合中其他100%擁有的黃金資產。我們的戰略努力使我們為預期的黃金行業復甦做好了最佳準備,如果運氣好的話,這將有助於我們在應對當前市場挑戰的過程中看到曙光。”

The Company is steadfastly working with its consultants to complete the engineering studies that are required prior to starting mine development.

該公司正堅定不移地與其顧問合作,以完成在開始礦山開發之前所需的工程研究。

Activities completed:

已完成的活動:

  • Hydrogeological assessment completed and sites selected for two ground water monitoring wells. Proposed sites submitted to regulatory authority for approval.
  • Engineering assessment completed for contact water capture and conveyance for area of new portal and rock dump.
  • Engineering assessment of drainage channel completed. As a result of this study and requirements associated with a required water licence, a new road crossing and new discharge point are now required. The initial design has been completed. An application for an archaeological permit to investigate the new discharge site was submitted.
  • 完成了水文地質評估,並選定了兩口地下水監測井的選址。擬選址已提交監管部門審批。
  • 完成了新洞口和排石場區域接觸集輸水的工程評估。
  • 排水渠工程評估已完成。由於這項研究和與所需供水許可證有關的要求,現在需要一個新的十字路口和新的排汙點。初步設計已經完成。提交了一份考古許可證申請,以調查新的排放地點。

On-going Technical Activities

持續進行的技術活動

  • Waiting on final approval drill monitoring wells and install groundwater monitoring equipment.
  • Finalization and approval of road crossing design. Archaeology permit to be obtained to conduct archeological supervision at new discharge point prior to construction (Estimated 4 months from submission ).
  • Mine water conveyance pumping system engineering design underway to be finished .
  • Complete mine engineering detailed design drawings for mine excavations including drill cut-outs, re-muck cut-outs, safety bays and sumps.
  • Completion of Geotechnical stability assessment of existing mine-site building foundations and mine roads.
  • Completion of Geotechnical design for 2 historic portals and new portal closures.
  • Obtain explosives storage and use permit. Discussion held with regulatory officer indicates site inspection and final use permit to be completed close to commencement of operations.
  • On-going water flow monitoring.
  • 在等待最終批准的情況下,打監測井,安裝地下水監測設備。
  • 道路交叉口設計的最終確定和批准。在施工前(預計自提交之日起4個月內)在新的排洩點進行考古監督,需獲得考古許可證。
  • 正在進行的礦井輸水泵送系統工程設計即將完成。
  • 完整的礦山工程詳細設計圖,包括鑽頭開挖、再挖泥開挖、安全艙和水池。
  • 完成對現有礦場建築地基和礦道的岩土穩定性評估。
  • 完成2個歷史門戶和新門戶關閉的岩土工程設計。
  • 取得爆炸物儲存和使用許可證。與監管人員進行的討論表明,現場檢查和最終使用許可證將在接近開始運營時完成。
  • 持續的水流監測。

The process of completing all the above technical works is required prior to commencing the start of underground development. The Company is fully committed to addressing these items in a timely and efficient manner and is very much looking forward to then starting the underground mine development on the 100% Company owned Kenville Gold Mine no matter the weather or the season.

在開始地下開發之前,必須完成上述所有技術工作。公司完全致力於以及時和高效的方式解決這些問題,並非常期待無論天氣或季節如何,都能在公司100%擁有的肯維爾金礦開始地下礦山開發。

Technical disclosure in this news release has been approved by Dr. Mathew Ball, P.Geo., a Qualified Person as defined by National Instrument 43-101 and VP Exploration for Ximen Mining Corp.

本新聞稿中的技術披露已得到美國國家儀器43-101定義的合格人員、西門礦業公司勘探副總裁馬修·鮑爾博士的批准。

On behalf of the Board of Directors,

我謹代表董事會:

"Christopher R. Anderson"
Christopher R. Anderson,
President, CEO and Director
604 488-3900

克裡斯托弗·R·安德森
克裡斯托弗·R·安德森,
董事首席執行官總裁
604 488-3900

Investor Relations: Sophy Cesar, 604-488-3900, ir@XimenMiningCorp.com

投資者關系部:索菲·塞薩爾604-488-3900電子郵件:ir@XimenMiningCorp.com

About Ximen Mining Corp.

關於西門礦業公司

Ximen Mining Corp. owns 100% interest in three of its precious metal projects located in southern BC. Ximen`s two Gold projects, The Amelia Gold Mine and The Brett Epithermal Gold Project. Ximen also owns the Treasure Mountain Silver Project adjacent to the past producing Huldra Silver Mine. Currently, the Treasure Mountain Silver Project is under an option agreement. The option partner is making annual staged cash and stocks payments as well as funding the development of the project. The company has also acquired control of the Kenville Gold mine near Nelson British Columbia which comes with surface and underground rights, buildings and equipment.

西門礦業擁有位於不列顛哥倫比亞省南部的三個貴金屬專案的100%權益。西門的兩個金礦專案,阿梅利亞金礦和佈雷特淺成熱液金礦專案。西門還擁有寶山銀礦專案,毗鄰過去生產的Huldra銀礦。目前,寶山白銀專案正在簽訂期權協定。期權合作夥伴每年分期支付現金和股票,並為專案的發展提供資金。該公司還獲得了不列顛哥倫比亞省納爾遜附近肯維爾金礦的控制權,該金礦擁有地面和地下的權利、建築和設備。

Ximen is a publicly listed company trading on the TSX Venture Exchange under the symbol XIM, in the USA under the symbol XXMMF, and in Frankfurt, Munich, and Berlin Stock Exchanges in Germany under the symbol 1XMA and WKN with the number as A2JBKL.

西門是一家上市公司,在多倫多證券交易所創業板上市,交易代碼為XIM,在美國交易代碼為XXMMF,在德國法蘭克福、慕尼黑和柏林證券交易所交易代碼為1XMA和WKN,交易代碼為A2JBKL。

This press release contains certain "forward-looking statements" within the meaning of Canadian securities This press release contains certain "forward-looking statements" within the meaning of Canadian securities legislation, including statements regarding the receipt of TSX Venture Exchange approval and the exercise of the Option by Ximen. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct. Forward-looking statements are statements that are not historical facts; they are generally, but not always, identified by the words "expects," "plans," "anticipates," "believes," "intends," "estimates," "projects," "aims," "potential," "goal," "objective," "prospective," and similar expressions, or that events or conditions "will," "would," "may," "can," "could" or "should" occur, or are those statements, which, by their nature, refer to future events. The Company cautions that forward-looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made and they involve a number of risks and uncertainties. Consequently, there can be no assurances that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Except to the extent required by applicable securities laws and the policies of the TSX Venture Exchange, the Company undertakes no obligation to update these forward-looking statements if management's beliefs, estimates or opinions, or other factors, should change. Factors that could cause future results to differ materially from those anticipated in these forward-looking statements include the possibility that the TSX Venture Exchange may not accept the proposed transaction in a timely manner, if at all. The reader is urged to refer to the Company's reports, publicly available through the Canadian Securities Administrators' System for Electronic Document Analysis and Retrieval (SEDAR) at for a more complete discussion of such risk factors and their potential effects.

本新聞稿包含某些加拿大證券定義的“前瞻性聲明”。本新聞稿包含加拿大證券法定義的某些“前瞻性聲明”,包括有關獲得多倫多證券交易所創業板交易所批准和西門行使期權的聲明。儘管該公司相信這樣的陳述是合理的,但它不能保證這種預期將被證明是正確的。前瞻性陳述是指非歷史事實的陳述;它們通常但不總是由以下詞語來標識:“預期”、“計劃”、“預期”、“相信”、“打算”、“估計”、“專案”、“目標”、“潛力”、“目標”、“目標”、“預期”以及類似的表述,或事件或條件“將”、“將”、“可能”、“可以”、“可能”或“應該”發生,或這些陳述,根據它們的性質,指的是未來的事件。該公司提醒,前瞻性陳述是基於公司管理層在陳述發表之日的信念、估計和意見,它們涉及許多風險和不確定因素。因此,不能保證這些陳述將被證明是準確的,實際結果和未來事件可能與此類陳述中預期的大不相同。除非適用的證券法和多倫多證券交易所創業板政策要求,否則如果管理層的信念、估計或意見或其他因素髮生變化,公司沒有義務更新這些前瞻性陳述。可能導致未來結果與這些前瞻性陳述中預期的結果大不相同的因素包括,多倫多證券交易所創業板可能不會及時接受擬議的交易(如果有的話)。建議讀者參考該公司的報告,該報告可通過加拿大證券管理人電子檔案分析和檢索系統(SEDAR)公開獲取,以更全面地討論此類風險因素及其潛在影響。

This press release shall not constitute an offer to sell or the solicitation of an offer to buy any securities, nor shall there be any sale of securities in any state in the United States in which such offer, solicitation or sale would be unlawful.

本新聞稿不應構成出售或徵求購買任何證券的要約,也不應在美國任何州進行任何證券銷售,在這種情況下,此類要約、徵求或出售將是非法的。

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

多倫多證券交易所風險交易所及其監管服務提供商(該術語在多倫多證券交易所的政策中定義)均不對本新聞稿的充分性或準確性承擔責任。

Ximen Mining Corp
888 Dunsmuir Street - Suite 888, Vancouver, B.C., V6C 3K4 Tel: 604-488-3900

西門礦業公司
888 Dunsmuir Street-Suite 888,溫哥華,卑詩省,V6C 3K4電話:604-488-3900

SOURCE: Ximen Mining Corp.

資料來源:西門礦業公司


View source version on accesswire.com:
在Accesswire.com上查看源代碼版本:

譯文內容由第三人軟體翻譯。


以上內容僅用作資訊或教育之目的,不構成與富途相關的任何投資建議。富途竭力但無法保證上述全部內容的真實性、準確性和原創性。
    搶先評論