Erdene Announces Q3 2021 Results and Provides Bayan Khundii Gold Project Update

额尔德尼宣布2021年第三季度业绩并提供巴彦昆迪黄金项目更新

HALIFAX, Nova Scotia, Nov. 10, 2021 (GLOBE NEWSWIRE) -- Erdene Resource Development Corp. (TSX:ERD; MSE:ERDN) ("Erdene" or the "Company") is pleased to announce operating and financial results for the three months ended September 30, 2021, and to provide an update on its Bayan Khundii Gold Project ("Bayan Khundii" or "BK"). This release should be read in conjunction with the Company's Q3 2021 Financial Statements and MD&A, available on the Company's website or SEDAR.

加拿大新斯科舍省哈利法克斯,2021年11月10日(Global Newswire)--Erdene Resource Development Corp.(多伦多证券交易所股票代码:ERD;MSE:ERDN)(以下简称“Erdene”或“公司”)高兴地宣布了截至2021年9月30日的三个月的经营和财务业绩,并提供了其巴彦昆迪金矿项目(“Bayan Khundii”或“BK”)的最新情况。本新闻稿应与公司网站或SEDAR上提供的公司2021年第三季度财务报表和MD&A一起阅读。

Highlights:

重点:


-- Recent exploration results indicate Bayan Khundii, Ulaan, and Dark Horse
Mane are part of the same large-scale, gold mineralized system
-- Intersected some of the thickest intervals of gold mineralization
in the Khundii Gold District to date at the recent South Ulaan
discovery
-- Drill results from follow-up exploration drilling at the Dark
Horse Mane are expected in mid-November
-- Advanced the Bayan Khundii Gold Project
-- Detailed Environmental Impact Assessment (DEIA) accepted by the
Professional Council of the Mongolian Ministry of Environment and
Tourism on October 5
-- Community programs underway following execution of Local
Cooperation Agreement (LCA) with the Bayankhongor Provincial
Government
-- Detailed design and engineering 90% complete, positioning Erdene
to start early works in coming months
-- Closed US$5 million Mongolian Stock Exchange offering on October 8
--近期勘探结果表明,巴彦昆地、乌兰、黑马锰是同一大规模金矿化系统的一部分。--与一些最厚的金矿化区间相交到目前为止在昆地金矿区的南乌兰发现--在黑暗中进行后续勘探钻探的钻探结果马厩预计将于11月中旬开工。--推进巴彦昆地金矿项目--详细环境影响评估(DEIA)蒙古环境和环境部专业理事会10月5日的旅游业--执行地方立法后正在实施的社区计划与巴彦洪郭尔省的合作协议(LCA)政府--详细设计和工程90%完成,定位Erdene在接下来的几个月里开始早期工作10月8日,蒙古国证券交易所完成500万美元的股票发行

Quotes from the Company:

引用该公司的话:

"During the third quarter, we executed upon our two strategic objectives of expanding the Khundii Gold District, while advancing the Bayan Khundii Gold Project towards development," said Peter Akerley, Erdene's President and CEO. "Expansion of the South Ulaan gold prospect demonstrates the scale potential of the Khundii-Ulaan system underlying our Khundii Gold District. Erdene has a 3,000-metre program scheduled for late 2021, in support of our 2 million ounce resource target in 2022."

Erdene总裁兼首席执行官Peter Akerley表示:“在第三季度,我们实现了扩大昆迪金矿区的两个战略目标,同时推动巴彦昆迪金矿项目的发展。”“南乌兰金矿远景的扩大展示了昆迪-乌兰系统在我们昆迪金矿区的规模潜力。额尔丁计划在2021年底实施一个3000米的项目,以支持我们在2022年实现200万盎司的资源目标。”

"We are also steadily progressing Bayan Khundii towards a construction decision, despite the uncertainty created by COVID-19," continued Mr. Akerley. "The Company intends to commence preparatory works in Q4 2021, with full construction ramping up in early 2022. However, the Company is monitoring the impact of COVID-19 on the availability and costs of key inputs and will provide a more fulsome update on schedule and budget in the coming months."

阿克利继续说,“尽管新冠肺炎带来了不确定性,但我们也在稳步推进巴彦昆迪的建设决策。”“本公司计划在2021年第四季度开始准备工作,2022年初全面开工。然而,本公司正在监测新冠肺炎对关键投入的可用性和成本的影响,并将在未来几个月提供更全面的时间表和预算最新情况。”

Q3 2021 Highlights and Subsequent Events:

2021年第三季度亮点和后续活动:

Bayan Khundii Gold Project -- 100% Erdene

巴彦昆地金矿项目--100%额尔德尼


-- Progressed construction readiness activities for the Bayan Khundii Gold
Project
-- Detailed design and engineering for process and non-process
infrastructure ("NPI") 90% complete
-- Regulatory review of detailed drawings well advanced, with eight
facilities fully approved, including those planned during site
establishment
-- Baseline scheduling and procurement advanced ahead of expected
commencement of preparatory works in Q4 2021
-- Advanced regulatory approvals required for mine development
-- Project Detailed Environmental Impact Assessment ("DEIA") accepted
by the Professional Council of the Ministry of Environment and
Tourism on October 5, 2021
-- Continued to carry out local community programs
-- Implemented initial community initiatives under Local Cooperation
Agreement, focused on COVID-19 response measures
-- Completed heavy equipment operation and mine construction training
for local residents
--推进巴彦昆地金矿开工准备工作项目--过程和非过程的详细设计和工程基础设施(“NPI”)完成90%--详细图规范审查工作全面推进,共8项完全批准的设施,包括现场规划的设施设立-基准日程安排和采购提前于预期筹备工作将于2021年第四季度展开-矿山开发需要高级监管审批--接受项目详细环境影响评估(DEIA)由环境和环境部专业理事会2021年10月5日的旅游--继续开展社区建设。-在地方合作下实施初步社区倡议协议,重点是新冠肺炎应对措施--完成重型设备操作和矿山建设培训对于当地居民来说

Exploration

探索


-- Expanded new gold discovery at South Ulaan, 300 metres west of Bayan
Khundii
-- Intersected some of the thickest intervals of gold in the Khundii
Gold District
-- UDH-10 -- 258 metres of 0.98 g/t gold beginning at 92
metres downhole, including 3.77 g/t gold over 40 metres,
starting at 99 metres downhole
-- UDH-14 -- 217 metres of 1.07 g/t gold beginning 188 metres
downhole, including 3.55 g/t gold over 53 metres
-- UDH-15 -- 364 metres of 0.79 g/t gold beginning 97 metres
downhole, including 1.98 g/t gold over 91 metres
-- UDH-19 -- 190 metres of 0.73 g/t gold beginning 82 metres
downhole, including 12.52 g/t gold over 5 metres
-- UDH-21 -- 77 metres of 3.19 g/t gold beginning 115 metres
downhole, including 8.74 g/t gold over 27 metres
-- UDH-22 -- 152 metres of 1.71 g/t gold beginning 85 metres
downhole, including 3.11 g/t gold over 65 metres
-- Follow-up drill program totaling approximately 3,000 metres
planned in Q4 2021
-- Completed follow-up exploration work at the Dark Horse prospect, 3.5 km
north of Bayan Khundii
-- Drilled 34 holes and two hole-extensions totaling 2,286 metres
during the third quarter -- samples are at the SGS lab in
Ulaanbaatar with assay results expected to be reported by
mid-November
-- Continued evaluation and interpretation program including
geophysics, clay mineral analysis, petrography, mineralogy, fluid
inclusion work and 3-D modelling
-在巴彦市以西300米的南乌兰扩大新的金矿发现昆地--与昆底山一些最厚的金矿相交黄金区--UDH-10--258米0.98g/t黄金,从92井下30米,包括40米以上3.77克/吨的黄金,从99米深的井下开始--UDH-14--217米1.07g/t黄金,从188米开始井下,包括超过53米的3.55克/吨黄金--UDH-15--364米0.79克/吨黄金,从97米开始井下,包括91米以上的1.98克/吨黄金--UDH-19--190米0.73克/吨黄金,从82米开始井下,包括超过5米的12.52克/吨黄金--UDH-21--77米3.19克/吨黄金,从115米开始井下,包括超过27米的8.74克/吨黄金--UDH-22--152米1.71克/吨黄金,从85米开始井下,包括超过65米的3.11克/吨黄金-后续钻探计划总计约3000米计划于2021年第四季度--完成了黑马探区的后续勘探工作,全长3.5公里巴彦昆地以北-钻了34个孔和2个延长孔,总长2286米在第三季度--样品在SGS实验室乌兰巴托,化验结果预计将于11月中旬-继续评估和口译计划,包括地球物理、粘土矿物分析、岩石学、矿物学、流体包裹体作功与三维建模

Corporate

公司


-- Closed US$5 million Mongolian Stock Exchange offering on October 8, 2021
-- Received subscriptions from 1,867 institutional and retail
Mongolian investors
-- Offering was 46% over-subscribed and filled pro-rata to orders as
required by Mongolian securities regulations
-- Progressed due diligence for the Bayan Khundii Project financing with
Export Development Canada (EDC) and Mongolian financiers
-- EDC mandate letter contemplates a senior secured debt facility of
up to US$55 million
-- Site visits completed in Q1 2021, and draft technical, and
environmental and social diligence reports received
-- Legal term sheet drafted that will form the basis of the EDC loan
document
-- Due diligence is proceeding in parallel with Mongolian financial
institutions on sub-ordinated debt
-- Advanced technical and strategic review of the Zuun Mod/Khuvyn Khar
molybdenum-copper project
-- RPMGlobal scheduled to deliver updated technical and economic
analysis by mid-November
-- Strategic discussions ongoing to optimize the Project's value
through options including sale, joint venture partnership, or
spinout
-- Recorded a net loss of $1,935,798 for the three months ended September
30, 2021, compared to a net loss of $3,871,340 for the three months ended
September 30, 2020
-- Exploration and evaluation expenditures, including capitalized
expenditures, totaled $3,501,181 for the three months ended
September 30, 2021, compared to $3,547,222 for the period ended
September 30, 2020, as a modest reduction in exploration activity
and lower non-cash share based compensation expenses due to the
timing of performance grants were partially offset by increased
Mining studies costs due to additional engineering effort for
Bayan Khundii and greater Stakeholder relations costs following
the signing of a Local Cooperation Agreement in July 2021
-- Corporate and administrative expenses totaled $565,092 for the
three months ended September 30, 2021, compared to $869,876 for
the three months ended September 30, 2020, primarily due to lower
non-cash share-based compensation expenses as a result of the
timing of performance grants
-蒙古国证券交易所于2021年10月8日完成500万美元的发行-收到1867家机构和零售机构的订阅蒙古投资者-发售超额认购46%,按比例填写订单蒙古国证券法规的要求-对巴彦昆地项目融资的尽职调查取得进展加拿大出口发展局(EDC)和蒙古金融家-EDC授权信考虑一项高级担保债务安排最高5500万美元-2021年第一季度完成实地考察,并起草技术草案,以及收到的环境和社会尽职调查报告-起草的法律条款说明书将构成EDC贷款的基础文档-尽职调查与蒙古金融同步进行次级债务机构-Zuun Mod/Khuvyn Khar的高级技术和战略审查钼铜项目-RPMGlobal计划提供最新的技术和经济11月中旬前的分析--正在进行战略讨论,以优化该项目的价值通过包括销售、合资伙伴关系或旋转式-截至9月的三个月录得1,935,798美元的净亏损2021年3月30日,而截至2021年的三个月净亏损3871,340美元2020年9月30日--勘探和评估支出,包括资本化支出支出,截至三个月共计3,501,181美元2021年9月30日,相比之下,截至2021年9月30日为3547,222美元2020年9月30日,作为勘探活动的适度减少以及降低基于非现金份额的薪酬费用,这是由于绩效补助的时间安排被增加的绩效津贴部分抵消采矿研究成本因额外的工程工作而增加巴彦昆迪和更大的利益相关者关系成本2021年7月签署地方合作协议-公司和行政费用总额为565,092美元截至2021年9月30日的三个月,相比之下,截至2020年9月30日的三个月,主要原因是以现金股份为基础的非现金薪酬支出绩效补助的时间安排

COVID-19 Update

新冠肺炎更新

In late January 2020, the Government of Mongolia instituted limitations on public gatherings, suspended in-person classroom learning, and implemented international border controls in response to COVID-19. The Canadian Government adopted similar measures in March 2020, as did most governments globally during 2020. With the first confirmed cases of community transmission of COVID-19 in November 2020, the Government of Mongolia further restricted the movement of people and the delivery of goods and services. While restrictions were eased in early 2021, precautionary measures were subsequently reintroduced in late Q1 2021, following an increase in the number of reported cases in Mongolia.

2020年1月下旬,蒙古政府对公众集会施加限制,暂停面对面课堂学习,并实施国际边境管制,以回应新冠肺炎。加拿大政府在2020年3月采取了类似的措施,2020年全球大多数政府也采取了类似的措施。随着2020年11月首例新冠肺炎社区传播确诊病例的出现,蒙古国政府进一步限制了人员流动和货物和服务的交付。虽然在2021年初放宽了限制,但随后在蒙古报告的病例数量增加后,于2021年第一季度末重新采取了预防措施。

In March 2021, Bayankhongor Province, where Erdene's projects are located, reported its first confirmed case of community transmission of COVID-19, leading to the imposition of restrictions on the movement of people within and to/from the province. Furthermore, in late June 2021, Bayankhongor province and the sub-province of Shinejinst, the communities in which Erdene operates, imposed states of emergency due to worsening community spread of COVID-19 in the area. Although the Company temporarily halted field work in late June in response, Company staff and contractors returned to site in early August 2021 to commence follow-up exploration work, which has continued without interruption since this date. Additionally, Canadian and International staff and consultants resumed travel to Mongolia in Q3 2021.