Core Scientific announced that CoreWeave has exercised its final infrastructure option under their June 2024 agreement, adding approximately 120MW of critical IT load for GPU hosting. This expansion brings their total contracted HPC infrastructure to 500MW across six sites, with operations expected to begin in H2 2026. The new 12-year contract adds $2.0B to the previously announced $6.7B in projected revenue.The infrastructure modifications will be funded by CoreWeave, with approximately $180M in capital investments credited against hosting payments. The agreement includes two optional 5-year renewal terms. Core Scientific's total power capacity of 1.2 gigawatts will be allocated between 700MW for HPC hosting (delivering 500MW of critical IT load) and 500MW for bitcoin mining operations.CEO Adam Sullivan emphasized significant demand for next-generation compute workloads infrastructure, stating the company is exploring power allocation expansions at existing data centers and evaluating new sites. This expansion positions Core Scientific to become one of the largest publicly traded data center operators in the United States.
Core Scientific announced that CoreWeave has exercised its final infrastructure option under their June 2024 agreement, adding approximately 120MW of critical IT load for GPU hosting. This expansion brings their total contracted HPC infrastructure to 500MW across six sites, with operations expected to begin in H2 2026. The new 12-year contract adds $2.0B to the previously announced $6.7B in projected revenue.The infrastructure modifications will be funded by CoreWeave, with approximately $180M in capital investments credited against hosting payments. The agreement includes two optional 5-year renewal terms. Core Scientific's total power capacity of 1.2 gigawatts will be allocated between 700MW for HPC hosting (delivering 500MW of critical IT load) and 500MW for bitcoin mining operations.CEO Adam Sullivan emphasized significant demand for next-generation compute workloads infrastructure, stating the company is exploring power allocation expansions at existing data centers and evaluating new sites. This expansion positions Core Scientific to become one of the largest publicly traded data center operators in the United States.
Core Scientific宣佈,CoreWeave已經根據他們在2024年6月的協議行使了最後的製造行業選擇,爲GPU託管增加了約120MW的關鍵IT負載。此次擴張使他們在六個地點的合同 HPC 製造行業總計達到500MW,預計將在2026年下半年開始運營。新的爲期12年的合同爲之前宣佈的6700000000美元的營業收入增加了20億。製造行業的改造將由CoreWeave資助,約18000萬的資本投資將被計入托管付款。該協議包括兩個可選的5年續期條款。Core Scientific的總電力容量爲1.2吉瓦,將在用於HPC託管的700MW(提供500MW的關鍵IT負載)和用於比特幣礦業的500MW之間進行分配。首席執行官亞當·沙利文強調了對下一代計算工作負載製造行業的巨大需求,表示公司正在探索現有IDC概念的電力分配擴展,並評估新地點。這次擴張使Core Scientific在成爲美國最大的上市IDC概念運營商之一方面佔據了有利地位。
Core Scientific宣佈,CoreWeave已經根據他們在2024年6月的協議行使了最後的製造行業選擇,爲GPU託管增加了約120MW的關鍵IT負載。此次擴張使他們在六個地點的合同 HPC 製造行業總計達到500MW,預計將在2026年下半年開始運營。新的爲期12年的合同爲之前宣佈的6700000000美元的營業收入增加了20億。製造行業的改造將由CoreWeave資助,約18000萬的資本投資將被計入托管付款。該協議包括兩個可選的5年續期條款。Core Scientific的總電力容量爲1.2吉瓦,將在用於HPC託管的700MW(提供500MW的關鍵IT負載)和用於比特幣礦業的500MW之間進行分配。首席執行官亞當·沙利文強調了對下一代計算工作負載製造行業的巨大需求,表示公司正在探索現有IDC概念的電力分配擴展,並評估新地點。這次擴張使Core Scientific在成爲美國最大的上市IDC概念運營商之一方面佔據了有利地位。