share_log

Press Release: Erdene Announces Q3 2021 Results and Provides Bayan Khundii Gold Project Update

Dow Jones Newswires ·  Nov 10, 2021 22:40

Erdene Announces Q3 2021 Results and Provides Bayan Khundii Gold Project Update

HALIFAX, Nova Scotia, Nov. 10, 2021 (GLOBE NEWSWIRE) -- Erdene Resource Development Corp. (TSX:ERD; MSE:ERDN) ("Erdene" or the "Company") is pleased to announce operating and financial results for the three months ended September 30, 2021, and to provide an update on its Bayan Khundii Gold Project ("Bayan Khundii" or "BK"). This release should be read in conjunction with the Company's Q3 2021 Financial Statements and MD&A, available on the Company's website or SEDAR.

Highlights:


-- Recent exploration results indicate Bayan Khundii, Ulaan, and Dark Horse
Mane are part of the same large-scale, gold mineralized system
-- Intersected some of the thickest intervals of gold mineralization
in the Khundii Gold District to date at the recent South Ulaan
discovery
-- Drill results from follow-up exploration drilling at the Dark
Horse Mane are expected in mid-November
-- Advanced the Bayan Khundii Gold Project
-- Detailed Environmental Impact Assessment (DEIA) accepted by the
Professional Council of the Mongolian Ministry of Environment and
Tourism on October 5
-- Community programs underway following execution of Local
Cooperation Agreement (LCA) with the Bayankhongor Provincial
Government
-- Detailed design and engineering 90% complete, positioning Erdene
to start early works in coming months
-- Closed US$5 million Mongolian Stock Exchange offering on October 8

Quotes from the Company:

"During the third quarter, we executed upon our two strategic objectives of expanding the Khundii Gold District, while advancing the Bayan Khundii Gold Project towards development," said Peter Akerley, Erdene's President and CEO. "Expansion of the South Ulaan gold prospect demonstrates the scale potential of the Khundii-Ulaan system underlying our Khundii Gold District. Erdene has a 3,000-metre program scheduled for late 2021, in support of our 2 million ounce resource target in 2022."

"We are also steadily progressing Bayan Khundii towards a construction decision, despite the uncertainty created by COVID-19," continued Mr. Akerley. "The Company intends to commence preparatory works in Q4 2021, with full construction ramping up in early 2022. However, the Company is monitoring the impact of COVID-19 on the availability and costs of key inputs and will provide a more fulsome update on schedule and budget in the coming months."

Q3 2021 Highlights and Subsequent Events:

Bayan Khundii Gold Project -- 100% Erdene


-- Progressed construction readiness activities for the Bayan Khundii Gold
Project
-- Detailed design and engineering for process and non-process
infrastructure ("NPI") 90% complete
-- Regulatory review of detailed drawings well advanced, with eight
facilities fully approved, including those planned during site
establishment
-- Baseline scheduling and procurement advanced ahead of expected
commencement of preparatory works in Q4 2021
-- Advanced regulatory approvals required for mine development
-- Project Detailed Environmental Impact Assessment ("DEIA") accepted
by the Professional Council of the Ministry of Environment and
Tourism on October 5, 2021
-- Continued to carry out local community programs
-- Implemented initial community initiatives under Local Cooperation
Agreement, focused on COVID-19 response measures
-- Completed heavy equipment operation and mine construction training
for local residents

Exploration


-- Expanded new gold discovery at South Ulaan, 300 metres west of Bayan
Khundii
-- Intersected some of the thickest intervals of gold in the Khundii
Gold District
-- UDH-10 -- 258 metres of 0.98 g/t gold beginning at 92
metres downhole, including 3.77 g/t gold over 40 metres,
starting at 99 metres downhole
-- UDH-14 -- 217 metres of 1.07 g/t gold beginning 188 metres
downhole, including 3.55 g/t gold over 53 metres
-- UDH-15 -- 364 metres of 0.79 g/t gold beginning 97 metres
downhole, including 1.98 g/t gold over 91 metres
-- UDH-19 -- 190 metres of 0.73 g/t gold beginning 82 metres
downhole, including 12.52 g/t gold over 5 metres
-- UDH-21 -- 77 metres of 3.19 g/t gold beginning 115 metres
downhole, including 8.74 g/t gold over 27 metres
-- UDH-22 -- 152 metres of 1.71 g/t gold beginning 85 metres
downhole, including 3.11 g/t gold over 65 metres
-- Follow-up drill program totaling approximately 3,000 metres
planned in Q4 2021
-- Completed follow-up exploration work at the Dark Horse prospect, 3.5 km
north of Bayan Khundii
-- Drilled 34 holes and two hole-extensions totaling 2,286 metres
during the third quarter -- samples are at the SGS lab in
Ulaanbaatar with assay results expected to be reported by
mid-November
-- Continued evaluation and interpretation program including
geophysics, clay mineral analysis, petrography, mineralogy, fluid
inclusion work and 3-D modelling

Corporate


-- Closed US$5 million Mongolian Stock Exchange offering on October 8, 2021
-- Received subscriptions from 1,867 institutional and retail
Mongolian investors
-- Offering was 46% over-subscribed and filled pro-rata to orders as
required by Mongolian securities regulations
-- Progressed due diligence for the Bayan Khundii Project financing with
Export Development Canada (EDC) and Mongolian financiers
-- EDC mandate letter contemplates a senior secured debt facility of
up to US$55 million
-- Site visits completed in Q1 2021, and draft technical, and
environmental and social diligence reports received
-- Legal term sheet drafted that will form the basis of the EDC loan
document
-- Due diligence is proceeding in parallel with Mongolian financial
institutions on sub-ordinated debt
-- Advanced technical and strategic review of the Zuun Mod/Khuvyn Khar
molybdenum-copper project
-- RPMGlobal scheduled to deliver updated technical and economic
analysis by mid-November
-- Strategic discussions ongoing to optimize the Project's value
through options including sale, joint venture partnership, or
spinout
-- Recorded a net loss of $1,935,798 for the three months ended September
30, 2021, compared to a net loss of $3,871,340 for the three months ended
September 30, 2020
-- Exploration and evaluation expenditures, including capitalized
expenditures, totaled $3,501,181 for the three months ended
September 30, 2021, compared to $3,547,222 for the period ended
September 30, 2020, as a modest reduction in exploration activity
and lower non-cash share based compensation expenses due to the
timing of performance grants were partially offset by increased
Mining studies costs due to additional engineering effort for
Bayan Khundii and greater Stakeholder relations costs following
the signing of a Local Cooperation Agreement in July 2021
-- Corporate and administrative expenses totaled $565,092 for the
three months ended September 30, 2021, compared to $869,876 for
the three months ended September 30, 2020, primarily due to lower
non-cash share-based compensation expenses as a result of the
timing of performance grants

COVID-19 Update

In late January 2020, the Government of Mongolia instituted limitations on public gatherings, suspended in-person classroom learning, and implemented international border controls in response to COVID-19. The Canadian Government adopted similar measures in March 2020, as did most governments globally during 2020. With the first confirmed cases of community transmission of COVID-19 in November 2020, the Government of Mongolia further restricted the movement of people and the delivery of goods and services. While restrictions were eased in early 2021, precautionary measures were subsequently reintroduced in late Q1 2021, following an increase in the number of reported cases in Mongolia.

In March 2021, Bayankhongor Province, where Erdene's projects are located, reported its first confirmed case of community transmission of COVID-19, leading to the imposition of restrictions on the movement of people within and to/from the province. Furthermore, in late June 2021, Bayankhongor province and the sub-province of Shinejinst, the communities in which Erdene operates, imposed states of emergency due to worsening community spread of COVID-19 in the area. Although the Company temporarily halted field work in late June in response, Company staff and contractors returned to site in early August 2021 to commence follow-up exploration work, which has continued without interruption since this date. Additionally, Canadian and International staff and consultants resumed travel to Mongolia in Q3 2021.

The above content is for informational or educational purposes only and does not constitute any investment advice related to Futu. Although we strive to ensure the truthfulness, accuracy, and originality of all such content, we cannot guarantee it.
    Write a comment