share_log

中核集团漳州核电1号机组获批装料

Unit 1 of Zhangzhou Nuclear Power Plant of CNNC has received approval for fuel loading.

Breakings ·  Oct 12 21:01

On October 12, the Ministry of Ecology and Environment issued a running permit to Unit 1 of Zhangzhou Nuclear Power Plant, a subsidiary of China National Nuclear Power Corporation under the China National Nuclear Power Corporation. At 15:18, Unit 1 of Zhangzhou Nuclear Power Plant started loading its first batch of nuclear fuel, marking the entry of the unit into the main system with nuclear commissioning phase, laying a solid foundation for subsequent criticality and grid connection.

The translation is provided by third-party software.


The above content is for informational or educational purposes only and does not constitute any investment advice related to Futu. Although we strive to ensure the truthfulness, accuracy, and originality of all such content, we cannot guarantee it.